ReraGenieLog inGet a buyer report

Home / Browse projects / Aurangabad, Maharashtra / Nirman Bharati City Center Building H-I

Registration lapsed No litigation declared Commercial project

Nirman Bharati City Center Building H-I

By CITY BHARATI TECHNO HERITAGE LLP

RG-MH-84770 · RERA P51500028992 · Last updated on MahaRERA portal: 12 Apr 2021

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 46 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Aurangabad registration emailed to you, free during the pilot beta.
Dec 2022Possession promised46 months past this date
5 of 11Construction stages donefurthest along: Internal walls, 80%
0Complaints at MahaRERAon this registration
Jump to the 14 documents Report an error

Nirman Bharati City Center Building H-I is a Commercial project by CITY BHARATI TECHNO HERITAGE LLP in Aurangabad, Maharashtra, registered with MahaRERA as P51500028992 on 23 Apr 2021. Possession was promised by 31 Dec 2022 and is now 46 months past that date.

At a glance

Project

  • NameNirman Bharati City Center Building H-I
  • TypeCommercial
  • Location
    • Samarth Nagar
    • Sillekhana
    • Aurangabad (M Corp.)
    • Aurangabad
    • 431001
  • Pincode431001
  • RERA no.P51500028992
  • ReraGenie IDRG-MH-84770

Builder

  • NameCITY BHARATI TECHNO HERITAGE LLP
  • Entity typePartnership
  • PartnersRAMESH NAGPAL, NAVIN BAGADIYA
  • Declared earlier projects1 →

Key dates

46 months past promisethis monthRegisteredApr 2021PromisedDec 2022

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on23 Apr 2021
  • Promised completion31 Dec 2022
  • Revised completionNone
  • Buildings1 building record
  • Documents filed14 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
NBCC Building H-INA50000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 12 Apr 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 80%.

NBCC Building H-I: 61% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.40%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 12 Apr 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed16

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots16
Open Space16

Land and ownership7

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,439 sq m
Land owned byThe promoter, with other names on the file
Named landowners7
LandownerVillageDistrict
Vikramsingh Dattusingh ChavanLatur (M Cl)Latur
Mahendrasing Vikramsingh ChavanLatur (M Cl)Latur
Dharmeshsingh V chavanLatur (M Cl)Latur
Jitedrasigh V ChavanLatur (M Cl)Latur
Smt Charusheela Jagdish SuryawanshiAurangabad (M Corp.)Aurangabad
Pritish Jagdish SuryawanshiAurangabad (M Corp.)Aurangabad
Priyartna Jagdish SuryawanshiAurangabad (M Corp.)Aurangabad

Approvals and building plan

Permissible FSI2765.88
Proposed, not sanctioned2,766 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchBansilal Nagar Aurangabad

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectManoj Kala and Associates
EngineerMIRZA AZHAR BAIG
Chartered AccountantNarendra Navandar And Company
PartnerRole in project
CITY BHARATI TECHNO HERITAGE LLP-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 11 Apr 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 11 Apr 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 11 Apr 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 12 Apr 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed14

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Details of encumbrancesFile: ENCUMBRANCE DECLARION.pdf12 Apr 2021
Commencement Certificates / NA Order for plotted developmentFile: revised bp.pdf12 Apr 2021
Declaration in FORM BFile: FORM B DEVELOPER.pdf12 Apr 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 - CA Cert NIRMAN BHARTI CITY CENTER- BUILDING- H-I.pdf12 Apr 2021
Proforma of Allotment letterFile: ATS FROMAT H-I BUILDING DEVELOPER - .pdf12 Apr 2021
Layout approvalFile: 1-6 REV BP NBCC.pdf11 Apr 2021
Building plan approvalFile: 1-6 REV BP NBCC.pdf11 Apr 2021
Building plan approvalFile: 3-6 REV BP NBCC.pdf11 Apr 2021
PAN CardFile: PAN.pdf11 Apr 2021
Copy of the legal title reportFile: Search 1.pdf11 Apr 2021
Copy of Layout Approval (in case of layout)File: 1-6 REV BP NBCC.pdf11 Apr 2021
Building Plan Approval / NA Order for plotted developmentFile: 1-6 REV BP NBCC.pdf11 Apr 2021
Building Plan Approval / NA Order for plotted developmentFile: 3-6 REV BP NBCC.pdf11 Apr 2021
Proforma of Allotment letterFile: Allotment.pdf11 Apr 2021

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
NIRMAN BHARTI CITY CENTRECTS NO 17849 SILLEKHNA1CompletedOct 2020Oct 2020

How this compares with Aurangabad

14%of Aurangabad projects moved their completion datethis one has not
32%of Aurangabad registrations have lapsed or been cancelledthis one is among them

Computed across the 1,400+ Aurangabad projects on ReraGenie, from their own filings.

Keep Nirman Bharati City Center Building H-I on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Sillekhana1,400+ in Aurangabad

Builder: CITY BHARATI TECHNO HERITAGE LLP

CITY BHARATI TECHNO HERITAGE LLP has 1 registration on MahaRERA, including Nirman Bharati City Center Building H-I. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Aurangabad district page.

Frequently asked questions

What does it mean that Nirman Bharati City Center Building H-I shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Nirman Bharati City Center Building H-I is delayed beyond 31 Dec 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Nirman Bharati City Center Building H-I?

The registered promoter entity is CITY BHARATI TECHNO HERITAGE LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Nirman Bharati City Center Building H-I?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Nirman Bharati City Center Building H-I?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Nirman Bharati City Center Building H-I?

The professionals named in the filing: Architect: Manoj Kala and Associates; Engineer: MIRZA AZHAR BAIG; Chartered Accountant: Narendra Navandar And Company. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Nirman Bharati City Center Building H-I?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Nirman Bharati City Center Building H-I. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Nirman Bharati City Center Building H-I to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.