Home / Browse projects / Satara, Maharashtra / Nisarg Pushp
Nisarg Pushp
By Pushp Construction through Sandeep panditrao Konde & Renuka Sandeep Konde
RG-MH-17111 · RERA P52700027885 · Last updated on MahaRERA portal: 30 Jul 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 24 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Satara registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Nisarg Pushp is a Residential / Group Housing project by Pushp Construction through Sandeep panditrao Konde & Renuka Sandeep Konde in Satara, Maharashtra, registered with MahaRERA as P52700027885 on 10 Jan 2021. Possession is promised by 31 Mar 2028. The completion date has moved by 24 months from the original filing. 47 of the 68 units on this registration are recorded sold or booked, and 1 of 11 construction stages are filed complete.
At a glance
Project
- NameNisarg Pushp
- TypeResidential / Group Housing
- Location
- Nisarg Colony
- Near Jarandwshar Naka
- Karanje Tarf Satara (CT)
- Satara
- 415002
- Pincode415002
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52700027885
- ReraGenie IDRG-MH-17111
Builder
- NamePushp Construction through Sandeep panditrao Konde & Renuka Sandeep Konde
- Entity typePartnership
- GSTIN27AAXFP3370M1ZE
- PartnerRenuka Sandeep Konde
- Declared earlier projects1 →
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on10 Jan 2021
- Promised completion31 Mar 2028
- Revised completionRevised to 31 Mar 2028 (originally 4 Mar 2026)
- Buildings2 building records
- Documents filed116 files
Current status
Figures as on 30 Jul 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Nisarg pushp | NA | 1 | 1 | 40 | 0 | 40 |
| Nisarg Pushp Phase 2 | NA | 8 | 7 | 28 | 0 | 28 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 30 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
1 of 11 construction stages are filed complete across 2 buildings. The stage furthest along is Basement (if any), at 0%.
Nisarg pushp9%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Nisarg Pushp Phase 2Not stated
| Activity | Progress |
|---|---|
| Excavation | Not applicable |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | Not applicable |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | Not applicable |
| Sanitary Fittings within the flats / premises | Not applicable |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | Not applicable |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | Not applicable |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | Not applicable |
Progress on shared amenities15
As on 30 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed128
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Podiums / Upper Parking Floor | Total |
|---|---|---|---|
| Nisarg pushp | 78 | 0 | 78 |
| Nisarg Pushp Phase 2 | 0 | 50 | 50 |
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Nisarg Pushp Phase 2 | NA | Rs 5.23 cr | Rs 3.38 cr |
| Nisarg pushp | NA | Rs 3.93 cr | Rs 3.93 cr |
| - | NA | Rs 1.19 cr | Rs 69.01 lakh |
Certifying professionals and partners6
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | shree mahajani |
| Engineer | dattatrya kirdat |
| Engineer | ARSHAD NASIRKHAN DANGE |
| Chartered Accountant | abhimanyu sharma |
| Chartered Accountant | Jivan Vijaysinh Jagtap |
| Chartered Accountant | Harshvardhan Jaideep Jadhav |
| Partner | Role in project |
|---|---|
| Pushp Construction through Sandeep panditrao Konde & Renuka Sandeep Konde | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterWe are planning to add one more Phase to the above Project
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 29 Dec 2020 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 1 Feb 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 2 Feb 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 29 Dec 2020Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Mar 2028
Documents filed116
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 116 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: arc.pdf | 30 Jul 2026 |
| Withdrawal Update Form 2File: FORM 2_0001.pdf | 30 Jul 2026 |
| Withdrawal Update Form 3File: FORM 3_0001.pdf | 30 Jul 2026 |
| Withdrawal Update Form 1File: arc.pdf | 22 May 2026 |
| Withdrawal Update Form 1File: arc.pdf | 22 May 2026 |
| Withdrawal Update Form 1File: arc.pdf | 22 May 2026 |
| Withdrawal Update Form 1File: arc.pdf | 22 May 2026 |
| Withdrawal Update Form 1File: arc.pdf | 22 May 2026 |
| Withdrawal Update Form 2File: FORM 2.pdf | 22 May 2026 |
| Withdrawal Update Form 2File: FORM 2.pdf | 22 May 2026 |
| Withdrawal Update Form 2File: FORM 2.pdf | 22 May 2026 |
| Withdrawal Update Form 2File: FORM 2.pdf | 22 May 2026 |
| Withdrawal Update Form 2File: FORM 2.pdf | 22 May 2026 |
| Withdrawal Update Form 3File: FORM 3_.pdf | 22 May 2026 |
| Withdrawal Update Form 3File: FORM 3.pdf | 22 May 2026 |
| Withdrawal Update Form 3File: FORM 3.pdf | 22 May 2026 |
| Withdrawal Update Form 3File: FORM 3_.pdf | 22 May 2026 |
| Withdrawal Update Form 3File: FORM 3.pdf | 22 May 2026 |
| Form 1File: FY 2021-22 Q2.pdf | 9 May 2026 |
| Form 2File: FY 21-22 Q2_0001.pdf | 9 May 2026 |
| Form 3File: 2021-22 Q2.pdf | 9 May 2026 |
| Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD UNSOLD INVENTORY 21-22 Q2.pdf | 9 May 2026 |
| Form 1File: FY 2021-22 Q3.pdf | 9 May 2026 |
| Form 2File: FY 21-22 Q3_0001_0001.pdf | 9 May 2026 |
| Form 3File: 2021-22 Q3.pdf | 9 May 2026 |
| Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD UNSOLD INVENTORY 21-22 Q3.pdf | 9 May 2026 |
| Form 1File: FY 2021-22 Q4.pdf | 9 May 2026 |
| Form 2File: FY 21-22 Q4_0001.pdf | 9 May 2026 |
| Form 3File: 2021-22 Q4.pdf | 9 May 2026 |
| Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD UNSOLD INVENTORY 21-22 Q4.pdf | 9 May 2026 |
| Form 1File: FY 2022-23 Q1.pdf | 9 May 2026 |
| Form 2File: FY 22-23 Q1_0001.pdf | 9 May 2026 |
| Form 3File: 2022-23 Q1.pdf | 9 May 2026 |
| Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD UNSOLD INVENTORY.pdf | 9 May 2026 |
| Form 1File: FY 2022-23 Q2.pdf | 9 May 2026 |
| Form 2File: FY 22-23 Q2_0001.pdf | 9 May 2026 |
| Form 3File: 2022-23 Q2.pdf | 9 May 2026 |
| Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD UNSOLD INVENTORY.pdf | 9 May 2026 |
| Form 1File: FY 2022-23 Q3.pdf | 9 May 2026 |
| Form 2File: FY 22-23 Q3_0001.pdf | 9 May 2026 |
| Form 3File: 2022-23 Q3.pdf | 9 May 2026 |
| Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD UNSOLD INVENTORY.pdf | 9 May 2026 |
| Form 1File: FY 2022-23 Q4.pdf | 9 May 2026 |
| Form 2File: FY 22-23 Q4_0001.pdf | 9 May 2026 |
| Form 3File: 2022-23 Q4.pdf | 9 May 2026 |
| Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD UNSOLD INVENTORYq4.pdf | 9 May 2026 |
| Form 1File: FY 2023-24 Q1.pdf | 9 May 2026 |
| Form 2File: FY 23-24 Q1_0001.pdf | 9 May 2026 |
| Form 3File: FY 2023-24 Q1.pdf | 9 May 2026 |
| Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD UNSOLD INVENTORY Q1.pdf | 9 May 2026 |
| Form 1File: FY 2023-24 Q2.pdf | 9 May 2026 |
| Form 2File: FY 23-24 Q2_0001.pdf | 9 May 2026 |
| Form 3File: FY 2023-24 Q2.pdf | 9 May 2026 |
| Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD UNSOLD INVENTORYQ2.pdf | 9 May 2026 |
| Form 1File: FY 2023-24 Q3.pdf | 9 May 2026 |
| Form 2File: FY 23-24 Q3_0001.pdf | 9 May 2026 |
| Form 3File: FY 2023-24 Q3.pdf | 9 May 2026 |
| Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD UNSOLD INVENTORY Q3.pdf | 9 May 2026 |
| Form 1File: FY 2023-24 Q4.pdf | 9 May 2026 |
| Form 2File: FY 23-24 Q4_0001.pdf | 9 May 2026 |
| Form 3File: FY 2023-24 Q4.pdf | 9 May 2026 |
| Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD UNSOLD INVENTORYQ4_page-0001.pdf | 9 May 2026 |
| Form 1File: FY 2024-25 Q1.pdf | 9 May 2026 |
| Form 2File: FY 24-25 Q1_0001.pdf | 9 May 2026 |
| Form 3File: FY 2024-25 Q1.pdf | 9 May 2026 |
| Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD UNSOLD INVENTORYQ1_page-0001.pdf | 9 May 2026 |
| Form 1File: FY 2024-25 Q2.pdf | 9 May 2026 |
| Form 2File: FY 24-25 Q2_0001.pdf | 9 May 2026 |
| Form 3File: FY 2024-25 Q2.pdf | 9 May 2026 |
| Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD UNSOLD INVENTORY.pdf | 9 May 2026 |
| Form 1File: FY 2024-25 Q3.pdf | 9 May 2026 |
| Form 2File: FY 24-25 Q3_0001.pdf | 9 May 2026 |
| Form 3File: FY 2024-25 Q3.pdf | 9 May 2026 |
| Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD UNSOLD INVENTORY..pdf | 9 May 2026 |
| Form 1File: FY 2024-25 Q4.pdf | 9 May 2026 |
| Form 2File: FY 24-25 Q4_0001.pdf | 9 May 2026 |
| Form 3File: FY 2024-25 Q4.pdf | 9 May 2026 |
| Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD UNSOLD INVENTORY..pdf | 9 May 2026 |
| Form 1File: FY 2020-21 Q4.pdf | 8 May 2026 |
| Form 2File: FY 2020-21-Q4_0001.pdf | 8 May 2026 |
Promoter's earlier projects2
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| Pushp Developers | Satara | 2 | Completed | Mar 2020 | Jun 2019 |
| Pushp Developers | satara | 2 | Completed | Nov 2019 | Late, Nov 2020 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Satara
Computed across the 1,100+ Satara projects on ReraGenie, from their own filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 116 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Nisarg Pushp on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Near Jarandwshar Naka1,100+ in Satara
Filed coordinates, straight-line distance. 32 registered projects within 2 km.
Sukhodayam Villas
M/s Ultra Urban Greene Realty LLP
YASHWANT ELITE
RAHULDEV PROMOTERS SATARA
KRISHNAKUNJ VIHAR PHASE-3
Pooja Shridhar Kangralkar
SHATAKSHI TOWER
VISHAL DILIP PAWAR
SHREE VIHAR
M/s SHREE SAIDARSHAN DEVELOPERS
SHIVSAMARTH RESIDENCY
MS BHOSALE AND NALAWADE
See every Satara project, with the district possession charts
Builder: Pushp Construction through Sandeep panditrao Konde & Renuka Sandeep Konde
Pushp Construction through Sandeep panditrao Konde & Renuka Sandeep Konde has 1 registration on MahaRERA, including Nisarg Pushp. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Satara district page.
Frequently asked questions
What are my rights if Nisarg Pushp is delayed beyond 31 Mar 2028?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Nisarg Pushp?
The registered promoter entity is Pushp Construction through Sandeep panditrao Konde & Renuka Sandeep Konde, a partnership as per the filing. Its GSTIN 27AAXFP3370M1ZE can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Nisarg Pushp?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Nisarg Pushp?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Nisarg Pushp?
The professionals named in the filing: Architect: shree mahajani; Engineer: dattatrya kirdat; Engineer: ARSHAD NASIRKHAN DANGE; Chartered Accountant: abhimanyu sharma; Chartered Accountant: Jivan Vijaysinh Jagtap; Chartered Accountant: Harshvardhan Jaideep Jadhav. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Nisarg Pushp?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback