Red flags

  • Registration lapsed
  • Possession 5 months past the filed date
  • Completion date moved by 17 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
May 2026Possession promised5 months past this date
3 of 11Construction stages donefurthest along: Basement (if any), 80%
0Complaints at MahaRERAon this registration
Jump to the 54 documents Report an error

Nishant Co -Op Hsg Society is a Residential / Group Housing project by Shri Laxmi Narayan Properties LLP in Pune, Maharashtra, registered with MahaRERA as P52100051130 on 30 May 2023. Possession was promised by 30 May 2026 and is now 5 months past that date. The completion date has moved by 17 months from the original filing.

At a glance

Project

  • NameNishant Co -Op Hsg Society
  • TypeResidential / Group Housing
  • Location
    • Bibwewadi
    • Bibwewadi -Munjeri
    • Gultekdi
    • Gultekadi
    • Haveli
    • Pune
    • 411037
  • Pincode411037
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100051130
  • ReraGenie IDRG-MH-79118

Builder

  • NameShri Laxmi Narayan Properties LLP
  • Entity typePartnership
  • LLPINAAS-2556
  • GSTIN27AEDFS3957F1ZT
  • LLPIN and GSTIN are from this promoter's other MahaRERA registrations. This project's own filing does not repeat them.
  • PartnersAbhishek Shrinath Bhimale, Prasad Yashwant Bhimale
  • Other registrations8 more →
  • Completed3 of 9
  • No longer live1 lapsed, de-registered or revoked

Key dates

5 months past promisethis monthRegisteredMay 2023First promiseDec 2024Revised toMay 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on30 May 2023
  • Promised completion30 May 2026
  • Revised completionRevised to 30 May 2026 (originally 1 Dec 2024)
  • Buildings1 building record
  • Documents filed54 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Wing ANA70000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 11 Feb 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 80%.

Wing A: 63% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)80%
Podiums (if any)100%
Plinth80%
Stilt Floor80%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks40%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 11 Feb 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)NoNot applicable
Storm Water DrainsYes0%
Landscaping & Tree PlantingNoNot applicable
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed34

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots34
Closed/Covered14
Open Space20

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area507 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
Nishant Co -Op Housing Society LimitedMANJARI BkPune

Approvals and building plan

Sanctioning authorityPune Municipal Corporation
Permissible FSI1474.53
Proposed, not sanctioned1,175 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMadiwale Colony 193 Phulwala Chowk, Guruwar Peth, Pune 411042

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectStudio 55
EngineerShubhlaxmi Engineers & Contractors
Chartered AccountantMRKS And Company
PartnerRole in project
Shri Laxmi Narayan Properties LLP-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100025695Dec 2024 → May 2026

Reason as filed by the promoterWe apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to issues with procurement, unforeseen site conditions, coordination challenges and temporary financial constraints. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. We will apply for the Occupancy Certificate once the remaining work is finished. We are closely monitoring progress and taking all necessary steps to ensure timely completion. Given the circumstances, we kindly request an extension until 30-05-2026 to c

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 3 May 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 27 Dec 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 27 Dec 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 3 May 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed54

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form-5 Nishant FY 2023-24_11zon.pdf11 Feb 2025
Declaration in FORM BFile: FORM -B.pdf10 Feb 2025
Disclosure of sold/ booked inventoryFile: Circular 29.pdf10 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2 Q3 NISHANT_compressed.pdf28 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3 Q3 NISHANT_compressed.pdf21 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Nishant CHS as on Dec 2024.pdf18 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A - Nishant CHS as on December 2024.pdf18 Jan 2025
Layout approvalFile: Sanction Plan N 1_11zon.pdf27 Dec 2024
Building plan approvalFile: Sanction Plan N 2.pdf27 Dec 2024
Copy of Layout Approval (in case of layout)File: Sanction Plan N 1_11zon.pdf27 Dec 2024
Building Plan Approval / NA Order for plotted developmentFile: Sanction Plan N 2.pdf27 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Nishant CHS as on Sep 2024.pdf18 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Nishant CHS as on Sep 2024.pdf18 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Nishant CHS as on Sep 2024.pdf18 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Nishant as on June 2024.pdf14 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM-1 Q1(N).pdf12 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2 (NISHANT) Q1 24-25_compressed.pdf12 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Nishant as on MArch 2024_compressed.pdf20 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 Nishant as on March 2024.pdf28 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 Nishant as on MArch 2024.pdf28 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 3 Architect’s Certificate of Percentage of Completion of Work (Form 1) (4).pdf20 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 4 Engineer’s Certificate on Cost Incurred on Project (Form 2) (7).pdf20 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: JJJ.pdf20 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 - Nishant CHS as on Sep 2023.pdf12 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 - Nishant CHS as on Dec 2023.pdf12 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 - Nishant CHS as on June 2023.pdf12 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 - Nishant CHS as on Sep 2023.pdf12 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 - Nishant CHS as on Dec 2023.pdf12 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 - Nishant CHS as on Sep 23.pdf8 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 - Nishant CHS as on Dec 23.pdf8 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 Q1.pdf8 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 - Nishant CHS as on Jun 23.pdf8 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 - Nishant CHS as on Dec 23.pdf8 Feb 2024
Details of encumbrances concerned to FinanceFile: 1 a Details of encumbrances concerned to Finance (1).pdf12 May 2023
Details of encumbrances concerned to FinanceFile: 2 b Details of encumbrances concerned to Legal (1).pdf12 May 2023
Details of encumbrances concerned to LegalFile: 1 a Details of encumbrances concerned to Finance (1).pdf12 May 2023
Details of encumbrances concerned to LegalFile: 2 b Details of encumbrances concerned to Legal (1).pdf12 May 2023
Declaration about Commencement CertificateFile: 1 Declaration about Commencement Certificate (3).pdf12 May 2023
Declaration in FORM BFile: 1 Declaration in FORM B (3).pdf12 May 2023
CERSAI detailsFile: 1 CERSAI details (1).pdf12 May 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Nishant Coop society_11zon.pdf12 May 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: 1 Disclosure of Interest in Other Real Estate Organizations (3).pdf12 May 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow12 May 2023
Deviation Report with respect to Allotment letterFile: 1 Deviation Report with respect to Allotment letter (3).pdf12 May 2023
Deviation Report with respect to model copy of AgreementFile: 1 Deviation Report with respect to model copy of Agreement (2).pdf12 May 2023
Layout approvalFile: 1 Copy of Layout Approval (in case of layout) (4).pdf9 May 2023
Copy of Layout Approval (in case of layout)File: 1 Copy of Layout Approval (in case of layout) (4).pdf9 May 2023
Proforma of Agreement for saleFile: AFS_Nishant Co Op Housing Society_ Shri Laxmi Narayan Properties LLP_08052023.pdf9 May 2023
Proforma of Allotment letterFile: Allotment Letter_Nishant Co Op Housing Society_Shri Laxminarayan Properties LLP_08052023.p9 May 2023
Building plan approvalFile: Sanaction Plan 2_11zon.pdf3 May 2023
PAN CardFile: SLNP PAN.pdf3 May 2023
Copy of the legal title reportFile: Title Report _Nishant.pdf3 May 2023
Building Plan Approval / NA Order for plotted developmentFile: Sanaction Plan 2_11zon.pdf3 May 2023
Commencement Certificates / NA Order for plotted developmentFile: Commencment Certificate.pdf3 May 2023

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 17 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Nishant Co -Op Hsg Society on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Bibwewadi -Munjeri, Gultekdi13,700+ in Pune

2 kmNishant Co -Op Hsg SocieCompleted 33Lapsed / revoked 18Other 62Dot size: filed unitsN

Filed coordinates, straight-line distance. 113 registered projects within 2 km.

Builder: Shri Laxmi Narayan Properties LLP

SHRI LAXMI NARAYAN PROPERTIES LLP has 9 registrations on MahaRERA, including RAMRAJ and Gautam. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that Nishant Co -Op Hsg Society shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Nishant Co -Op Hsg Society is delayed beyond 30 May 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Nishant Co -Op Hsg Society?

The registered promoter entity is Shri Laxmi Narayan Properties LLP, a partnership as per the filing. Its LLPIN AAS-2556 and GSTIN 27AEDFS3957F1ZT can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Nishant Co -Op Hsg Society?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Nishant Co -Op Hsg Society?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Nishant Co -Op Hsg Society?

The professionals named in the filing: Architect: Studio 55; Engineer: Shubhlaxmi Engineers & Contractors; Chartered Accountant: MRKS And Company. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Nishant Co -Op Hsg Society?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Nishant Co -Op Hsg Society. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Nishant Co -Op Hsg Society to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.