Home / Browse projects / Mumbai Suburban, Maharashtra / OM GAUTAM RESIDENCY
OM GAUTAM RESIDENCY
By ATHARVA RISE
RG-MH-52099 · RERA P51800046074 · Last updated on MahaRERA portal: 30 Apr 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 16 months past the filed date
- Completion date moved by 12 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
OM GAUTAM RESIDENCY is a Residential / Group Housing project by ATHARVA RISE in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800046074 on 15 Jun 2022. Possession was promised by 29 Jun 2025 and is now 16 months past that date. The completion date has moved by 12 months from the original filing.
At a glance
Project
- NameOM GAUTAM RESIDENCY
- TypeResidential / Group Housing
- Location
- HAJI BAPU ROAD
- MALAD EAST
- Borivali
- Mumbai Suburban
- 400097
- Pincode400097
- RERA no.P51800046074
- ReraGenie IDRG-MH-52099
Builder
- NameATHARVA RISE
- Entity typePartnership
- PartnersACHALA SHAH, SAUDAMINI SHAH
- Other registrations1 more →
- No longer live1 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on15 Jun 2022
- Promised completion29 Jun 2025
- Revised completionRevised to 29 Jun 2025 (originally 30 Jun 2024)
- Buildings2 building records
- Documents filed47 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| OM GAUTAM RESIDENCY WING A | NA | 11 | 0 | 0 | 0 | 0 |
| OM GAUTAM RESIDENCY WING B | NA | 11 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 30 Apr 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
12 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Staircases, at 90%.
OM GAUTAM RESIDENCY WING A75%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 90% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 90% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 50% |
OM GAUTAM RESIDENCY WING B75%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 90% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 90% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 50% |
Progress on shared amenities15
As on 30 Apr 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 95% |
| Water Supply | No | Not applicable |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 95% |
| Storm Water Drains | Yes | 95% |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | Yes | 95% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed44
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| OM GAUTAM RESIDENCY WING A | 22 | 22 |
| OM GAUTAM RESIDENCY WING B | 22 | 22 |
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| OM GAUTAM CHS LTD | Borivali | Mumbai Suburban |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | DIMENSIONAL CONSULTANTS LLP |
| Engineer | Mr. Nitin M. Nivale |
| Chartered Accountant | NEHALI & CO |
| Partner | Role in project |
|---|---|
| ATHARVA RISE | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDue to shortage of material and labour not able to complete project please grant us extension till 29/06/2025
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 28 Apr 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 28 Apr 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 28 Apr 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 28 Apr 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed47
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 - Architect certificate.pdf | 30 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate.pdf | 30 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate.pdf | 30 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3.pdf | 23 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Inventary Disclouser.pdf | 12 Jun 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 C A Certificate.pdf | 5 Jun 2024 |
| Declaration in FORM BFile: Revised Form B.pdf | 15 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Form 1.pdf | 15 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 04 24.pdf | 13 May 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Site Supervision Form 2A.pdf | 13 May 2024 |
| Disclosure of sold/ booked inventoryFile: Inventory Detail_1.pdf | 13 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf | 8 May 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf | 8 May 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form - 5.pdf | 8 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE (1) (1).pdf | 19 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER.pdf | 19 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Signed CA Certificate Atharva dec'23.pdf | 19 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA Certficate 05 10 2023 form 1.pdf | 16 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer certficate form 2.pdf | 16 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Signed CA Certificate Atharva sep'23 form 3.pdf | 16 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT RERA Certificate.pdf | 12 Jul 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER'S CERTIFICATE.pdf | 12 Jul 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Signed CA Certificate Atharva.pdf | 12 Jul 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf | 26 Apr 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineering Certificate 10 April 2023 (1).pdf | 26 Apr 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: signed CA Certificate Atharva mar'23.pdf | 19 Apr 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect form 1.pdf | 23 Feb 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer form 2.pdf | 23 Feb 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Signed CA Certificate Atharva dec'22 f.pdf | 22 Feb 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 - Architect certificate and Inventory.pdf | 29 Nov 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Engineer Certificate 24 Nov 2022.pdf | 29 Nov 2022 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: RERA Bank Details (1).pdf | 28 Nov 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Signed CA Certificate Atharva Sept'22.pdf | 25 Nov 2022 |
| Proforma of Allotment letterFile: ALLOTMENT LETTER.pdf | 26 May 2022 |
| Declaration about Commencement CertificateFile: CC COVERING LETTER.pdf | 25 May 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ATHARVA FORM 3.pdf | 25 May 2022 |
| Building plan approvalFile: IOD 7494.pdf | 28 Apr 2022 |
| Layout approvalFile: Drawing 7494.pdf | 28 Apr 2022 |
| PAN CardFile: Atharva Rise Pan Card.pdf | 28 Apr 2022 |
| Copy of the legal title reportFile: TITLE REPORT.pdf | 28 Apr 2022 |
| Details of encumbrancesFile: No encumbrance self declaration.pdf | 28 Apr 2022 |
| Copy of Layout Approval (in case of layout)File: Drawing 7494.pdf | 28 Apr 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: IOD 7494.pdf | 28 Apr 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: 2325199_FirstCC_signed.pdf | 28 Apr 2022 |
| Declaration in FORM BFile: Form B Promoter.pdf | 28 Apr 2022 |
| CERSAI detailsFile: CERSAI DECLARATION.pdf | 28 Apr 2022 |
| Proforma of Allotment letterFile: AGREEMENT FOR SALE.pdf | 28 Apr 2022 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration, which the RERA portal never shows together
- All 47 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep OM GAUTAM RESIDENCY on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near MALAD EAST6,700+ in Mumbai Suburban
Alta Monte and Signet
ERA REALTORS PRIVATE LIMITED
MAULI OMKAR
MAULI SAI DEVELOPERS PVT LTD
HIVE 97
AMITY CONSTRUCTIONS
MAULI PRIDE
MAULI SAI DEVELOPERS PVT LTD
Aarambh Phase III by group Satellite
Satellite Developers Private Limited
Sethia Imperial Avenue
Sai Enterprises
See every Mumbai Suburban project, with the district possession charts
Builder: ATHARVA RISE
ATHARVA RISE has 2 registrations on MahaRERA, including OM GAUTAM RESIDENCY and KALPAVRIKSHA. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What does it mean that OM GAUTAM RESIDENCY shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if OM GAUTAM RESIDENCY is delayed beyond 29 Jun 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of OM GAUTAM RESIDENCY?
The registered promoter entity is ATHARVA RISE, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in OM GAUTAM RESIDENCY?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for OM GAUTAM RESIDENCY?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at OM GAUTAM RESIDENCY?
The professionals named in the filing: Architect: DIMENSIONAL CONSULTANTS LLP; Engineer: Mr. Nitin M. Nivale; Chartered Accountant: NEHALI & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in OM GAUTAM RESIDENCY?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.