Home / Browse projects / Mumbai Suburban, Maharashtra / Nirmal Lifestyle-Blu Diamond-One Edition
Nirmal Lifestyle-Blu Diamond-One Edition
RG-MH-53496 · RERA P51800006693 · Last updated on MahaRERA portal: 1 Feb 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 22 months past the filed date
- 48 complaints at MahaRERA
- Completion date moved by 64 months
- 3 extensions taken
- Rs 54.00 crore secured on the land, in favour of ACRE
- The declared charge does not appear in the CERSAI report on the filing
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
7 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Nirmal Lifestyle-Blu Diamond-One Edition is a Residential / Group Housing project by Nirmal Lifestyle Ltd in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800006693 on 16 Aug 2017. Possession was promised by 31 Dec 2024 and is now 22 months past that date. The completion date has moved by 64 months from the original filing. 250 of the 385 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete. 48 complaints are on record with the regulator.
At a glance
Project
- NameNirmal Lifestyle-Blu Diamond-One Edition
- TypeResidential / Group Housing
- Location
- LBS ROAD
- MULUND WEST
- Kurla
- Mumbai Suburban
- 400080
- Pincode400080
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800006693
- ReraGenie IDRG-MH-53496
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on16 Aug 2017
- Promised completion31 Dec 2024
- Revised completionRevised to 31 Dec 2024 (originally 31 Aug 2019)
- Buildings1 building record
- Documents filed54 files
Current status
Figures as on 1 Feb 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Blu Diamond -One Edition | NA | 34 | 19 | 385 | 0 | 385 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 1 Feb 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
4 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 67%.
Blu Diamond -One Edition: 59% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 67% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 47% |
| Sanitary Fittings within the flats / premises | 48% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 49% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 32% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 8% |
Progress on shared amenities15
As on 1 Feb 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | Yes | 0% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 0% |
Parking filed177
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Manoj V Daisaria |
| Engineer | Kamal Hadkar |
| Chartered Accountant | J. Acharya & Associates |
| Partner | Role in project |
|---|---|
| Nirmal Lifestyle Ltd | - |
Extensions applied for3
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterWIP
Reason as filed by the promoterThe Customers have formed the society and have jointly with us decided to get the building completed.
Reason as filed by the promoterwork in progress and delay due to COVID
Complaints filed with MahaRERA48
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000396959 | Blue Diamond Cooperative Housing Society Limited | Nirmal Lifestyle Limited | 08/08/2023 |
| CC006000000055510 | Geeta Sekhar | Nirmal Lifestyle Ltd | 28/07/2018 |
| CC006000000055513 | Narendra Nadkarni | Nirmal Lifestyle Ltd | 28/07/2018 |
| CC006000000055514 | Umesh Bahdur | Nirmal Lifestyle Ltd | 28/07/2018 |
| CC006000000055515 | Sheela Ved | Nirmal Development Ltd | 28/07/2018 |
| CC006000000055518 | Deepa Patil | Nirmal Lifestyle Ltd | 28/07/2018 |
| CC006000000055519 | Ashok Anand | Nirmal Lifestyle Ltd | 28/07/2018 |
| CC006000000055520 | Shrikumar Naik | Nirmal Lifestyle Ltd | 28/07/2018 |
| CC006000000055521 | Ashok Balani | Nirmal Lifestyle Ltd | 28/07/2018 |
| CC006000000055522 | Rajkumar Balani | Nirmal Lifestyle Ltd | 28/07/2018 |
| CC006000000055525 | Kamlesh Advani | Nirmal Lifestyle Ltd | 28/07/2018 |
| CC006000000055526 | Mukesh Hiran | Nirmal Lifestyle Ltd | 28/07/2018 |
| CC006000000055529 | Dr Praveen Mody | Nirmal life style ltd | 28/07/2018 |
| CC006000000055527 | Dhiraj Saxena | Nirmal Lifestyle Ltd | 28/07/2018 |
| CC006000000055528 | Upendra Tiwari | Nirmal Lifestyle Ltd | 28/07/2018 |
| CC006000000055530 | Suresh Shetty | Nirmal Lifestyle Ltd | 28/07/2018 |
| CC006000000055531 | Prashant Borade | Nirmal Lifestyle Ltd | 28/07/2018 |
| CC006000000055532 | Mr Dharmu Balani And Mrs Neetu Balani | nirmal lifesytle ltd | 28/07/2018 |
| CC006000000055534 | Mr Manish Korgaonkar & Mrs Meena korgaonkar | Nirmal lifestyle ltd | 28/07/2018 |
| CC006000000055535 | Pradeep D'souza | Nirmal Lifestyle Ltd | 28/07/2018 |
| CC006000000055536 | Mohanlal Padhi | Nirmal Lifestyle Ltd | 30/07/2018 |
| CC006000000055538 | Colville Sequeira | Nirmal Lifestyle Ltd | 28/07/2018 |
| CC006000000055541 | Ramprakash Iyar | Niraml lifestyle ltd | 28/07/2018 |
| CC006000000055540 | Mohamed Ansari | Nirmal Lifestyle Ltd | 28/07/2018 |
| CC006000000055544 | Kulwant Singh Mokha | Nirmal Lifestyle Ltd | 28/07/2018 |
| CC006000000055545 | Anthony Peter | Nirmal Lifestyle Ltd | 28/07/2018 |
| CC006000000055546 | Anand Vachhani | nirmal lifestyle ltd | 28/07/2018 |
| CC006000000055547 | R Krishnan | Nirmal Lifestyle Ltd | 28/07/2018 |
| CC006000000055548 | Manoj R Iyar | nirmal lifestyle ltd | 28/07/2018 |
| CC006000000055549 | Manisha A Ramchandani | nirmal lifestyle ltd | 28/07/2018 |
| CC006000000055550 | Aruna Godwin | nirmal lifestyle ltd | 28/07/2018 |
| CC006000000055553 | Avaneet soni | nirmal lifestyle ltd | 28/07/2018 |
| CC006000000196351 | MRS DISHA SHAH | NIRMAL LIFESTYLE LIMITED | 24/03/2021 |
| CC006000000056338 | Gautam Addanki | Nirmal Lifestyle Ltd | 25/10/2018 |
| CC006000000110813 | Cynthia Akhil Chaturvedi | Nirmal Lifestyle Ltd | 06/09/2019 |
| CC006000000110826 | Vijay Manish Dua | Nirmal Lifestyle tLtd | 07/09/2019 |
| CC006000000120965 | Vivek V Shinde | Nirmal Lifestyle Ltd | 18/09/2019 |
| CC006000000141088 | Dr Madhu Prasad | Nirmal LIfestyle Ltd | 28/09/2019 |
| CC006000000079113 | Prakash Kundandas | Nirmal Lifestyle Lmited | 01/05/2019 |
| CC006000000090040 | Mrs. Nayna Avnish Joshi | M/s. Nirmal Lifestyle | 31/07/2019 |
| CC006000000089542 | Kailash Visht and 2 others | Nirmal Lifestyle Ltd | 01/06/2019 |
| CC006000000396657 | Balbir Profiles Pvt Ltd | Nirmal Lifestyle Limited | 18/07/2023 |
| CC006000000397530 | Kailash Visht | Nirmal Lifestyle Ltd | 23/09/2023 |
| CC006000000397532 | Kailash Visht | Nirmal Lifestyle Ltd | 23/09/2023 |
| CC006000000397533 | Kailash Visht | Nirmal Lifestyle Ltd | 23/09/2023 |
| CC006000000397534 | Kailash Visht | Nirmal Lifestyle Ltd | 23/09/2023 |
| CC006000000397535 | Kailash Visht | Nirmal Lifestyle Ltd | 23/09/2023 |
| CC006000000397536 | Kailash Visht | Nirmal Lifestyle Ltd | 23/09/2023 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 8 Mar 2019 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 30 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 29 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 29 Mar 2018Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed54
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 5 (FY 2023-2024)File: Form 5 BD (1).pdf | 1 Feb 2026 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 of NLL-Blue Diamond for FY 2018-2019 Signed.pdf | 10 Apr 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 of NLL-Blue Diamond for FY 2019-2020 Signed.pdf | 10 Apr 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 of NLL-Blue Diamond for FY 2020-2021 Signed.pdf | 10 Apr 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 of NLL-Blue Diamond for FY 2021-2022 Signed.pdf | 10 Apr 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 of NLL-Blue Diamond for FY 2022-2023 Signed.pdf | 10 Apr 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 of NLL-Blue Diamond for FY 2018-2019.pdf | 8 Apr 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 of NLL-Blue Diamond for FY 2019-2020.pdf | 8 Apr 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 of NLL-Blue Diamond for FY 2020-2021.pdf | 8 Apr 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 of NLL-Blue Diamond for FY 2021-2022.pdf | 8 Apr 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 of NLL-Blue Diamond for FY 2022-2023.pdf | 8 Apr 2024 |
| Certificates of CA (Form 3)File: Form 3 BD_31032018.pdf | 13 Oct 2023 |
| Certificates of CA (Form 3)File: Form 3 BD_31_03_20219.pdf | 13 Oct 2023 |
| Certificates of CA (Form 3)File: Form 3 BD_31032020.pdf | 13 Oct 2023 |
| Certificates of CA (Form 3)File: Form 3 BD_31_03_2021.pdf | 13 Oct 2023 |
| Certificates of CA (Form 3)File: Form 3 BD_31_03_2022.pdf | 13 Oct 2023 |
| Certificates of CA (Form 3)File: Form 3 BD_31032023.pdf | 13 Oct 2023 |
| Certificates of CA (Form 3)File: Form 3 BD_30092023.pdf | 13 Oct 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 BD.pdf | 6 Oct 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 BD.pdf | 6 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A.pdf | 6 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: sold unsold inventory.pdf | 6 Oct 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Rera Form 1.pdf | 15 Sep 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Form 2.pdf | 15 Sep 2023 |
| Declaration in FORM BFile: Form B.pdf | 22 Aug 2023 |
| Declaration about Commencement CertificateFile: Declaration about CC Blue Diamond.pdf | 14 Aug 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Quality Assurance Certificate -Engineering Certificate.pdf | 14 Aug 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Quality Assurance Certificate -Engineering Certificate.pdf | 14 Aug 2023 |
| Declaration about Commencement CertificateFile: Declaration about CC Blue Diamond.pdf | 19 Apr 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Quality Assurance Certificate -Engineering Certificate.pdf | 19 Apr 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Quality Assurance Certificate -Engineering Certificate.pdf | 19 Apr 2022 |
| CERSAI detailsFile: CERSAI_Search_Report_200235366728_For_Asset_Based_Search_19_04_2022_12_03_17_847.pdf | 19 Apr 2022 |
| CERSAI detailsFile: CERSAI_Search_Report_200235366768_For_Asset_Based_Search_19_04_2022_12_03_44_321.pdf | 19 Apr 2022 |
| CERSAI detailsFile: CERSAI_Search_Report_200235366812_For_Asset_Based_Search_19_04_2022_12_04_09_324.pdf | 19 Apr 2022 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory.pdf | 18 Apr 2022 |
| Details of encumbrancesFile: Index II 27-03-2019.pdf | 25 Jun 2019 |
| Copy of the legal title reportFile: Blue Diamond Titel Certificate.pdf | 8 Mar 2019 |
| Copy of the legal title reportFile: BLUE DIAIMOND Cover Letter.pdf | 8 Mar 2019 |
| Certificates of CA (Form 5)File: Blue Diamond Form 5.pdf | 24 Jan 2019 |
| Commencement Certificates / NA Order for plotted developmentFile: blue diamond- cc validation receipt.pdf | 29 Mar 2018 |
| Commencement Certificates / NA Order for plotted developmentFile: Blue Diamond CC.pdf | 29 Mar 2018 |
| Layout approvalFile: BLUE DIAMOND PROPSOED FUTURE LAYOUT.pdf | 30 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: BLUE DIAMOND PROPSOED FUTURE LAYOUT.pdf | 30 Jul 2017 |
| Declaration in FORM BFile: blue diamond - one edition new affidavit form B.pdf | 30 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Blue Diamond one edition.pdf | 30 Jul 2017 |
| Certificates of CA (Form 3)File: CA certificate Blue Diamond One Edition.pdf | 30 Jul 2017 |
| Proforma of Allotment letterFile: Blue Diamond One Edition.pdf | 30 Jul 2017 |
| Building plan approvalFile: IOD-BLUE DIAMOND.pdf | 29 Jul 2017 |
| Layout approvalFile: APPROVED LAYOUT-BLUE DIAMOND.pdf | 29 Jul 2017 |
| Copy of the legal title reportFile: Sanofi - Report on Title .pdf | 29 Jul 2017 |
| Details of encumbrancesFile: Index_Altico_300 crores_NLL.pdf | 29 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: APPROVED LAYOUT-BLUE DIAMOND.pdf | 29 Jul 2017 |
| Building Plan Approval (IOD)File: IOD-BLUE DIAMOND.pdf | 29 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Blue Diamond - One Edition.pdf | 29 Jul 2017 |
Promoter's earlier projects4
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| Relish, Cherish | City of Joy Plot No 661 1 7 Jata Shanker Road Mulund W Mumbai 400080 | 332 | Completed | Sep 2009 | Late, Mar 2010 |
| Bliss, Rejoice | City of Joy Plot No 661 1 7 Jata Shanker Road Mulund W Mumbai 400080 | 332 | Completed | Sep 2009 | Late, Mar 2010 |
| Happiness, Hurrah | City of Joy Plot No 661 1 7 Jata Shanker Road Mulund W Mumbai 400080 | 228 | Completed | Jun 2007 | Late, Dec 2007 |
| Celebration , Sparkle | City of Joy Plot No 661 1 7 Jata Shanker Road Mulund W Mumbai 400080 | 228 | Completed | Jun 2007 | Late, Dec 2007 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 7 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 6 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 54 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Nirmal Lifestyle-Blu Diamond-One Edition on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near MULUND WEST6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 253 registered projects within 2 km.
Eternia Towers A to D
Oberoi Constructions Limited
Bellanza Phase 1 - Wing A, B, C at The Prestig
PRESTIGE MULUND REALTY PRIVATE LIMITED
Atmosphere O2
Atmosphere Realty Pvt Ltd
Bellanza Phase 2 - Wing D, E, F at The Prestig
PRESTIGE MULUND REALTY PRIVATE LIMITED
Forest Hills Ph 1 at The Prestige City
PRESTIGE MULUND REALTY PRIVATE LIMITED
Kalpataru Elitus
Arimas Real Estate Private Limited
See every Mumbai Suburban project, with the district possession charts
Builder: Nirmal Lifestyle Ltd
Nirmal Lifestyle Ltd has 7 registrations on MahaRERA, including NIRMAL LIFESTYLE, TRIUMPH AND THRILL and Nirmal Lifestyle-Zircon. Its filings disclose 10 earlier MahaRERA projects: declares 0 of 9 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What does it mean that Nirmal Lifestyle-Blu Diamond-One Edition shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Nirmal Lifestyle-Blu Diamond-One Edition is delayed beyond 31 Dec 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Nirmal Lifestyle-Blu Diamond-One Edition?
The registered promoter entity is Nirmal Lifestyle Ltd, a company as per the filing. Its GSTIN 27AAACN9145J1Z6 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Nirmal Lifestyle-Blu Diamond-One Edition?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Nirmal Lifestyle-Blu Diamond-One Edition?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Nirmal Lifestyle-Blu Diamond-One Edition?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Nirmal Lifestyle-Blu Diamond-One Edition?
The professionals named in the filing: Architect: Manoj V Daisaria; Engineer: Kamal Hadkar; Chartered Accountant: J. Acharya & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Nirmal Lifestyle-Blu Diamond-One Edition?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback