Home / Browse projects / Mumbai Suburban, Maharashtra / Nirvana
Nirvana
By Siddhivinayak Developers Kurar
RG-MH-53169 · RERA P51800033952 · Last updated on MahaRERA portal: 13 Aug 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 24 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Nirvana is a Others project by Siddhivinayak Developers Kurar in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800033952 on 14 Mar 2022. Possession is promised by 31 Dec 2027. The completion date has moved by 24 months from the original filing. 158 of the 212 units on this registration are recorded sold or booked, and 6 of 22 construction stages are filed complete.
At a glance
Project
- NameNirvana
- TypeOthers
- Location
- Hawa Hira park
- Kurar Village Malad East
- Borivali
- Mumbai Suburban
- 400097
- Pincode400097
- RERA no.P51800033952
- ReraGenie IDRG-MH-53169
Builder
- NameSiddhivinayak Developers Kurar
- Entity typePartnership
- PartnersRasik Harilal Thakker, Sanjay Nathalal Shah
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on14 Mar 2022
- Promised completion31 Dec 2027
- Revised completionRevised to 31 Dec 2027 (originally 31 Dec 2025)
- Buildings2 building records
- Documents filed80 files
Current status
Figures as on 13 Aug 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A Wing | NA | 83 | 83 | 117 | 4 | 121 |
| B Wing | NA | 84 | 84 | 87 | 4 | 91 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 13 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
6 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Stilt Floor, at 95%.
A Wing63%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 95% |
| Slabs of Super Structure | 95% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 70% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 70% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 40% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 20% |
B Wing63%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 95% |
| Slabs of Super Structure | 95% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 70% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 70% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 40% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 20% |
Progress on shared amenities15
As on 13 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed121
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| A Wing | 60 | 60 |
| B Wing | 61 | 61 |
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| The Malad Lucky Co Operative Housing Society Ltd | Borivali | Mumbai Suburban |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| A Wing | NA | Rs 27.03 cr | Rs 10.43 cr |
| B Wing | NA | Rs 18.13 cr | Rs 6.99 cr |
| - | NA | Rs 6.56 cr | - |
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Rasik P Hingoo Associates p hingoo |
| Architect | Rasik P Hingoo Associates |
| Engineer | AVP Structural Consultants |
| Chartered Accountant | Vipul M Gharpure |
| Chartered Accountant | K S P M & ASSOCIATES |
| Partner | Role in project |
|---|---|
| Siddhivinayak Developers Kurar | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoter1) Poor booking response from customer. 2) Because of poor response our work was very slow. But now we have completed our 70 % Project
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 4 Mar 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 29 Jan 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 29 Jan 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 24 Jan 2025Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2027
Documents filed80
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1 Architect Certificate June 26.pdf | 13 Aug 2026 |
| Withdrawal Update Form 1File: Form 1 -june-nirvanaSigned Copy.pdf | 13 Aug 2026 |
| Withdrawal Update Form 1File: Form 1.pdf | 13 Aug 2026 |
| Withdrawal Update Form 1File: Form 1 30-06-2026.pdf | 13 Aug 2026 |
| Withdrawal Update Form 2File: Form 2-june-nirvana-signed.pdf | 13 Aug 2026 |
| Withdrawal Update Form 2File: Form 2-june-nirvana-signed.pdf | 13 Aug 2026 |
| Withdrawal Update Form 2File: Form 2.pdf | 13 Aug 2026 |
| Withdrawal Update Form 2File: Form 2 30-06-2026.pdf | 13 Aug 2026 |
| Withdrawal Update Form 3File: Form 3 CA certificate as on 30-06-2026.pdf | 13 Aug 2026 |
| Withdrawal Update Form 3File: Form 3 CA certificate as on 30-06-2026.pdf | 13 Aug 2026 |
| Withdrawal Update Form 3File: Form 3 - converted.pdf | 13 Aug 2026 |
| Withdrawal Update Form 3File: Form 3 30-06-2026.pdf | 13 Aug 2026 |
| Withdrawal Update Form 1File: SDK Form 1 Architect Certificate ( Jan 26 to Mar 26 ).pdf | 27 Jul 2026 |
| Withdrawal Update Form 2File: FORM 2 NIRVANA CHSL 31032026.pdf | 27 Jul 2026 |
| Withdrawal Update Form 3File: SDK CA Certificate Form 3.pdf | 27 Jul 2026 |
| Form 2A (FY 2021-2022)File: Form 2A 21-22.pdf | 16 Feb 2026 |
| Form 2A (FY 2022-2023)File: Form 2A 22-23.pdf | 16 Feb 2026 |
| Form 2A (FY 2023-2024)File: Form 2A 23-24.pdf | 16 Feb 2026 |
| Form 2A (FY 2024-2025)File: Form 2A 24-25.pdf | 16 Feb 2026 |
| Form 5 (FY 2024-2025)File: Form 5 24-25.pdf | 16 Feb 2026 |
| Form 1File: Form 1 SDK Nirvana ( April 25 to June 25 ).pdf | 6 Feb 2026 |
| Form 2File: FORM 2_NIRVANA CHSL_30-06-2025.pdf | 6 Feb 2026 |
| Form 3File: Form 3 SDK 31st Dec 2025 new.pdf | 6 Feb 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of sold_ booked.pdf | 6 Feb 2026 |
| Form 1File: Form 1 SDK Nirvana ( july 25 to sep 25 ).pdf | 6 Feb 2026 |
| Form 2File: FORM 2_NIRVANA CHSL_30-09-2025.pdf | 6 Feb 2026 |
| Form 3File: Form 3 SDK CA RERA as on 30th Sep 2025.pdf | 6 Feb 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of sold_ booked.pdf | 6 Feb 2026 |
| Form 1File: Form 1 SDK Nirvana ( oct 25 to dec 25 ).pdf | 6 Feb 2026 |
| Form 2File: FORM 2_NIRVANA CHSL_31-12-2025.pdf | 6 Feb 2026 |
| Form 3File: Form 3 SDK RERA CA Certificate As on 30th June 2025 new.pdf | 6 Feb 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of sold_ booked.pdf | 6 Feb 2026 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SDK Rera Form 3 as on 31-12-2024_compressed.pdf | 31 Jan 2025 |
| Declaration about all RERA Designated Bank Accounts (Format A)File: Declaration about RERA Designated Bank Ac.pdf | 27 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf | 24 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SDK CA Certificate As on Dec 2023_compressed (1).pdf | 24 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SDK Rera Form 3 CA certificate as on 31st March 2024_compressed (1).pdf | 24 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SDK Rera Form 3 CA certificate as.pdf | 24 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SDK CA certificate as on 30th Sep 2024_compressed.pdf | 24 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate.pdf | 24 Jan 2025 |
| Commencement Certificates / NA Order for plotted developmentFile: New CC.pdf | 24 Jan 2025 |
| Proforma of Agreement for saleFile: Agreement For Sale- SDK.pdf | 24 Jan 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 SDK 31st March 2024.pdf | 24 Jan 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: siddhivinayak developers form 5 .pdf | 6 Nov 2023 |
| Details of encumbrancesFile: SDK ENCUMBRANCE LETTER.pdf | 13 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Nirvana Architect certificate for Rera.pdf | 13 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineers Cert-NIRVANA PROJECT.pdf | 13 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA certificate Nirvana 62023.pdf | 13 Oct 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: SDK New CC as on 07072023.pdf | 11 Aug 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 5th Architect Certificate SDK site.pdf | 11 Aug 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_Engineers Cert-NIRVANA PROJECT.pdf | 11 Aug 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 5th SDK CA RERA Certificate Form 3 Compress.pdf | 11 Aug 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: SDK CC.pdf | 16 Mar 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SDK Architect Rera Form 1 ss.pdf | 16 Mar 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_Engineers Cert-NIRVANA PROJECT.pdf | 16 Mar 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SDK CA RERA Certificate Form 3_.pdf | 16 Mar 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SDK 3rd Architect Certificate Form 1_compressed.pdf | 24 Dec 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_Engineers Cert-NIRVANA PROJECT-03.pdf | 24 Dec 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate of Nirvana Project (1).pdf | 24 Dec 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: SDK New CC.pdf | 18 Nov 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SDK 2nd ARCHITECT CERTIFICATE RERA Form 1.pdf | 18 Nov 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_Engineers Certificate -02.pdf | 18 Nov 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SDK 2nd CA rera Certificate Data as on 30-06-2022_compressed.pdf | 2 Sep 2022 |
| Copy of the legal title reportFile: SDK Title Report_compressed.pdf | 4 Mar 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate as per Rera Format_compressed (1).pdf | 4 Mar 2022 |
| Details of encumbrancesFile: No Encumbrances.pdf | 19 Feb 2022 |
| Proforma of Allotment letterFile: Proforma Allotment letter Scan copy.pdf | 12 Feb 2022 |
| Building plan approvalFile: SDK Amended New IOA or IOD.pdf | 29 Jan 2022 |
| Layout approvalFile: Ground Floor Plan_.pdf | 29 Jan 2022 |
| Copy of Layout Approval (in case of layout)File: Ground Floor Plan_.pdf | 29 Jan 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: SDK Amended New IOA or IOD.pdf | 29 Jan 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: SDK Plinth CC.pdf | 29 Jan 2022 |
| Declaration about Commencement CertificateFile: Declaration about CC.pdf | 29 Jan 2022 |
| Declaration in FORM BFile: Form B_.pdf | 29 Jan 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate-.pdf | 29 Jan 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Certificate_.pdf | 29 Jan 2022 |
| CERSAI detailsFile: CERSAI_Search_Report_200229030819_For_Asset_Based_Search_29_01_2022_13_00_35_084.pdf | 29 Jan 2022 |
| CERSAI detailsFile: Declaration about no security.pdf | 29 Jan 2022 |
| Proforma of Allotment letterFile: Agreement draft For Sale- RERA .pdf | 29 Jan 2022 |
| PAN CardFile: SIDDHIVINAYAK DEVELOPERS KURAR PAN Card.pdf | 28 Jan 2022 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- All 80 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Nirvana on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Kurar Village Malad East6,700+ in Mumbai Suburban
Alta Monte and Signet
ERA REALTORS PRIVATE LIMITED
MAULI OMKAR
MAULI SAI DEVELOPERS PVT LTD
HIVE 97
AMITY CONSTRUCTIONS
MAULI PRIDE
MAULI SAI DEVELOPERS PVT LTD
Aarambh Phase III by group Satellite
Satellite Developers Private Limited
Sethia Imperial Avenue
Sai Enterprises
See every Mumbai Suburban project, with the district possession charts
Builder: Siddhivinayak Developers Kurar
Siddhivinayak Developers Kurar has 1 registration on MahaRERA, including Nirvana. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What are my rights if Nirvana is delayed beyond 31 Dec 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Nirvana?
The registered promoter entity is Siddhivinayak Developers Kurar, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Nirvana?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Nirvana?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Nirvana?
The professionals named in the filing: Architect: Rasik P Hingoo Associates p hingoo; Architect: Rasik P Hingoo Associates; Engineer: AVP Structural Consultants; Chartered Accountant: Vipul M Gharpure; Chartered Accountant: K S P M & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Nirvana?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback