Home / Browse projects / NYATI ERA II

Completed Litigation declared Others project

NYATI ERA II

By NYATI CONSTRUCTION PRIVATE LIMITED

RG-MH-27617 · RERA P52100035037 · Last updated on MahaRERA portal: 30 Sep 2025

Source: official MahaRERA filing

Red flags

  • Litigation declared, 4 cases
  • Completion date moved by 6 months
  • 1 extension taken

Clear

  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: .
Sep 2025Possession promisedregistration recorded completed
1 of 11Construction stages donefurthest along: Excavation, 98%
164 of 177Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 77 documents Report an error

NYATI ERA II is a Others project by NYATI CONSTRUCTION PRIVATE LIMITED in DHANORI, 411015, registered with MahaRERA as P52100035037 on 29 Apr 2022. The registration is recorded completed; possession was promised by 30 Sep 2025. The completion date has moved by 6 months from the original filing. 13 of the 177 units on this registration are recorded sold or booked, and 1 of 11 construction stages are filed complete.

At a glance

Project

  • NameNYATI ERA II
  • TypeOthers
  • Location
    • DHANORI LOHEGAON ROAD
    • DHANORI
    • 411015
  • Pincode411015
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100035037
  • ReraGenie IDRG-MH-27617

Builder

  • NameNYATI CONSTRUCTION PRIVATE LIMITED
  • Entity typeCompany
  • CINU45202MH1996PTC102517
  • GSTIN27AAACN6421D1ZU
  • CIN and GSTIN are from this promoter's other MahaRERA registrations. This project's own filing does not repeat them.
  • DirectorsPRANAV NITIN NYATI, NITIN DWARKADAS NYATI
  • Other registrations5 more →
  • Completed2 of 6

Key dates

this monthRegisteredApr 2022First promiseMar 2025Revised toSep 2025Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on29 Apr 2022
  • Promised completion30 Sep 2025
  • Revised completionRevised to 30 Sep 2025 (originally 31 Mar 2025)
  • Buildings1 building record
  • Documents filed77 files

Current status

7%13 of 177 units booked
62.1%Work done, per cost certificate

Figures as on 30 Sep 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Wing TNA131212057177

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 30 Sep 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

1 of 11 construction stages are filed complete. The stage furthest along is Excavation, at 98%.

Wing T: 59% average across the applicable activities

ActivityProgress
Excavation98%
Basement (if any)98%
Podiums (if any)0%
Plinth98%
Stilt Floor100%
Slabs of Super Structure95%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises47%
Sanitary Fittings within the flats / premises23%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks23%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.8%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.63%

Progress on shared amenities15

As on 30 Sep 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area3,830 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on7 Jul 2025
LandownerVillageDistrict
COOJI ALIAS COOVERJI DADY KATRAKPune (CB)Pune

Approvals and building plan

Sanctioning authorityPune Municipal Corporation
Permissible FSI9457.61
Proposed, not sanctioned9,458 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchKHARADI PUNE
Estimated costRs 13.39 cr
Cost incurredRs 8.31 cr
Work done62.07%
BuildingWingEstimatedIncurred
Wing TNARs 11.17 crRs 8.31 cr
-NARs 2.22 cr-

Certifying professionals and partners8

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSHIRISH DASNURKAR
ArchitectSANJEEV MUKUND MEHTA
EngineerACHYUT WATVE
EngineerAMOL SHITOLE
EngineerSANDEEP HIROLIKAR
EngineerVishwanath Dhande
Chartered AccountantNICKY HIRANAND MILANI
Chartered AccountantVipin Gujarathi & Associates
PartnerRole in project
NYATI CONSTRUCTION PRIVATE LIMITED-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100028021Mar 2025 → Sep 2025

Reason as filed by the promoterWe have applied for Occupation Certificate, but since it will take time to receive and the date of completion is nearing, we are applying for the Extension Application for 6 months. 119 Units are MHADA Units which will be handed over to MHADA, 58 Units are of the Developer of which 13 units have been sold/booked. We have obtained consent from 7 allottees out of these 13 allottees.

Litigation declared4

CaseCourtStatus
1046/2023CIVIL JUDGE SENIOR DIVISION PUNEOngoing
721/2024CIVIL JUDGE SENIOR DIVISIONOngoing
608/2020CIVIL JUDGE SENIOR DIVISONOngoing
1867/2024CIVIL JUDGE SENIOR DIVISIONOngoing

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 7 Oct 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 6 Mar 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 11 Mar 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 6 Mar 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed77

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupational CertificateFile: Nyati ERA 1st Part OC 08-08-2025.pdf30 Sep 2025
Occupational CertificateFile: Nyati Era 2nd PART OC Commercial 26-09-2025.pdf30 Sep 2025
Form 2A (FY 2024-2025)File: Nyati Era II Form 2A 2024-2025.pdf26 Sep 2025
Form 5 (FY 2024-2025)File: Nyati Era-II-Form 5.pdf4 Sep 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf11 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A.pdf11 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf9 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf7 Apr 2025
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD UNSOLD INVENTORY.pdf7 Apr 2025
Declaration in FORM BFile: FORM B.pdf27 Mar 2025
Layout approvalFile: Sanction Layout.pdf6 Mar 2025
Layout approvalFile: Sanction Layout.pdf6 Mar 2025
Copy of Layout Approval (in case of layout)File: Sanction Layout.pdf6 Mar 2025
Copy of Layout Approval (in case of layout)File: Sanction Layout.pdf6 Mar 2025
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf6 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf16 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf7 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf7 Jan 2025
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD UNSOLD INVENTORY.pdf7 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf11 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf11 Nov 2024
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD UNSOLD INVENTORY.pdf29 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf19 Oct 2024
Copy of the legal title reportFile: TITLE CERTIFICATE 03102024.pdf7 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Nyati Era II - Form 5.pdf7 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.PDF17 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf12 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf8 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf8 Jul 2024
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD UNSOLD INVENTORY.pdf8 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A.pdf18 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: NCPL Form 3 - Era II_11zon.pdf11 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf8 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf8 Apr 2024
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD UNSOLD INVENTORY.pdf8 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf16 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf16 Jan 2024
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD UNSOLD INVENTORY.pdf16 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf16 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf19 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf16 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf16 Oct 2023
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD UNSOLD INVENTORY.pdf16 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Nyati Era II.pdf30 Sep 2023
Declaration about Commencement CertificateFile: Declaration about CC Era II 17042023.pdf27 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A.pdf4 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A.pdf25 Jan 2023
Proforma of Allotment letterFile: NYATI ERA II UNIT AGREEMENT SHOPS.pdf28 Apr 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate.pdf27 Apr 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate.pdf26 Apr 2022
Declaration about Commencement CertificateFile: Declaration about CC.pdf16 Mar 2022
Declaration in FORM BFile: Form B NCPL.pdf16 Mar 2022
Details of encumbrancesFile: Self Declaration.pdf15 Mar 2022
CERSAI detailsFile: CERSAI UNDERTAKING.pdf15 Mar 2022
PAN CardFile: NCPL - PAN.pdf14 Mar 2022
Copy of the legal title reportFile: Legal Title Report Dt 14122021.pdf14 Mar 2022
Layout approvalFile: Sanction Layou BP.pdf11 Mar 2022
Layout approvalFile: Sancton Layout DP.pdf11 Mar 2022
Layout approvalFile: Parking Layout.pdf11 Mar 2022
Building plan approvalFile: Wing T 1 st floor.pdf11 Mar 2022
Building plan approvalFile: Wing T 7th 11th Plan.pdf11 Mar 2022
Building plan approvalFile: Wing T Basement.pdf11 Mar 2022
Building plan approvalFile: Wing T Elevation Section.pdf11 Mar 2022
Building plan approvalFile: Wing T Ground Floor.pdf11 Mar 2022
Building plan approvalFile: Wing T MHADA Plans.pdf11 Mar 2022
Copy of Layout Approval (in case of layout)File: Sanction Layou BP.pdf11 Mar 2022
Copy of Layout Approval (in case of layout)File: Sancton Layout DP.pdf11 Mar 2022
Copy of Layout Approval (in case of layout)File: Parking Layout.pdf11 Mar 2022
Building Plan Approval / NA Order for plotted developmentFile: Wing T 1 st floor.pdf11 Mar 2022
Building Plan Approval / NA Order for plotted developmentFile: Wing T 7th 11th Plan.pdf11 Mar 2022
Building Plan Approval / NA Order for plotted developmentFile: Wing T Basement.pdf11 Mar 2022
Building Plan Approval / NA Order for plotted developmentFile: Wing T Elevation Section.pdf11 Mar 2022
Building Plan Approval / NA Order for plotted developmentFile: Wing T Ground Floor.pdf11 Mar 2022
Building Plan Approval / NA Order for plotted developmentFile: Wing T MHADA Plans.pdf11 Mar 2022
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate BP.pdf11 Mar 2022
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate DP.pdf11 Mar 2022
CERSAI detailsFile: CERSAI Search Report.pdf11 Mar 2022

Keep NYATI ERA II on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near DHANORI

2 kmNYATI ERA IICompleted 36Lapsed / revoked 11Other 22Dot size: filed unitsN

Filed coordinates, straight-line distance. 69 registered projects within 2 km.

Builder: NYATI CONSTRUCTION PRIVATE LIMITED

NYATI CONSTRUCTION PRIVATE LIMITED has 6 registrations on MahaRERA, including NYATI ERA I and NYATI ERA II. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 5 of its registrations. Read the full track record.

Frequently asked questions

What are my rights if NYATI ERA II is delayed beyond 30 Sep 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of NYATI ERA II?

The registered promoter entity is NYATI CONSTRUCTION PRIVATE LIMITED, a company as per the filing. Its CIN U45202MH1996PTC102517 and GSTIN 27AAACN6421D1ZU can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in NYATI ERA II?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for NYATI ERA II?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at NYATI ERA II?

The professionals named in the filing: Architect: SHIRISH DASNURKAR; Architect: SANJEEV MUKUND MEHTA; Engineer: ACHYUT WATVE; Engineer: AMOL SHITOLE; Engineer: SANDEEP HIROLIKAR; Engineer: Vishwanath Dhande. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in NYATI ERA II?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About NYATI ERA II. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save NYATI ERA II to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.