Home / Browse projects / Sindhudurg, Maharashtra / NIRMAAN BHAVAN

Registration lapsed No litigation declared Others project

NIRMAAN BHAVAN

By NIRMAN BUILDERS AND DEVELOPERS

RG-MH-51687 · RERA P52900007056 · Last updated on MahaRERA portal: 3 Jul 2023

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 84 months past the filed date
  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Sindhudurg registration emailed to you, free during the pilot beta.
Oct 2019Possession promised84 months past this date
4 of 11Construction stages donefurthest along: Stilt Floor, 90%
0Complaints at MahaRERAon this registration
Jump to the 37 documents Report an error

NIRMAAN BHAVAN is a Others project by NIRMAN BUILDERS AND DEVELOPERS in Sindhudurg, Maharashtra, registered with MahaRERA as P52900007056 on 17 Aug 2017. Possession was promised by 31 Oct 2019 and is now 84 months past that date. The completion date has moved by 12 months from the original filing.

At a glance

Project

  • NameNIRMAAN BHAVAN
  • TypeOthers
  • Location
    • Sawantwadi (M Cl)
    • Sawantwadi
    • Sindhudurg
    • 416510
  • Pincode416510
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52900007056
  • ReraGenie IDRG-MH-51687

Builder

  • NameNIRMAN BUILDERS AND DEVELOPERS
  • Entity typePartnership
  • Declared earlier projects1 →

Key dates

84 months past promisethis monthRegisteredAug 2017First promiseOct 2018Revised toOct 2019

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on17 Aug 2017
  • Promised completion31 Oct 2019
  • Revised completionRevised to 31 Oct 2019 (originally 31 Oct 2018)
  • Buildings1 building record
  • Documents filed37 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
NIRMAAN BHAVANNA60000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 3 Jul 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Stilt Floor, at 90%.

NIRMAAN BHAVAN: 58% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor90%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises35%
Sanitary Fittings within the flats / premises30%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.35%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 3 Jul 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes15%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed65

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots65
Open Space65

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,300 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI1551.6
Proposed, not sanctioned1,303 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch64 RAMESHWAR PLAZA NEAR MOTI TALAO SAWANTWADI 416510

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSHRADDHA MADHU SAWANT
EngineerYESHWANT ATMARAM NAIK
PartnerRole in project
NIRMAN BUILDERS AND DEVELOPERS-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52900000716Oct 2018 → Oct 2019

Reason as filed by the promoterTHERE BEING MAJOR FAMILY HEALTH ISSUES WITH ONE OF THE PARTNER cum CONSULTANT AND THEN SUDDEN DEATH OF HIS WIFE DURING THE PROJECT PERIOD. ALSO DUE TO RECESSION IN CONSTRUCTION INDUSTRY RESPONSE FROM THE CUSTOMER WAS MUCH LESS THAN EXPECTED WHICH IMPACTED ON OUR FUNDS.CONSIDERING ALL ABOVE ISSUES PLEASE ALLOW US THE EXPECTED EXTENSION.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 30 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 30 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 3 Jul 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 3 Jul 2023

Documents filed37

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Details of encumbrances concerned to FinanceFile: encumbrances affidavite.pdf3 Jul 2023
Details of encumbrances concerned to LegalFile: encumbrances affidavite.pdf3 Jul 2023
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf3 Jul 2023
Commencement Certificates / NA Order for plotted developmentFile: Nirman Full OC.pdf3 Jul 2023
Commencement Certificates / NA Order for plotted developmentFile: Nirman Sanctioned Plan.pdf3 Jul 2023
Declaration about Commencement CertificateFile: Commencement Certificate 1.pdf3 Jul 2023
Declaration about Commencement CertificateFile: Commencement certificate 2.pdf3 Jul 2023
Declaration about Commencement CertificateFile: Commencement Certificate 1-1.pdf3 Jul 2023
Declaration about Commencement CertificateFile: Commencement Certificate 2-1.pdf3 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Quality assurance .pdf3 Jul 2023
CERSAI detailsFile: CERSAI_Search_Report.pdf3 Jul 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure Of Interest .pdf3 Jul 2023
Proforma of Agreement for saleFile: Proforma of Agreement for Sale.pdf3 Jul 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Completion certificate Architect I.pdf3 Jul 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank Account .pdf3 Jul 2023
Deviation Report with respect to Allotment letterFile: Deviation Report with respect to Allotment letter.pdf3 Jul 2023
Deviation Report with respect to model copy of AgreementFile: Deviation Report with respect to Model copy of Agreement.pdf3 Jul 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: ARCHITECT CERTIFICATE.pdf7 Aug 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: ilovepdf_merged.pdf5 Aug 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: img02080.pdf5 Aug 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: ARCHITECT CERTIFICATE_reduce.pdf25 Feb 2020
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 25-02-20, 16_17 Office Lens_reduce.pdf25 Feb 2020
Building plan approvalFile: NIRMAN BHAVAN SANCTIONED PLAN.pdf30 Jul 2017
Building plan approvalFile: municipal order COMPRESSED.pdf30 Jul 2017
Layout approvalFile: NIRMAN BHAVAN SANCTIONED PLAN.pdf30 Jul 2017
PAN CardFile: New Doc 2017-07-30.pdf30 Jul 2017
Copy of the legal title reportFile: search.pdf30 Jul 2017
Details of encumbrancesFile: self decleration.pdf30 Jul 2017
Copy of Layout Approval (in case of layout)File: NIRMAN BHAVAN SANCTIONED PLAN.pdf30 Jul 2017
Building Plan Approval (IOD)File: municipal order COMPRESSED.pdf30 Jul 2017
Building Plan Approval (IOD)File: NIRMAN BHAVAN SANCTIONED PLAN.pdf30 Jul 2017
Declaration in FORM BFile: declaration.pdf30 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE COMPRESSED.pdf30 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: eng cert.pdf30 Jul 2017
Certificates of CA (Form 3)File: for ca.pdf30 Jul 2017
Proforma of Allotment letterFile: allotment letter.pdf30 Jul 2017
Proforma of Allotment letterFile: AGREEMENT FOR SALE FOR NIRMAAN.pdf30 Jul 2017

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
NIRMAAN BAHARPLOT NO 1 KHASKILWADA NEAR JJ MEDICAL SAWANTWADI 41651012CompletedJun 2014Late, Mar 2015

How this compares with Sindhudurg

21%of Sindhudurg projects moved their completion datethis one moved by 12 months
30%of Sindhudurg registrations have lapsed or been cancelledthis one is among them

Computed across the 530+ Sindhudurg projects on ReraGenie, from their own filings.

Keep NIRMAAN BHAVAN on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Sawantwadi (M Cl)530+ in Sindhudurg

2 kmNIRMAAN BHAVANCompleted 28Lapsed / revoked 10Other 16Dot size: filed unitsN

Filed coordinates, straight-line distance. 54 registered projects within 2 km.

Builder: NIRMAN BUILDERS AND DEVELOPERS

NIRMAN BUILDERS AND DEVELOPERS has 1 registration on MahaRERA, including NIRMAAN BHAVAN. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Sindhudurg district page.

Frequently asked questions

What does it mean that NIRMAAN BHAVAN shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if NIRMAAN BHAVAN is delayed beyond 31 Oct 2019?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of NIRMAAN BHAVAN?

The registered promoter entity is NIRMAN BUILDERS AND DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in NIRMAAN BHAVAN?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for NIRMAAN BHAVAN?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at NIRMAAN BHAVAN?

The professionals named in the filing: Architect: SHRADDHA MADHU SAWANT; Engineer: YESHWANT ATMARAM NAIK. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in NIRMAAN BHAVAN?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About NIRMAAN BHAVAN. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save NIRMAAN BHAVAN to a free account