Home / Browse projects / New National Market Annexe

Registered No litigation declared Commercial project

New National Market Annexe

By Suleman Haroon & Company

RG-MH-29747 · RERA P51900029270 · Last updated on MahaRERA portal: 9 Jun 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 63 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: .
Dec 2027Possession promisedmoved 63 months from the original
7 of 11Construction stages donefurthest along: External plumbing and external plaster, 90%
53 of 135Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 71 documents Report an error

New National Market Annexe is a Commercial project by Suleman Haroon & Company in Dadar Naigaon Division, 400031, registered with MahaRERA as P51900029270 on 10 May 2021. Possession is promised by 31 Dec 2027. The completion date has moved by 63 months from the original filing. 82 of the 135 units on this registration are recorded sold or booked, and 7 of 11 construction stages are filed complete.

At a glance

Project

  • NameNew National Market Annexe
  • TypeCommercial
  • Location
    • Rafi Ahmed Kidwai Marg
    • Dadar Naigaon Division
    • 400031
  • Pincode400031
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51900029270
  • ReraGenie IDRG-MH-29747

Builder

  • NameSuleman Haroon & Company
  • Entity typePartnership
  • PartnersRajesh Ghewarchand Jain, Neumec Development And Allied Services Private Limited

Key dates

this monthRegisteredMay 2021First promiseSep 2022Revised toDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on10 May 2021
  • Promised completion31 Dec 2027
  • Revised completionRevised to 31 Dec 2027 (originally 30 Sep 2022)
  • Buildings1 building record
  • Documents filed71 files

Current status

61%82 of 135 units booked
67.7%Work done, per cost certificate

Figures as on 9 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Building No - 3-4th and 5th FloorNA540135135

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 9 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 11 construction stages are filed complete. The stage furthest along is External plumbing and external plaster, at 90%.

Building No - 3-4th and 5th Floor: 87% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.85%

Progress on shared amenities15

As on 9 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes90%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed16

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots16
Closed/Covered16

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area948 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
Neumec Builders & DevelopersGreater Mumbai (M Corp.) (Part) (802794)Mumbai Suburban

Approvals and building plan

Sanctioning authoritySlum Rehabilitation Authority
Permissible FSI973.93
Proposed, not sanctioned559 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchFort University Mumbai -400023
Estimated costRs 5.09 cr
Cost incurredRs 3.45 cr
Work done67.74%
BuildingWingEstimatedIncurred
Building No - 3-4th and 5th FloorNARs 4.84 crRs 3.28 cr
-NARs 25.47 lakhRs 17.25 lakh

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectConsultants Combined Architects
EngineerSK Consultants & Engineers
Chartered AccountantRutuja Narsingh & Associates
Chartered AccountantNB Sayed & Associates
PartnerRole in project
Suleman Haroon & Company-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51900017384Sep 2022 → Sep 2025

Reason as filed by the promoterIn accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 74% allottees for purpose of extension of RERA registration period of the said project.

EXT51900012702Sep 2022 → Sep 2023

Reason as filed by the promoterIn accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19.

EA06022619747Sep 2022 → Dec 2027

Reason as filed by the promoterWe apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, financial constraints, and site challenges. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. Given the circumstances, we kindly request an extension until 31-12-2027, to complete the project and fulfil all regulatory requirements.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 23 Apr 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 14 Apr 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 14 Oct 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 14 Oct 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 27 Jul 2021

Documents filed71

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 5 (FY 2024-2025)File: Form 5 New National Market Annexe FY 2024-25.pdf9 Jun 2026
Withdrawal Update Form 1File: Form 1 - New National Market Annexe as on Dec 2025.pdf12 Mar 2026
Withdrawal Update Form 2File: Form 2 - New National Market Annexe as on Dec 2025 (signed).pdf12 Mar 2026
Withdrawal Update Form 3File: Form 3 - New National Market Annexe as on Dec 2025.pdf12 Mar 2026
Withdrawal Update Form 1File: Form 1 - New National Market Annexe as on Dec 2025.pdf5 Feb 2026
Withdrawal Update Form 1File: Form 1 - New National Market Annexe as on Dec 2025.pdf5 Feb 2026
Withdrawal Update Form 2File: Form 2 - New National Market Annexe as on Dec 2025 (signed).pdf5 Feb 2026
Withdrawal Update Form 2File: Form 2 - New National Market Annexe as on Dec 2025 (signed).pdf5 Feb 2026
Withdrawal Update Form 3File: Form 3 - New National Market Annexe as on Dec 2025.pdf5 Feb 2026
Withdrawal Update Form 3File: Form 3 - New National Market Annexe as on Dec 2025.pdf5 Feb 2026
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 New National Market Annexe FY 2023-24.pdf20 Mar 2025
Building plan approvalFile: Binder2 (1)_11zon.pdf14 Oct 2024
Building plan approvalFile: Binder2 (1)_11zon.pdf14 Oct 2024
Building Plan Approval / NA Order for plotted developmentFile: Binder2 (1)_11zon.pdf14 Oct 2024
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf14 Oct 2024
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf14 Oct 2024
Building Plan Approval / NA Order for plotted developmentFile: Binder2 (1)_11zon.pdf14 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 3 Architect’s Certificate of Percentage of Completion of Work (Form 1) (1).pdf16 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 10 Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf16 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 11 CA Certificate on Project Cost Fund withdrawal (Form 3).pdf16 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - New National Market Annexe March 2022.pdf19 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - New National Market Annexe June 2022.pdf19 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - New National Market Annexe September 2022.pdf19 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - New National Market Annexe December 2022.pdf19 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - New National Market Annexe March 2023.pdf19 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - New National Market Annexe June 2023.pdf19 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - New National Market Annexe September 2023.pdf19 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - New National Market Annexe December 2023.pdf19 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3-New National Market Annexe March 2022.pdf19 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3-New National Market Annexe June 2022.pdf19 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3-New National Market Annexe Sep 2022.pdf19 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3-New National Market Annexe Dec 2022.pdf19 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3-New National Market Annexe March 2023.pdf19 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3-New National Market Annexe June 2023.pdf19 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3-New National Market Annexe Sep 2023.pdf19 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3-New National Market Annexe Dec 2023.pdf19 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - New National Market Annex as on Dec 2023.pdf18 Jun 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 - New National Market Annex for FY 2022-23.pdf18 Jun 2024
Declaration about Commencement CertificateFile: Format D.pdf18 Aug 2023
Declaration in FORM BFile: Form B.pdf18 Aug 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A 21-22_compressed (1).pdf18 Aug 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 22-23 New National Market.pdf18 Aug 2023
Disclosure of sold/ booked inventoryFile: Circular 29.pdf18 Aug 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 Certificate 313_compressed.pdf1 Oct 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Suleman_Haroon Architect Certificate.pdf8 Apr 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 New national market annexe Sept 2021.pdf21 Mar 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 New national market annexe Dec 2021.pdf21 Mar 2022
CERSAI detailsFile: New National Market Annex.pdf21 Mar 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_Suleman Haroon and Co_Sept 2021_11zon.pdf21 Mar 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_Suleman Haroon and Co_Dec 2021_11zon.pdf21 Mar 2022
Disclosure of sold/ booked inventoryFile: Suleman_Haroon_List.pdf3 Sep 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: New_National_Market_Annexe-Form-1.pdf20 Aug 2021
Declaration about Commencement CertificateFile: Market_Annexe-Form-D.pdf16 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: New_National_Market_Annexe-Form2A_compressed.pdf16 Aug 2021
Commencement Certificates / NA Order for plotted developmentFile: Suleman Haroon new CC.pdf27 Jul 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Suleman Haroon OC 22nd june 2017.pdf27 Jul 2021
Commencement Certificates / NA Order for plotted developmentFile: CC SULEMEN HAROON.pdf5 May 2021
Building plan approvalFile: PLAN 2.pdf23 Apr 2021
Building plan approvalFile: PLAN 3.pdf23 Apr 2021
Copy of the legal title reportFile: Title_Certificate_Suleman_Haroon-1-5_compressed.pdf23 Apr 2021
Copy of the legal title reportFile: Suleman Haroon Co.pdf23 Apr 2021
Building Plan Approval / NA Order for plotted developmentFile: PLAN 2.pdf23 Apr 2021
Building Plan Approval / NA Order for plotted developmentFile: PLAN 3.pdf23 Apr 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Suleman Haroon and Co.pdf23 Apr 2021
Proforma of Allotment letterFile: Allotment Letter.pdf16 Apr 2021
Proforma of Allotment letterFile: AFS_New_RERA-Suleman_Haroon___Company.pdf15 Apr 2021
Layout approvalFile: 1-1 PLAN.pdf14 Apr 2021
Details of encumbrancesFile: ENCUMBRANCE.pdf14 Apr 2021
Copy of Layout Approval (in case of layout)File: 1-1 PLAN.pdf14 Apr 2021
Declaration in FORM BFile: Affidavitcum Declaration (2).pdf14 Apr 2021
PAN CardFile: Suleman Haroon pAN.pdf6 Apr 2021

Keep New National Market Annexe on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Dadar Naigaon Division

2 kmNew National Market AnneCompleted 6Lapsed / revoked 3Other 9Dot size: filed unitsN

Filed coordinates, straight-line distance. 18 registered projects within 2 km.

Builder: Suleman Haroon & Company

Suleman Haroon & Company has 1 registration on MahaRERA, including New National Market Annexe. Its filings disclose no earlier MahaRERA projects. Read the full track record.

Frequently asked questions

What are my rights if New National Market Annexe is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of New National Market Annexe?

The registered promoter entity is Suleman Haroon & Company, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in New National Market Annexe?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for New National Market Annexe?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at New National Market Annexe?

The professionals named in the filing: Architect: Consultants Combined Architects; Engineer: SK Consultants & Engineers; Chartered Accountant: Rutuja Narsingh & Associates; Chartered Accountant: NB Sayed & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in New National Market Annexe?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About New National Market Annexe. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save New National Market Annexe to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.