Home / Browse projects / KRISHVI ESCAPE
KRISHVI ESCAPE
RG-MH-12709 · RERA P51900023229 · Last updated on MahaRERA portal: 19 Jun 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Litigation declared, 2 cases
Clear
- No complaints on record
- Completion date never moved
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: .Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
KRISHVI ESCAPE is a Mixed project by SHAGUN REALTY in Bhuleshwar, 400002, registered with MahaRERA as P51900023229 on 6 Dec 2019. Possession is promised by 30 Dec 2026. 89 of the 539 units on this registration are recorded sold or booked, and 3 of 11 construction stages are filed complete.
At a glance
Project
- NameKRISHVI ESCAPE
- TypeMixed
- Location
- 4th Floor
- A wing
- Krishvi Escape
- Sitaram Podar Marg
- near Vinay Health Home
- Fanaswadi
- Bhuleshwar
- 400002
- Pincode400002
- RERA no.P51900023229
- ReraGenie IDRG-MH-12709
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on6 Dec 2019
- Promised completion30 Dec 2026
- Revised completionNone
- Buildings1 building record
- Documents filed191 files
Current status
Figures as on 19 Jun 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Krishvi Escape | NA | 60 | 58 | 441 | 80 | 521 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 19 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
3 of 11 construction stages are filed complete across 2 buildings. The stage furthest along is Internal walls, at 80%.
Krishvi Escape59%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 60% |
| Podiums (if any) | 60% |
| Plinth | 100% |
| Stilt Floor | 20% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 80% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 70% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 50% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 10% |
NA Plot Without StructureNot stated
| Activity | Progress |
|---|---|
| Excavation | Not applicable |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | Not applicable |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | Not applicable |
| Sanitary Fittings within the flats / premises | Not applicable |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | Not applicable |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | Not applicable |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | Not applicable |
Progress on shared amenities15
As on 19 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 60% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
Parking filed256
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership1
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| SHAGUN REALTY | - | Mumbai City |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Krishvi Escape | NA | Rs 165.00 cr | Rs 143.65 cr |
Certifying professionals and partners7
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | PARIN SHAH |
| Engineer | JACOB BASTYAW DSOUZA |
| Engineer | SUNIL PATIL |
| Chartered Accountant | NIKHITA MIHIR SHAH |
| Chartered Accountant | GAURAV SATISH RAJPAL |
| Chartered Accountant | DIMPLE SHAH |
| Chartered Accountant | DINESH GANDHI |
| Partner | Role in project |
|---|---|
| SHAGUN REALTY | - |
Litigation declared2
| Case | Court | Status |
|---|---|---|
| 200011/2000/2000 | Small Causes court | Pending |
| 102375/2017/2017 | Bombay City Civil | Pending |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 31 Oct 2019 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 11 Nov 2019 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 10 Jan 2025 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 10 Jan 2025Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 30 Dec 2026
Documents filed191
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 191 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form I Architect certificate krishvi escape march 2026 Signed.pdf | 19 Jun 2026 |
| Withdrawal Update Form 2File: FORM 2 31-03-2026 (KRISHVI ESCAPE) Signed.pdf | 19 Jun 2026 |
| Withdrawal Update Form 3File: FORM 3 31-03-2026 SIGNED.pdf | 19 Jun 2026 |
| Withdrawal Update Form 1File: Form 1 architects certificate Q1 Krishiv Escape June 2025.pdf | 18 Feb 2026 |
| Withdrawal Update Form 1File: Form-1 Krishiv Escape Q2 September 2025 - converted.pdf | 18 Feb 2026 |
| Withdrawal Update Form 1File: Form 1 architects certificate Q3 Krishiv escape Dec 2025.pdf | 18 Feb 2026 |
| Withdrawal Update Form 2File: FORM 2 KRISHVI ESCAPE FOR 2 april to june 25..pdf | 18 Feb 2026 |
| Withdrawal Update Form 2File: FORM 2 KRISHVI ESCAPE FOR 2 july to september 25..pdf | 18 Feb 2026 |
| Withdrawal Update Form 2File: KRISHVI ESCAPE FOR 2 dec 25 (1).pdf | 18 Feb 2026 |
| Withdrawal Update Form 3File: FORM 3 JUNE NEW.pdf | 18 Feb 2026 |
| Withdrawal Update Form 3File: FORM 3 SEPT NEW.pdf | 18 Feb 2026 |
| Withdrawal Update Form 3File: Form 3 Dec Q3.pdf | 18 Feb 2026 |
| Form 5 (FY 2024-2025)File: FORM 5 Kishvi Escape 31-03-2025 (1).pdf | 19 Nov 2025 |
| Form 1File: form 1 2019.pdf | 6 Nov 2025 |
| Form 2File: FORM 2 - MARCH 2019.pdf | 6 Nov 2025 |
| Form 3File: FORM 3 - MARCH 2019.pdf | 6 Nov 2025 |
| Disclosure of Sold and Booked InventoryFile: SOLD - BOOKED INVENTORY 12-05-2023.pdf | 6 Nov 2025 |
| Form 1File: FORM 1 2021.pdf | 6 Nov 2025 |
| Form 2File: FORM 2 - MARCH 2021.pdf | 6 Nov 2025 |
| Form 3File: FORM 3 - 31 MARCH 2021.pdf | 6 Nov 2025 |
| Disclosure of Sold and Booked InventoryFile: SOLD - BOOKED INVENTORY 12-05-2023.pdf | 6 Nov 2025 |
| Form 1File: FORM 1 - 31-12-2021.pdf | 6 Nov 2025 |
| Form 2File: form 2 - DEC 2021.pdf | 6 Nov 2025 |
| Form 3File: FORM 3 - 31 DEC 2021.pdf | 6 Nov 2025 |
| Disclosure of Sold and Booked InventoryFile: SOLD - BOOKED INVENTORY 12-05-2023.pdf | 6 Nov 2025 |
| Form 1File: FORM 1 - 31-3-2022.pdf | 6 Nov 2025 |
| Form 2File: FORM 2 - MARCH 2022.pdf | 6 Nov 2025 |
| Form 3File: FORM 3 - 31 MARCH 2022.pdf | 6 Nov 2025 |
| Disclosure of Sold and Booked InventoryFile: SOLD - BOOKED INVENTORY 12-05-2023.pdf | 6 Nov 2025 |
| Form 1File: FORM 1 - 30-6-2022.pdf | 6 Nov 2025 |
| Form 2File: FORM 2 - JUNE 2022.pdf | 6 Nov 2025 |
| Form 3File: FORM 3 - 30 JUNE 2022.pdf | 6 Nov 2025 |
| Disclosure of Sold and Booked InventoryFile: SOLD - BOOKED INVENTORY 12-05-2023.pdf | 6 Nov 2025 |
| Form 1File: FORM 1 -30-9-2022.pdf | 6 Nov 2025 |
| Form 2File: FORM 2 - SEPT 2022.pdf | 6 Nov 2025 |
| Form 3File: FORM 3 - 30 SEPT 2022.pdf | 6 Nov 2025 |
| Disclosure of Sold and Booked InventoryFile: SOLD - BOOKED INVENTORY 12-05-2023.pdf | 6 Nov 2025 |
| Form 1File: FORM 1 - 31-12-2022.pdf | 6 Nov 2025 |
| Form 2File: FORM 2 - DEC 2022.pdf | 6 Nov 2025 |
| Form 3File: FORM 3 - 31 DEC 2022.pdf | 6 Nov 2025 |
| Disclosure of Sold and Booked InventoryFile: SOLD - BOOKED INVENTORY 12-05-2023.pdf | 6 Nov 2025 |
| Form 1File: FORM 1 - 31-03-2023.pdf | 6 Nov 2025 |
| Form 2File: FORM 2 - MARCH 2023.pdf | 6 Nov 2025 |
| Form 3File: FORM 3 - 31 MARCH 2023.pdf | 6 Nov 2025 |
| Disclosure of Sold and Booked InventoryFile: SOLD - BOOKED INVENTORY 12-05-2023.pdf | 6 Nov 2025 |
| Form 1File: FORM 1 - 31-12-2024.pdf | 6 Nov 2025 |
| Form 2File: FORM 2 - 31-12-2024.pdf | 6 Nov 2025 |
| Form 3File: FORM 3 - 31-12-2024.pdf | 6 Nov 2025 |
| Disclosure of Sold and Booked InventoryFile: SOLD - BOOKED INVENTORY 31-03-2025.pdf | 6 Nov 2025 |
| Form 1File: Form 1 architects certificate MAR 2025 (1).pdf | 6 Nov 2025 |
| Form 2File: KRISHVI ESCAPE FOR 2 MARCH 25.pdf | 6 Nov 2025 |
| Form 3File: FORM 3 31-03-2025 (2 files merged) (1).pdf | 6 Nov 2025 |
| Disclosure of Sold and Booked InventoryFile: SOLD - BOOKED INVENTORY 31-03-2025.pdf | 6 Nov 2025 |
| Form 2A (FY 2019-2020)File: FORM 2A - 2019-2020.pdf | 6 Nov 2025 |
| Form 2A (FY 2020-2021)File: FORM 2A - 2020-2021.pdf | 6 Nov 2025 |
| Form 2A (FY 2021-2022)File: FORM 2A - 2021-2022.pdf | 6 Nov 2025 |
| Form 2A (FY 2023-2024)File: FORM 2A - 2023-2024.pdf | 6 Nov 2025 |
| Form 5 (FY 2023-2024)File: FORM 5 - MARCH 2024.pdf | 6 Nov 2025 |
| Form 5 (FY 2021-2022)File: FORM 5 - 2022.pdf | 6 Nov 2025 |
| Form 5 (FY 2022-2023)File: FORM 5- 2023.pdf | 6 Nov 2025 |
| Form 5 (FY 2019-2020)File: FORM 5 - 2020.pdf | 6 Nov 2025 |
| Form 5 (FY 2020-2021)File: FORM 5 - 2021.pdf | 6 Nov 2025 |
| Disclosure of sold/ booked inventoryFile: KRISHVI ESCAPE.pdf | 3 May 2025 |
| Proforma of Allotment letterFile: ALLOTMENT LETTER draft.pdf | 12 Apr 2025 |
| Proforma of Agreement for saleFile: Draft B - customer agreement.pdf | 12 Apr 2025 |
| Proforma of Allotment letterFile: ALLOTMENT LETTER draft.pdf | 12 Apr 2025 |
| Proforma of Agreement for saleFile: Draft B - customer agreement.pdf | 12 Apr 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 Kishvi Escape 31-03-2024.pdf | 17 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 31-12-24.pdf | 21 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 (2).pdf | 10 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2.pdf | 10 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 final 31-12-2024.pdf | 7 Feb 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: form 2A 2023-24.pdf | 7 Feb 2025 |
| Building plan approval or NA orderFile: Amended Plans Dated 24102024 (5)-1_compressed.pdf | 10 Jan 2025 |
| Building plan approval or NA orderFile: Amended Plans Dated 24102024 (5)-2-4.pdf | 10 Jan 2025 |
| Building plan approval or NA orderFile: Amended Plans Dated 24102024 (5)-5-8.pdf | 10 Jan 2025 |
| Building plan approval or NA orderFile: Amended Plans Dated 24102024 (5)-9-11.pdf | 10 Jan 2025 |
| Building plan approval or NA orderFile: Amended Plans Dated 24102024 (5)-9-11.pdf | 10 Jan 2025 |
| Building plan approval or NA orderFile: Amended Plans Dated 24102024 (5)-12-14.pdf | 10 Jan 2025 |
| Building plan approval or NA orderFile: Amended Plans Dated 24102024 (5)-15-17.pdf | 10 Jan 2025 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 1 condition on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 3 other registrations, which the RERA portal never shows together
- All 191 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep KRISHVI ESCAPE on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bhuleshwar
One Marina
VALENCIA AND MISHAL VENTURES PVT LTD
La Belleza
Qaswa Enterprises
AJMERA DOWNTOWN
ASHJIT REALTIES PVT. LTD.
Prestige Ocean Towers - South
Prestige Projects Private Limited
Prestige Ocean Towers - North
Prestige Projects Private Limited
Sejal Aquarius
Balaji Realty Developers
Builder: SHAGUN REALTY
Shagun Realty has 4 registrations on MahaRERA, including WHITE WOODS and ESSENTIA. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record.
Frequently asked questions
What are my rights if KRISHVI ESCAPE is delayed beyond 30 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of KRISHVI ESCAPE?
The registered promoter entity is SHAGUN REALTY, a partnership as per the filing. Its GSTIN 27ABLFS1536K1ZT can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in KRISHVI ESCAPE?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for KRISHVI ESCAPE?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at KRISHVI ESCAPE?
The professionals named in the filing: Architect: PARIN SHAH; Engineer: JACOB BASTYAW DSOUZA; Engineer: SUNIL PATIL; Chartered Accountant: NIKHITA MIHIR SHAH; Chartered Accountant: GAURAV SATISH RAJPAL; Chartered Accountant: DIMPLE SHAH. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in KRISHVI ESCAPE?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback