Home / Browse projects / Nirvana Part I

Registration lapsed No litigation declared Residential / Group Housing project

Nirvana Part I

By RUNWAL DEVELOPERS LTD

RG-MH-87431 · RERA P51900010100 · Last updated on MahaRERA portal: 12 Dec 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 22 months past the filed date
  • 3 complaints at MahaRERA
  • Completion date moved by 24 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: .
Dec 2024Possession promised22 months past this date
9 of 11Construction stages donefurthest along: Installation of Lifts, 95%
3Complaints at MahaRERAon this registration
Jump to the 203 documents Report an error

Nirvana Part I is a Residential / Group Housing project by RUNWAL DEVELOPERS LTD in 400012, registered with MahaRERA as P51900010100 on 24 Aug 2017. Possession was promised by 30 Dec 2024 and is now 22 months past that date. The completion date has moved by 24 months from the original filing. 3 complaints are on record with the regulator.

At a glance

Project

  • NameNirvana Part I
  • TypeResidential / Group Housing
  • Location
    • G. D. Ambekar Road
    • 400012
  • Pincode400012
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51900010100
  • ReraGenie IDRG-MH-87431

Builder

  • NameRUNWAL DEVELOPERS LTD
  • Entity typeCompany
  • CINU70100MH1988PTC046631
  • GSTIN27AAACR0395J1Z8
  • DirectorPallavi Matkari
  • Other registrations3 more →
  • No longer live3 lapsed, de-registered or revoked
  • Declared earlier projects2 →

Key dates

22 months past promisethis monthRegisteredAug 2017First promiseDec 2022Revised toDec 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on24 Aug 2017
  • Promised completion30 Dec 2024
  • Revised completionRevised to 30 Dec 2024 (originally 31 Dec 2022)
  • Buildings1 building record
  • Documents filed203 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Nirvana Part INA660000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 12 Dec 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 95%.

Nirvana Part I: 99% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%

Progress on shared amenities15

As on 12 Dec 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes20%
Water SupplyYes30%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes60%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes70%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed273

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots273
Closed/Covered273

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area5,046 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
ACCORD ESTATES PVT LTD-Mumbai City

Approvals and building plan

Sanctioning authorityMCGM
Permissible FSI22700.79
Proposed, not sanctioned16,796 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchShop NO 9, 10 , Mary Land Corner, Sion , Mumbai 400022

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPallavi Matkari
ArchitectNinad Dinkar Mhaskar
EngineerSanjay Singh
Chartered AccountantS P Gunjal & Associates
Chartered AccountantSinghi & Co.
PartnerRole in project
RUNWAL DEVELOPERS LTD-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51900005735Dec 2022 → Dec 2023

Reason as filed by the promoterWe, have registered our project ““NIRVANA PART I” (hereinafter referred to as “the said Project) on the RERA Website bearing Registration No. 51900010100 on 24/08/2017. The “Revised Proposed Date of Completion” while registering the said Project was mentioned on RERA Website as 31/12/2022 for the completion of the project. We submit that the construction of the said Project is in progress. However, there is delay in issuing approvals from concerned authorities for further construction of the said Project and therefore, we anticipate delay for completing the construction of the said Project fro

Litigation declared4

CaseCourtStatus
129/2010BOMBAY CITY CIVIL COURTPENDING
3079/2013BOMBAY CITY CIVIL COURTPENDING
3596/2013BOMBAY CITY CIVIL COURTPENDING
75/2010SMALL CAUSES COURT AT BOMBAYDECREED

Complaints filed with MahaRERA3

Case no.ComplainantRespondentFiled
CC006000000141194Mrs. Neelam Sahebrao SatreM/s Accord Estates (P) Limited10/10/2019
CC006000000195166Hina ShahRunwal Realty Pvt Ltd07/12/2020
CC12500574Azimulla Yusuf SayyedRUNWAL DEVELOPERS PVT LTD19/02/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 24 Oct 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 15 Oct 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 13 Jan 2025

Documents filed203

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 203 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2024-2025)File: Form 2A.pdf12 Dec 2025
Form 5 (FY 2024-2025)File: Form 5.pdf3 Dec 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf5 May 2025
Disclosure of sold/ booked inventoryFile: Sold unsold Inventory.pdf5 May 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf18 Apr 2025
Certificates of CA (Form 3)File: Form 3.pdf18 Apr 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5.pdf15 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Dec 2024.pdf6 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Dec 2024.pdf27 Jan 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold Dec 2024.pdf23 Jan 2025
Certificates of CA (Form 3)File: Form 3 Dec 2024.pdf20 Jan 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Nirvana OC 10 01 2025.pdf13 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A.pdf17 Dec 2024
Building plan approvalFile: Amended letter 19 08 2024.pdf24 Oct 2024
Building plan approvalFile: Amended Plan 19 08 2024 Plans 1 to 7.pdf24 Oct 2024
Building plan approvalFile: Amended Plan 19 08 2024 Plans 8 to 14.pdf24 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Sep 2024.pdf24 Oct 2024
Building Plan Approval (IOD)File: Amended letter 19 08 2024.pdf24 Oct 2024
Building Plan Approval (IOD)File: Amended Plan 19 08 2024 Plans 1 to 7.pdf24 Oct 2024
Building Plan Approval (IOD)File: Amended Plan 19 08 2024 Plans 8 to 14.pdf24 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Sep 2024.pdf22 Oct 2024
Declaration about Commencement CertificateFile: NIRVANA Part 1 Declaration about CC RDPL 30 09 2024.pdf22 Oct 2024
Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory Sep 2024.pdf21 Oct 2024
Certificates of CA (Form 3)File: From 3 Spe 2024.pdf18 Oct 2024
Commencement Certificates / NA Order for plotted developmentFile: Nirwana FullCC dated 19 09 24.pdf15 Oct 2024
Details of encumbrancesFile: Declaration on encumbrances-Nirvana 08 08 2024.pdf8 Aug 2024
Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory June 2024.pdf23 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 June 2024.pdf22 Jul 2024
Certificates of CA (Form 3)File: Form 3 June 2024.pdf22 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 June 2024.pdf19 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: From 2 March 2024.pdf29 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: From 1 March 2024.pdf22 Apr 2024
Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory 2024.pdf19 Apr 2024
Certificates of CA (Form 3)File: Form 3 March 2024.pdf19 Apr 2024
Proforma of Agreement for saleFile: Revised Nirvana AFS 11 03 2021.pdf5 Feb 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf23 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A.pdf23 Jan 2024
Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory.pdf23 Jan 2024
Certificates of CA (Form 3)File: Form 3 compressed.pdf23 Jan 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf19 Jan 2024
OtherFile: self declaratio on revised area sharing 21 11 2023.pdf21 Nov 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5.pdf16 Nov 2023
OtherFile: Self Declaration of Accord for its Flats.pdf6 Nov 2023
Disclosure of sold/ booked inventoryFile: Sold Unsold.pdf30 Oct 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Nirvana 30-09-2023.pdf23 Oct 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Nirvana 30 09 2023.pdf23 Oct 2023
Certificates of CA (Form 3)File: Form 3 Nirvana Part I 30 Sept 2023.pdf20 Oct 2023
Home Buyer /Allottee Grievance Redressal CellFile: Declaration Nirvana Part I.pdf20 Oct 2023
Disclosure of sold/ booked inventoryFile: Sold Unsold list of Nirvana as on 30 06 2023.pdf21 Jul 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 ARCHITECT CERTIFICATE 30 06 2023.pdf20 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Nirvana as on 30 June 2023.pdf20 Jul 2023
Certificates of CA (Form 3)File: Form 3 Nirvana Part 1 as on 30 06 2023.pdf20 Jul 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 ARCHITECT CERTIFICATE 30 06 2023.pdf17 Jul 2023
Disclosure of sold/ booked inventoryFile: Sold Unsold Nirvana 31 03 2023.pdf21 Apr 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Nirvanan Part I 31 03 2023.pdf20 Apr 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Nirvana Engineer Certificate 31 03 2023.pdf20 Apr 2023
Certificates of CA (Form 3)File: Form 3 CA certificate for 31032023 Nirvana.pdf19 Apr 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: NIRVANA_ARCHITECT CERTIFICATE_31-12-2022 Form 1.pdf27 Jan 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Nirvana Engineers Certificate.pdf27 Jan 2023
Disclosure of sold/ booked inventoryFile: Nirvana sold and unsold.pdf27 Jan 2023
Certificates of CA (Form 3)File: Form 3 Nirvana.pdf27 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 Nirvana.pdf17 Dec 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Nirvana Sep 2022.pdf19 Oct 2022
Disclosure of sold/ booked inventoryFile: sold unsold Nirvana Sep 2022.pdf19 Oct 2022
Certificates of CA (Form 3)File: Form 3 Nirvana Sep 2022.pdf19 Oct 2022
Commencement Certificates / NA Order for plotted developmentFile: CC 12 10 2022.pdf14 Oct 2022
Commencement Certificates / NA Order for plotted developmentFile: Nirvana_FurtherCC_signed.pdf11 Oct 2022
Declaration about Commencement CertificateFile: NIRVANA Part 1_Declaration about CC_RDPL_30092022.pdf10 Oct 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: NIRVANA_ARCHITECT CERTIFICATE_FOR RERA_30-09-2022.pdf10 Oct 2022
CERSAI detailsFile: Nirvana Part I.pdf18 Jul 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Eng Cer Nirvana 30062022.pdf16 Jul 2022
Certificates of CA (Form 3)File: Nirvana Part 1 Form 3 30 06 2022.pdf16 Jul 2022
Declaration about Commencement CertificateFile: Nirvana CC declaration 30062022.pdf15 Jul 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Nirvana 30062022.pdf15 Jul 2022
Disclosure of sold/ booked inventoryFile: Sold Unsold Nirvana T-1 30062022.pdf15 Jul 2022
Certificates of CA (Form 5)File: Nirvana - Form 5 - Mar 18.pdf1 Jul 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Engg Certificate - Sep-20 - Nirvana_PM.pdf29 Jun 2022
Disclosure of sold/ booked inventoryFile: Nirvana 30062021.pdf21 Jun 2022
Disclosure of sold/ booked inventoryFile: Nirvana 30092021.pdf21 Jun 2022
Disclosure of sold/ booked inventoryFile: Nirvana 31122021.pdf21 Jun 2022

Keep Nirvana Part I on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near this project

2 kmNirvana Part ICompleted 27Lapsed / revoked 11Other 14Dot size: filed unitsN

Filed coordinates, straight-line distance. 52 registered projects within 2 km.

Builder: RUNWAL DEVELOPERS LTD

Runwal Developers Ltd has 4 registrations on MahaRERA, including RUNWAL ANTHURIUM - VALENTINE and Nirvana Part I. Its filings disclose 2 earlier MahaRERA projects: declares 0 of 2 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record.

Frequently asked questions

What does it mean that Nirvana Part I shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Nirvana Part I is delayed beyond 30 Dec 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Nirvana Part I?

The registered promoter entity is RUNWAL DEVELOPERS LTD, a company as per the filing. Its CIN U70100MH1988PTC046631 and GSTIN 27AAACR0395J1Z8 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Nirvana Part I?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Nirvana Part I?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Nirvana Part I?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Nirvana Part I?

The professionals named in the filing: Architect: Pallavi Matkari; Architect: Ninad Dinkar Mhaskar; Engineer: Sanjay Singh; Chartered Accountant: S P Gunjal & Associates; Chartered Accountant: Singhi & Co.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Nirvana Part I?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Nirvana Part I. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Nirvana Part I to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.