Olympeo Riverside - Phase 2
By Olympeo Riverside Projects LLP
RG-MH-08933 · RERA P52000002440 · Last updated on MahaRERA portal: 27 Feb 2023
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 36 months past the filed date
- 2 complaints at MahaRERA
- Completion date moved by 52 months
- 3 extensions taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Olympeo Riverside - Phase 2 is a Residential / Group Housing project by Olympeo Riverside Projects LLP in Raigarh, Maharashtra, registered with MahaRERA as P52000002440 on 1 Aug 2017. Possession was promised by 31 Oct 2023 and is now 36 months past that date. The completion date has moved by 52 months from the original filing. 2 complaints are on record with the regulator.
At a glance
Project
- NameOlympeo Riverside - Phase 2
- TypeResidential / Group Housing
- Location
- Awasare
- Neral
- awsare
- Karjat
- Raigarh
- 410101
- Pincode410101
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52000002440
- ReraGenie IDRG-MH-08933
Builder
- NameOlympeo Riverside Projects LLP
- Entity typePartnership
- PartnerPrabhat Ranjan
- Other registrations2 more →
- Completed1 of 3
- No longer live1 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on1 Aug 2017
- Promised completion31 Oct 2023
- Revised completionRevised to 31 Oct 2023 (originally 30 Jun 2019)
- Buildings2 building records
- Documents filed83 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| C1 | NA | 8 | 0 | 0 | 0 | 0 |
| C2 | NA | 8 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 27 Feb 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
18 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Podiums (if any), at 0%.
C182%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
C282%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 27 Feb 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 100% |
| Open Parking | Yes | 100% |
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Songbird Estates LLP | Navi Mumbai (M Corp.) | Thane |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Architect Vivek Kumar |
| Engineer | Engineering Creations Consultancy Pvt Ltd |
| Partner | Role in project |
|---|---|
| Olympeo Riverside Projects LLP | - |
Extensions applied for3
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThe project is in advance stage of completion and Civil and Infrastructure works have completed/nearing completion. Currently Finishing and Landscaping work is in progress. The project progress was hampered due to NBFC issues started in September 2019. This in turn has impacted sales collection and new sales. On account of prolonged liquidity constraint, construction timeline has got impacted. Though Significant work of project has completed, but we would still need more time to completed pending work and get Occupancy certificate from Competent Authority.
Reason as filed by the promoterProject has been delayed due to COVID 19 and its associated issues such as slow disbursement from bank, job losses at customer end, labour shortage etc.
Reason as filed by the promoterWe have completed Civil and finishing works of both buildings and have applied for OC. Since, OC is taking some time, request you to please provide extension till 31 Oct 23 to enable us get all approval.
Complaints filed with MahaRERA2
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000220914 | KISHOR MANOHAR PENDHARKAR | OLYMPEO RIVERSIDE PROJECTS LLP | 22/04/2022 |
| CC12600632 | Shakeel Ahmed Shaikh | Olympeo Riverside Projects LLP | 03/02/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 7 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 21 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 7 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 28 Mar 2018Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed83
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 83 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Quality Certificate_2021-22.pdf | 27 Feb 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Adobe Scan 25-Feb-2023 (1).pdf | 25 Feb 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Phase 2 Engineers Certificate 31 12 2022.pdf | 25 Feb 2023 |
| Certificates of CA (Form 5)File: Form 5_FY 2018-19_Signed.pdf | 25 Feb 2023 |
| Certificates of CA (Form 5)File: Form 5_FY 2019-20_Signed.pdf | 25 Feb 2023 |
| Certificates of CA (Form 5)File: Form 5_FY 2020-21_Signed.pdf | 25 Feb 2023 |
| Certificates of CA (Form 5)File: Form 5_FY 2021-22_Signed.pdf | 25 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5_FY 2021-22_Signed.pdf | 25 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: ORPLL Audit report 2022-1-4.pdf | 25 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: ORPLL Audit report 2022-5-8.pdf | 25 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: ORPLL Audit report 2022-9-11.pdf | 25 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: ORPLL Audit report 2022-12-14.pdf | 25 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: ORPLL Audit report 2022-15-16.pdf | 25 Feb 2023 |
| Proforma of Agreement for saleFile: Phase 2.pdf | 25 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5_FY 2018-19_Signed.pdf | 24 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5_FY 2019-20_Signed.pdf | 24 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5_FY 2020-21_Signed.pdf | 24 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5_FY 2021-22_Signed.pdf | 24 Feb 2023 |
| CERSAI detailsFile: Asset Based Search 1.pdf | 8 Sep 2022 |
| CERSAI detailsFile: CERSAI_Search_Report_200246671922_For_Asset_Based_Search_08_09_2022_14_51_52_385.pdf | 8 Sep 2022 |
| Details of encumbrances concerned to LegalFile: Phase 2_Encumbrance Certificate.pdf | 20 Aug 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Riverside_Audited Financials 20-21_compressed-1-5.pdf | 20 Aug 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Riverside_Audited Financials 20-21_compressed-6-10.pdf | 20 Aug 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Riverside_Audited Financials 20-21_compressed-11-15.pdf | 20 Aug 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Riverside_Audited Financials 20-21_compressed-16-20.pdf | 20 Aug 2022 |
| Declaration about Commencement CertificateFile: CC Declaration.pdf | 27 Nov 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: QAC_2019-20.pdf | 27 Nov 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: QAC_2020-21.pdf | 27 Nov 2021 |
| Disclosure of sold/ booked inventoryFile: Disclosure of sold units-1-2.pdf | 27 Nov 2021 |
| Disclosure of sold/ booked inventoryFile: Disclosure of sold units-3-4.pdf | 27 Nov 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: 2018-19.pdf | 27 Nov 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: 2018-19_1-1-3.pdf | 27 Nov 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: 2018-19_1-4-6.pdf | 27 Nov 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: 2018-19_1-7-9.pdf | 27 Nov 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: 2018-19_1-10-12.pdf | 27 Nov 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: 2019-20-7-8.pdf | 27 Nov 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: 2019-20-1-2.pdf | 27 Nov 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: 2019-20-3-4.pdf | 27 Nov 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: 2019-20-5-6.pdf | 27 Nov 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: 2019-20-9-10.pdf | 27 Nov 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: 2019-20-11-12.pdf | 27 Nov 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: 2019-20-13-14.pdf | 27 Nov 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: 2019-20-15-16.pdf | 27 Nov 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: 2019-20-17-18.pdf | 27 Nov 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: 2019-20-19.pdf | 27 Nov 2021 |
| Certificates of CA (Form 5)File: Form 5.pdf | 9 Jul 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate_Phase 2_Sep 18.pdf | 15 Apr 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate_Phase 2_Dec 18.pdf | 15 Apr 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate_Phase 2_Mar 19.pdf | 15 Apr 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate - Phase 2.pdf | 8 Feb 2019 |
| Certificates of CA (Form 3)File: RERA Phase 2 Signed June 2018-ilovepdf-compressed.pdf | 8 Feb 2019 |
| Details of encumbrancesFile: Phase 2_Encumbrance Certificate.pdf | 31 Dec 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 ( Architects Certificate ) Phase 2.pdf | 23 Oct 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 ( Architects Certificate ) Phase 2.pdf | 23 Oct 2018 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form---2-(-Vishal-Kumar-)-2.pdf | 23 Oct 2018 |
| Certificates of CA (Form 3)File: Signed-Rera-Certificate-Phase-II-1-3.pdf | 23 Oct 2018 |
| Certificates of CA (Form 3)File: Signed-Rera-Certificate-Phase-II-3-6-ilovepdf-compressed.pdf | 23 Oct 2018 |
| Certificates of CA (Form 3)File: Signed-Rera-Certificate-Phase-II-7-8.pdf | 23 Oct 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate - Phase 2.pdf | 31 May 2018 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate - Phase 2.pdf | 31 May 2018 |
| Certificates of CA (Form 3)File: Olympeo Riverside Project LLP-Phase-II-ilovepdf-compressed.pdf | 31 May 2018 |
| Commencement Certificates / NA Order for plotted developmentFile: NA-ORDER-07-11-2015-1-3.pdf | 28 Mar 2018 |
| Commencement Certificates / NA Order for plotted developmentFile: NA-ORDER-07-11-2015-4-6.pdf | 28 Mar 2018 |
| Commencement Certificates / NA Order for plotted developmentFile: Grampanchyat-NOC-1-5.pdf | 28 Mar 2018 |
| Commencement Certificates / NA Order for plotted developmentFile: Grampanchyat-NOC-6-10.pdf | 28 Mar 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificate Phase 2.pdf | 16 Nov 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificate Phase 2.pdf | 16 Nov 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Vishal Kumar (Engineers Certificate) 2.pdf | 16 Nov 2017 |
| Certificates of CA (Form 3)File: phase 2.pdf | 16 Nov 2017 |
| Layout approvalFile: Approval Drawings.pdf | 21 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: Approval Drawings.pdf | 21 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Phase 2.pdf | 21 Jul 2017 |
| Certificates of CA (Form 3)File: Phase 2 Signed scan copy-compressed.pdf | 21 Jul 2017 |
| Proforma of Allotment letterFile: Phase 2.pdf | 21 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Phase 2.pdf | 18 Jul 2017 |
| Declaration in FORM BFile: Form B - Phase 2.pdf | 12 Jul 2017 |
| Building plan approvalFile: NA-ORDER-07-11-2015-1-3.pdf | 7 Jul 2017 |
| Building plan approvalFile: NA-ORDER-07-11-2015-4-6.pdf | 7 Jul 2017 |
| PAN CardFile: Pan card - ORPLLP.pdf | 7 Jul 2017 |
| Copy of the legal title reportFile: Dsk Legal December 20,2014.pdf | 7 Jul 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Raigarh
Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.
Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 2 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 83 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep Olympeo Riverside - Phase 2 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Neral5,900+ in Raigarh
Filed coordinates, straight-line distance. 17 registered projects within 2 km.
ForeverLand
HOABL IMPACTUM LAND PRIVATE LIMITED
Chitrapatjanak Dadasaheb Phalke Township - Pha
Anukarati Homes Pvt Ltd
Olympeo Neo City
PRIZTINE INFRA LLP
DEEPJYOTI CITY
DeepJyoti Infra
VISION AARAMBH
M/s Vision Aarambh ( AOP )
Olympeo Riverside - Phase 3
Olympeo Riverside Projects LLP
See every Raigarh project, with the district possession charts
Builder: Olympeo Riverside Projects LLP
Olympeo Riverside Projects LLP has 3 registrations on MahaRERA, including Olympeo Riverside - Phase 1 and Olympeo Riverside - Phase 2. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.
Frequently asked questions
What does it mean that Olympeo Riverside - Phase 2 shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Olympeo Riverside - Phase 2 is delayed beyond 31 Oct 2023?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Olympeo Riverside - Phase 2?
The registered promoter entity is Olympeo Riverside Projects LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Olympeo Riverside - Phase 2?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Olympeo Riverside - Phase 2?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Olympeo Riverside - Phase 2?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Olympeo Riverside - Phase 2?
The professionals named in the filing: Architect: Architect Vivek Kumar; Engineer: Engineering Creations Consultancy Pvt Ltd. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Olympeo Riverside - Phase 2?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.