OPTIMA HEIGHTS BUILDING F
RG-MH-13187 · RERA P52100022656 · Last updated on MahaRERA portal: 29 Jan 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 22 months past the filed date
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
OPTIMA HEIGHTS BUILDING F is a Residential / Group Housing project by AVNEE AND VEDA ASSOCIATES in Pune, Maharashtra, registered with MahaRERA as P52100022656 on 10 Oct 2019. Possession was promised by 30 Dec 2024 and is now 22 months past that date.
At a glance
Project
- NameOPTIMA HEIGHTS BUILDING F
- TypeResidential / Group Housing
- Location
- KESNAND GAON
- KESNAND
- Haveli
- Pune
- 412207
- Pincode412207
- RERA no.P52100022656
- ReraGenie IDRG-MH-13187
Builder
- NameAVNEE AND VEDA ASSOCIATES
- Entity typePartnership
- PartnersVINAY CHUDIWAL, DARSHAN TARUNKUMAR DHUMAVAT, MAHANTESH PALRESHA
- Other registrations2 more →
- Completed2 of 3
- No longer live1 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on10 Oct 2019
- Promised completion30 Dec 2024
- Revised completionNone
- Buildings1 building record
- Documents filed81 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| F BUILDING | NA | 21 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 29 Jan 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
10 of 11 construction stages are filed complete. The stage furthest along is Stilt Floor, at 0%.
F BUILDING: 91% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 29 Jan 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 95% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 20% |
| Street Lighting | Yes | 50% |
| Community Buildings | Yes | 70% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 98% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
Parking filed213
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | MANGESH GOTAL |
| Engineer | Peritus Realty Solutions LLP |
| Engineer | Ravindra Bhosale |
| Chartered Accountant | K G Jhamvar & Co |
| Chartered Accountant | Birla & Co |
| Partner | Role in project |
|---|---|
| AVNEE AND VEDA ASSOCIATES | - |
Litigation declared3
| Case | Court | Status |
|---|---|---|
| 766/2017 | CIVIL JUDGE SENIOR DIVISION PUNE | AWAITING FOR SUMMONS |
| 487/2019 | CIVIL JUDGE SENIOR DIVISION PUNE | WRITTEN STATEMENT |
| 1091/2018 | CIVIL JUDGE SENIOR DIVISION PUNE | PENDING FOR FRAMING OF ISSUES |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 24 Sep 2019 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 1 Oct 2019 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 2 Oct 2019 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 1 Oct 2019Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 21 Jan 2025
Documents filed81
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 81 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 signed June 24_compressed.pdf | 29 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Mar 24_compressed.pdf | 27 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AVA FORM 1 ARCHITECTS CERTIFICATE JAN TO MARCH 24.pdf | 21 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AVA ARCHITECTS CERTIFICATE FROM 1 Q1 24-25.pdf | 21 Jan 2025 |
| Architect’s Certificate on Completion of Project (Form 4)File: AVA FORM 4.pdf | 21 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: AVA ENGINEER CERTIFICATE MARCH -24.pdf | 21 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: AVA ENGINEER CERTIFICATE MARCH -24.pdf | 21 Jan 2025 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: F Bldg completion Certificate.pdf | 21 Jan 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: RERA Form 5 - Veda F Building.pdf | 6 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold or Booked Inventory - Mar 23.pdf | 13 Feb 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold or Booked Inventory - Jun 23.pdf | 13 Feb 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold or Booked Inventory - Sep 23.pdf | 13 Feb 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold or Booked Inventory - Dec 23.pdf | 13 Feb 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architects Certificate Form-1.pdf | 5 Feb 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architech Certificate F Bldg Form-1.pdf | 5 Feb 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architech Certificate F Bldg Form-1.pdf | 5 Feb 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architech Certificate F Bldg Form-1.pdf | 5 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate F Bldg Form 2.pdf | 5 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: AVA - Engineers Certificate.pdf | 5 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: AVA - Engineers Certificate.pdf | 5 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: AVA - Engineers Certificate - Dec-23 - F Bldg.pdf | 5 Feb 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate F Building - Mar 23_compressed.pdf | 5 Feb 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate F Building - Jun 23_compressed.pdf | 5 Feb 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate F Building - Sep 23_compressed.pdf | 5 Feb 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate F Building - Dec 23_compressed.pdf | 5 Feb 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate F Building - Dec 23_compressed.pdf | 5 Feb 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Annual Report on Statement of Accounts.pdf | 10 Nov 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect - Dec 19.pdf | 11 Mar 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Architect - mar 20.pdf | 11 Mar 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Architect - June 20.pdf | 11 Mar 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Architect - Sep 20.pdf | 11 Mar 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Architect - Mar 21.pdf | 11 Mar 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Architect - June 21.pdf | 11 Mar 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Architect - Mar 22.pdf | 11 Mar 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Architect - June 22.pdf | 11 Mar 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Architect - Dec 22.pdf | 11 Mar 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer - Dec 19.pdf | 11 Mar 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer - Mar 20.pdf | 11 Mar 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer - June 20.pdf | 11 Mar 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer - Sep 20.pdf | 11 Mar 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer - Mar 21.pdf | 11 Mar 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer - June 21.pdf | 11 Mar 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer - Mar 22.pdf | 11 Mar 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer - June 22.pdf | 11 Mar 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer - Dec 22.pdf | 11 Mar 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf | 11 Mar 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Dec 22.pdf | 11 Mar 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate - Mar 21.pdf | 11 Mar 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate - June 21.pdf | 11 Mar 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: AVA - F Bldg - Form 5.pdf | 17 Dec 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AVA Architect Certificate-E Bldg Dec-21 Form 1_compressed.pdf | 23 Jul 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate F Bldg Form 2.pdf | 23 Jul 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: F Building _compressed.pdf | 23 Jul 2022 |
| Details of encumbrancesFile: Encumbrance certificate.pdf | 9 Mar 2022 |
| Details of encumbrancesFile: Encumbrance certificate.pdf | 9 Mar 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate_compressed.pdf | 19 Feb 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Certificate_compressed.pdf | 19 Feb 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate - Optima F Building - Sep 20_compressed.pdf | 19 Feb 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Avnee Veda F Building-compressed (1).pdf | 30 Sep 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate - Optima F Building - Compressed.pdf | 12 May 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate - Optima F Building - June 20_compressed.pdf | 12 May 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate - Optima F Building - Sep 20_compressed.pdf | 12 May 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate - Optima F Building - Sep 20_compressed.pdf | 12 May 2021 |
| OtherFile: Final Form 5.pdf | 30 Sep 2020 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Form 1.pdf | 3 Oct 2019 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Form 3.pdf | 3 Oct 2019 |
| Building plan approvalFile: Scan_20191002_124308-compressed.pdf | 2 Oct 2019 |
| Building plan approvalFile: 12-compressed.pdf | 2 Oct 2019 |
| Building plan approvalFile: 11-compressed.pdf | 2 Oct 2019 |
| Building Plan Approval / NA Order for plotted developmentFile: 12-compressed.pdf | 2 Oct 2019 |
| Building Plan Approval / NA Order for plotted developmentFile: 11-compressed.pdf | 2 Oct 2019 |
| Building Plan Approval / NA Order for plotted developmentFile: Scan_20191002_124308-compressed.pdf | 2 Oct 2019 |
| Layout approvalFile: Layout Plan.pdf | 1 Oct 2019 |
| Copy of Layout Approval (in case of layout)File: Layout Plan.pdf | 1 Oct 2019 |
| Commencement Certificates / NA Order for plotted developmentFile: CC.pdf | 1 Oct 2019 |
| Declaration in FORM BFile: Form B.pdf | 1 Oct 2019 |
| PAN CardFile: PAN CARD.pdf | 24 Sep 2019 |
| Copy of the legal title reportFile: TITLE REPORT.pdf | 24 Sep 2019 |
| Details of encumbrancesFile: incumburance certificate_compressed.pdf | 24 Sep 2019 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate F Bldg Form 2.pdf | 24 Sep 2019 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 2 other registrations, which the RERA portal never shows together
- All 81 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep OPTIMA HEIGHTS BUILDING F on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near KESNAND13,700+ in Pune
Yashwin Enchante Phase 2
Vilas Javdekar Infinitee Developers Pvt. L
Godrej Greens
DREAM WORLD LANDMARKS LLP
Yashwin Enchante Phase 1
Vilas Javdekar Infinitee Developers Pvt. L
Kohinoor Kaleido
Intofinity Promoters Private Limited
VIJAY VIHAR
COL. RPS RAWAT
FLAMANTE BY VTP LUXE PHASE 1
INTEGRATED BUSINESS ECOSYSTEM PRIVATE LIMI
Builder: AVNEE AND VEDA ASSOCIATES
AVNEE AND VEDA ASSOCIATES has 3 registrations on MahaRERA, including OPTIMA HEIGHTS B BUILDING and OPTIMA HEIGHTS BUILDING E. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What does it mean that OPTIMA HEIGHTS BUILDING F shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if OPTIMA HEIGHTS BUILDING F is delayed beyond 30 Dec 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of OPTIMA HEIGHTS BUILDING F?
The registered promoter entity is AVNEE AND VEDA ASSOCIATES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in OPTIMA HEIGHTS BUILDING F?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for OPTIMA HEIGHTS BUILDING F?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at OPTIMA HEIGHTS BUILDING F?
The professionals named in the filing: Architect: MANGESH GOTAL; Engineer: Peritus Realty Solutions LLP; Engineer: Ravindra Bhosale; Chartered Accountant: K G Jhamvar & Co; Chartered Accountant: Birla & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in OPTIMA HEIGHTS BUILDING F?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback