OMEGA SAACHEE EMERALD
By SAACHEE & ABHILASH PROMOTERS & DEVELOPERS
RG-MH-73486 · RERA P52100049137 · Last updated on MahaRERA portal: 28 Sep 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 50 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
OMEGA SAACHEE EMERALD is a Residential / Group Housing project by SAACHEE & ABHILASH PROMOTERS & DEVELOPERS in Pune, Maharashtra, registered with MahaRERA as P52100049137 on 1 Feb 2023. Possession is promised by 31 Dec 2028. The completion date has moved by 50 months from the original filing. 0 of the 63 units on this registration are recorded sold or booked, and 2 of 11 construction stages are filed complete.
At a glance
Project
- NameOMEGA SAACHEE EMERALD
- TypeResidential / Group Housing
- Location
- Punawale
- Pimpri Chinchawad (M Corp.)
- Haveli
- Pune
- 411019
- Pincode411019
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100049137
- ReraGenie IDRG-MH-73486
Builder
- NameSAACHEE & ABHILASH PROMOTERS & DEVELOPERS
- Entity typePartnership
- PartnersSuyog Suryakant Chhajed, Sunil Chandrabhan Jadhav
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on1 Feb 2023
- Promised completion31 Dec 2028
- Revised completionRevised to 31 Dec 2028 (originally 31 Oct 2024)
- Buildings1 building record
- Documents filed144 files
Current status
Figures as on 28 Sep 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| OMEGA SAACHEE EMERALD | NA | 9 | 8 | 63 | 0 | 63 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 28 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
2 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 70%.
OMEGA SAACHEE EMERALD: 26% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 70% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 15% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 28 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | No | Not applicable |
| Sewerage (Chamber, Lines, Septic Tank , STP) | No | Not applicable |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 0% |
Parking filed6
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership5
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| Ajith Sudhakaran Panikar | Pimpri Chinchawad (M Corp.) | Pune |
| Shylaja Sudhakaran Panikar | Pimpri Chinchawad (M Corp.) | Pune |
| Sunu Sudhakaran Panikar | Pimpri Chinchawad (M Corp.) | Pune |
| Sujit Sudhakaran Panikar | Pimpri Chinchawad (M Corp.) | Pune |
| SAACHEE & ABHILASH PROMOTERS & DEVELOPERS | Baner | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| OMEGA SAACHEE EMERALD | NA | Rs 10.01 cr | Rs 3.50 cr |
| - | NA | Rs 81.17 lakh | Rs 4.87 lakh |
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Hrushikesh Deore |
| Engineer | Abhilash Jadhav |
| Engineer | Shailesh Jadhav |
| Chartered Accountant | CA Pravin Pise and Associates |
| Chartered Accountant | Vaibhav Bhise |
| Partner | Role in project |
|---|---|
| SAACHEE & ABHILASH PROMOTERS & DEVELOPERS | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThe delay in construction occurred because the landowner carried out road widening without obtaining the necessary permission from the corporation. As a result, the widened portion of the road was not officially handed over to the corporation. This situation likely caused a delay in construction since the corporation could not proceed with development or infrastructure work on the land it did not formally control. Without proper legal transfer and approval, the corporation couldn't manage or complete the construction as planned, leading to setbacks in the overall project timeline.
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 1 Aug 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 11 Jul 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 11 Jul 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 11 Jul 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2028
Documents filed144
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 144 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1 June 25 Sign_compressed.pdf | 28 Sep 2026 |
| Withdrawal Update Form 1File: Form 1 Sep 25_compressed (1).pdf | 28 Sep 2026 |
| Withdrawal Update Form 1File: Form 1 Sep 25_compressed (1).pdf | 28 Sep 2026 |
| Withdrawal Update Form 1File: Form 1 Dec 2025.pdf | 28 Sep 2026 |
| Withdrawal Update Form 1File: Form 1 March 26 Sign.pdf | 28 Sep 2026 |
| Withdrawal Update Form 1File: Form 1 June 26 Sign.pdf | 28 Sep 2026 |
| Withdrawal Update Form 2File: Form 2 June 25 Sign.pdf | 28 Sep 2026 |
| Withdrawal Update Form 2File: Form 2 Sep 2025.pdf | 28 Sep 2026 |
| Withdrawal Update Form 2File: Form 2 Sep 2025.pdf | 28 Sep 2026 |
| Withdrawal Update Form 2File: Form 2 31 dec 2025.pdf | 28 Sep 2026 |
| Withdrawal Update Form 2File: Omega sache Form 2 March 26.pdf | 28 Sep 2026 |
| Withdrawal Update Form 2File: omega saachee Form 2.pdf | 28 Sep 2026 |
| Withdrawal Update Form 3File: Form 3 June 25 Sign.pdf | 28 Sep 2026 |
| Withdrawal Update Form 3File: Form 3 June 25 Sign.pdf | 28 Sep 2026 |
| Withdrawal Update Form 3File: Form 3 Sep 25.pdf | 28 Sep 2026 |
| Withdrawal Update Form 3File: Form 3 Dec 25.pdf | 28 Sep 2026 |
| Withdrawal Update Form 3File: Form 3 March 26 Sign.pdf | 28 Sep 2026 |
| Withdrawal Update Form 3File: Form 3 June 26 Sign.pdf | 28 Sep 2026 |
| Form 2A (FY 2025-2026)File: 2025-26 A.pdf | 28 Sep 2026 |
| Form 2A (FY 2026-2027)File: 2026-27 2A.pdf | 28 Sep 2026 |
| Form 1File: Form 1 (5).pdf | 26 Sep 2026 |
| Form 2File: Form 2.pdf | 26 Sep 2026 |
| Form 3File: Form 3.pdf | 26 Sep 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold.pdf | 26 Sep 2026 |
| Form 5 (FY 2022-2023)File: RERA AUDIT-FY 22-23 (1).pdf | 20 Jun 2026 |
| Form 5 (FY 2023-2024)File: RERA AUDIT -FY 23-24 (1).pdf | 20 Jun 2026 |
| Form 5 (FY 2024-2025)File: F5-OMEGAA SAACHEE(FY 24-25) (2).pdf | 16 Jun 2026 |
| Form 2A (FY 2022-2023)File: form 2A new format 22-23 (1).pdf | 15 Jun 2026 |
| Form 2A (FY 2023-2024)File: form 2A new format 23-24 n (1) (1).pdf | 15 Jun 2026 |
| Form 2A (FY 2024-2025)File: form 2A new format 24-25 n (1).pdf | 15 Jun 2026 |
| Form 1File: Form 1 s.pdf | 1 Dec 2025 |
| Form 2File: Form 2 s.pdf | 1 Dec 2025 |
| Form 3File: Form 3.pdf | 1 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold.pdf | 1 Dec 2025 |
| Form 1File: Form 1 s.pdf | 1 Dec 2025 |
| Form 2File: Form 2.pdf | 1 Dec 2025 |
| Form 3File: Form 3.pdf | 1 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold.pdf | 1 Dec 2025 |
| Form 1File: Form 1 s.pdf | 1 Dec 2025 |
| Form 2File: Form 2.pdf | 1 Dec 2025 |
| Form 3File: Form 3.pdf | 1 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold.pdf | 1 Dec 2025 |
| Form 1File: Form 1 s.pdf | 1 Dec 2025 |
| Form 2File: Form 2.pdf | 1 Dec 2025 |
| Form 3File: Form 3.pdf | 1 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold.pdf | 1 Dec 2025 |
| Form 1File: Form 1 s.pdf | 1 Dec 2025 |
| Form 2File: Form 2.pdf | 1 Dec 2025 |
| Form 3File: Form 3.pdf | 1 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold.pdf | 1 Dec 2025 |
| Form 1File: Form 1s.pdf | 1 Dec 2025 |
| Form 2File: Form 2.pdf | 1 Dec 2025 |
| Form 3File: Form 3.pdf | 1 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold.pdf | 1 Dec 2025 |
| Form 1File: Form 1 s.pdf | 1 Dec 2025 |
| Form 2File: Form 2.pdf | 1 Dec 2025 |
| Form 3File: Form 3.pdf | 1 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold.pdf | 1 Dec 2025 |
| Form 1File: Form 1 s.pdf | 1 Dec 2025 |
| Form 2File: Form 2.pdf | 1 Dec 2025 |
| Form 3File: Form 3.pdf | 1 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold.pdf | 1 Dec 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A - Site Supervisor march 23.pdf | 26 Apr 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: RERA AUDIT -FY 23-24.pdf | 26 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3 (MARCH-25) (1).pdf | 14 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 10 Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf | 11 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: GetUserDocumentFileContent (5).pdf | 11 Apr 2025 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: FORM-3 (MARCH-25).pdf | 11 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1 2023 sept _compressed.pdf | 9 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1 dec 23_compressed.pdf | 9 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1 march 24_compressed.pdf | 9 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1 june 24 _compressed.pdf | 9 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1 sept 24 (1)_compressed.pdf | 9 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1 dec 24 (1)_compressed.pdf | 9 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1 march 25 (2)_compressed.pdf | 9 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1 june 2023_compressed.pdf | 9 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 sept 2023_compressed (1).pdf | 9 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 dec 2024_compressed (1).pdf | 9 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 SEPT-24_compressed (1).pdf | 9 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 june 2024_compressed (1).pdf | 9 Apr 2025 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 144 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep OMEGA SAACHEE EMERALD on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Punawale13,700+ in Pune
Filed coordinates, straight-line distance. 227 registered projects within 2 km.
THE CENTRAL PARK PHASE -I
R RETAIL VENTURES PRIVATE LIMITED
THE CENTRAL PARK PHASE - II
R RETAIL VENTURES PRIVATE LIMITED
SHUBH VEDA Tower E F G and Block 8
UPSQUARE VENTURES LLP
EMPIRE SQUARE PHASE III
EMPIRE PROPERTIES
THE CENTRAL PARK PHASE - III
R RETAIL VENTURES PRIVATE LIMITED
The Central Park Phase- IV Tower D3
R Retail Ventures Private Limited
Builder: SAACHEE & ABHILASH PROMOTERS & DEVELOPERS
SAACHEE & ABHILASH PROMOTERS & DEVELOPERS has 1 registration on MahaRERA, including OMEGA SAACHEE EMERALD. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if OMEGA SAACHEE EMERALD is delayed beyond 31 Dec 2028?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of OMEGA SAACHEE EMERALD?
The registered promoter entity is SAACHEE & ABHILASH PROMOTERS & DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in OMEGA SAACHEE EMERALD?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for OMEGA SAACHEE EMERALD?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at OMEGA SAACHEE EMERALD?
The professionals named in the filing: Architect: Hrushikesh Deore; Engineer: Abhilash Jadhav; Engineer: Shailesh Jadhav; Chartered Accountant: CA Pravin Pise and Associates; Chartered Accountant: Vaibhav Bhise. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in OMEGA SAACHEE EMERALD?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback