Home / Browse projects / Mumbai Suburban, Maharashtra / OM GAUTAM RESIDENCY

Registration lapsed No litigation declared Residential / Group Housing project

OM GAUTAM RESIDENCY

By ATHARVA RISE

RG-MH-52099 · RERA P51800046074 · Last updated on MahaRERA portal: 30 Apr 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 16 months past the filed date
  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Jun 2025Possession promised16 months past this date
12 of 22Construction stages doneacross 2 buildings; furthest along: Staircases, 90%
0Complaints at MahaRERAon this registration
Jump to the 47 documents Report an error

OM GAUTAM RESIDENCY is a Residential / Group Housing project by ATHARVA RISE in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800046074 on 15 Jun 2022. Possession was promised by 29 Jun 2025 and is now 16 months past that date. The completion date has moved by 12 months from the original filing.

At a glance

Project

  • NameOM GAUTAM RESIDENCY
  • TypeResidential / Group Housing
  • Location
    • HAJI BAPU ROAD
    • MALAD EAST
    • Borivali
    • Mumbai Suburban
    • 400097
  • Pincode400097
  • RERA no.P51800046074
  • ReraGenie IDRG-MH-52099

Builder

  • NameATHARVA RISE
  • Entity typePartnership
  • PartnersACHALA SHAH, SAUDAMINI SHAH
  • Other registrations1 more →
  • No longer live1 lapsed, de-registered or revoked

Key dates

16 months past promisethis monthRegisteredJun 2022First promiseJun 2024Revised toJun 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on15 Jun 2022
  • Promised completion29 Jun 2025
  • Revised completionRevised to 29 Jun 2025 (originally 30 Jun 2024)
  • Buildings2 building records
  • Documents filed47 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
OM GAUTAM RESIDENCY WING ANA110000
OM GAUTAM RESIDENCY WING BNA110000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 30 Apr 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

12 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Staircases, at 90%.

OM GAUTAM RESIDENCY WING A75%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%
OM GAUTAM RESIDENCY WING B75%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%

Progress on shared amenities15

As on 30 Apr 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes95%
Water SupplyNoNot applicable
Sewerage (Chamber, Lines, Septic Tank , STP)Yes95%
Storm Water DrainsYes95%
Landscaping & Tree PlantingNoNot applicable
Street LightingYes95%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed44

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots44
Closed/Covered44
BuildingClosed/CoveredTotal
OM GAUTAM RESIDENCY WING A2222
OM GAUTAM RESIDENCY WING B2222

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area983 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
OM GAUTAM CHS LTDBorivaliMumbai Suburban

Approvals and building plan

Permissible FSI2905.51
Proposed, not sanctioned2,906 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMALAD EAST

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDIMENSIONAL CONSULTANTS LLP
EngineerMr. Nitin M. Nivale
Chartered AccountantNEHALI & CO
PartnerRole in project
ATHARVA RISE-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800019777Jun 2024 → Jun 2025

Reason as filed by the promoterDue to shortage of material and labour not able to complete project please grant us extension till 29/06/2025

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 28 Apr 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 28 Apr 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 28 Apr 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 28 Apr 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed47

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 - Architect certificate.pdf30 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate.pdf30 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate.pdf30 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3.pdf23 Jan 2025
Disclosure of sold/ booked inventoryFile: Inventary Disclouser.pdf12 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 C A Certificate.pdf5 Jun 2024
Declaration in FORM BFile: Revised Form B.pdf15 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Form 1.pdf15 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 04 24.pdf13 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Site Supervision Form 2A.pdf13 May 2024
Disclosure of sold/ booked inventoryFile: Inventory Detail_1.pdf13 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf8 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf8 May 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form - 5.pdf8 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE (1) (1).pdf19 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER.pdf19 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Signed CA Certificate Atharva dec'23.pdf19 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA Certficate 05 10 2023 form 1.pdf16 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer certficate form 2.pdf16 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Signed CA Certificate Atharva sep'23 form 3.pdf16 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT RERA Certificate.pdf12 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER'S CERTIFICATE.pdf12 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Signed CA Certificate Atharva.pdf12 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf26 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineering Certificate 10 April 2023 (1).pdf26 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: signed CA Certificate Atharva mar'23.pdf19 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect form 1.pdf23 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer form 2.pdf23 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Signed CA Certificate Atharva dec'22 f.pdf22 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 - Architect certificate and Inventory.pdf29 Nov 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Engineer Certificate 24 Nov 2022.pdf29 Nov 2022
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: RERA Bank Details (1).pdf28 Nov 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Signed CA Certificate Atharva Sept'22.pdf25 Nov 2022
Proforma of Allotment letterFile: ALLOTMENT LETTER.pdf26 May 2022
Declaration about Commencement CertificateFile: CC COVERING LETTER.pdf25 May 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ATHARVA FORM 3.pdf25 May 2022
Building plan approvalFile: IOD 7494.pdf28 Apr 2022
Layout approvalFile: Drawing 7494.pdf28 Apr 2022
PAN CardFile: Atharva Rise Pan Card.pdf28 Apr 2022
Copy of the legal title reportFile: TITLE REPORT.pdf28 Apr 2022
Details of encumbrancesFile: No encumbrance self declaration.pdf28 Apr 2022
Copy of Layout Approval (in case of layout)File: Drawing 7494.pdf28 Apr 2022
Building Plan Approval / NA Order for plotted developmentFile: IOD 7494.pdf28 Apr 2022
Commencement Certificates / NA Order for plotted developmentFile: 2325199_FirstCC_signed.pdf28 Apr 2022
Declaration in FORM BFile: Form B Promoter.pdf28 Apr 2022
CERSAI detailsFile: CERSAI DECLARATION.pdf28 Apr 2022
Proforma of Allotment letterFile: AGREEMENT FOR SALE.pdf28 Apr 2022

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 12 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep OM GAUTAM RESIDENCY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near MALAD EAST6,700+ in Mumbai Suburban

Builder: ATHARVA RISE

ATHARVA RISE has 2 registrations on MahaRERA, including OM GAUTAM RESIDENCY and KALPAVRIKSHA. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that OM GAUTAM RESIDENCY shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if OM GAUTAM RESIDENCY is delayed beyond 29 Jun 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of OM GAUTAM RESIDENCY?

The registered promoter entity is ATHARVA RISE, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in OM GAUTAM RESIDENCY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for OM GAUTAM RESIDENCY?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at OM GAUTAM RESIDENCY?

The professionals named in the filing: Architect: DIMENSIONAL CONSULTANTS LLP; Engineer: Mr. Nitin M. Nivale; Chartered Accountant: NEHALI & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in OM GAUTAM RESIDENCY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About OM GAUTAM RESIDENCY. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save OM GAUTAM RESIDENCY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.