Home / Browse projects / Mumbai Suburban, Maharashtra / Neumec godawari

Registered No litigation declared Residential / Group Housing project

Neumec godawari

By NEUMEC ESTATE DEVELOPER LLP

RG-MH-19659 · RERA P51800005145 · Last updated on MahaRERA portal: 28 Sep 2026

Source: official MahaRERA filing

Red flags

  • 4 complaints at MahaRERA
  • Completion date moved by 93 months
  • 4 extensions taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 93 months from the original
9 of 11Construction stages donefurthest along: Basement (if any), 0%
12 of 19Units unsoldnot recorded sold or booked
4Complaints at MahaRERAon this registration
Jump to the 124 documents Report an error

Neumec godawari is a Residential / Group Housing project by NEUMEC ESTATE DEVELOPER LLP in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800005145 on 9 Aug 2017. Possession is promised by 31 Dec 2026. The completion date has moved by 93 months from the original filing. 7 of the 19 units on this registration are recorded sold or booked, and 9 of 11 construction stages are filed complete. 4 complaints are on record with the regulator.

At a glance

Project

  • NameNeumec godawari
  • TypeResidential / Group Housing
  • Location
    • Shradhanand Road
    • Vile Parle
    • Andheri
    • Mumbai Suburban
    • 400057
  • Pincode400057
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800005145
  • ReraGenie IDRG-MH-19659

Builder

  • NameNEUMEC ESTATE DEVELOPER LLP
  • Entity typeOthers
  • GSTIN27AAHFN6978R1Z2
  • PartnersRAJESH JAIN, NILESH GUNJAL, NEUMEC DEVELOPMENT AND ALLIED SERVICES PVT LTD, DIYUG CONSTRUCTION PVT LTD
  • Other registrations1 more →
  • Declared earlier projects1 →

Key dates

this monthRegisteredAug 2017First promiseMar 2019Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on9 Aug 2017
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 31 Mar 2019)
  • Buildings1 building record
  • Documents filed124 files

Current status

37%7 of 19 units booked
100.0%Work done, per cost certificate

Figures as on 28 Sep 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
NEUMEC GODAWARINA161419019

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 28 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 0%.

NEUMEC GODAWARI: 82% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 28 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed29

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots29
Closed/Covered14
Open Space15

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area434 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
Declared on24 Sep 2024

Approvals and building plan

Sanctioning authorityMCGM
Permissible FSI1388.08
Proposed, not sanctioned1,285 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch66/80, Mumbai Samachar Marg, Post Bag No 253 and 518 ,Fort Mumbai, 400023
Estimated costRs 5.25 cr
Cost incurredRs 5.25 cr
Work done100.0%
BuildingWingEstimatedIncurred
NEUMEC GODAWARINARs 4.99 crRs 4.99 cr
-NARs 26.25 lakhRs 26.25 lakh

Certifying professionals and partners9

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSynergy Architects and Consultants
ArchitectVikas Abhang & Associates
ArchitectPremal Gogri
EngineerNexus Consultants and Engineers
EngineerS K Consultants & Engineers
Chartered AccountantN B Sayed & Associates
Chartered AccountantVikas Abhang & Associates
Chartered AccountantAnkita Pawar & Co. Chartered Accountant
Chartered AccountantCA Rutuja Narsingh & Associates
PartnerRole in project
NEUMEC ESTATE DEVELOPER LLP-

Extensions applied for4

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800002045Mar 2019 → Mar 2020

Reason as filed by the promoterDELAY IN GETTING HEIGHT APPROVAL AND GETTING BUILDING PLAN APPROVAL DUE TO IMPLEMENTATION OF NEW DP

EXT51800011055Mar 2019 → Sep 2022

Reason as filed by the promoterIn accordance with circular no 28, we hereby apply for extension of the project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of pandemic of Covid-19.

EXT51800024545Mar 2019 → Dec 2025

Reason as filed by the promoterIn accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have received Part OC for our project, the OC is pending for only 14th floor, the consent of which has been taken for extension.

EA09092622496Mar 2019 → Dec 2026

Reason as filed by the promoterThe project has been delayed as the Part Occupation Certificate for the completed portions has been received, while the balance certificate is pending due to remaining finishing, development work, and approval-related issues. Necessary efforts are being made to complete the pending work and obtain the required approvals at the earliest. We kindly request an extension up to 31-12-2026 to.

Complaints filed with MahaRERA4

Case no.ComplainantRespondentFiled
CC006000000057841Vibhas Acharekarrajesh jain30/01/2019
CC006000000194391vibhas acharekarGHEWARCHAND JAIN/RAJESH JAIN22/10/2020
CC12601060NEUMEC ESTATE DEVELOPER LLPMr Prakash Yeshwant Vadhavkar (Deceased) through its legal heirs Dr Saiprasad Prakash Vadhavkar26/02/2026
CC12606065Anant Abaji RaneNEUMEC ESTATE DEVELOPER LLP18/09/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 25 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 24 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 10 Mar 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 10 Mar 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 7 Aug 2024

Documents filed124

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 124 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 5 (FY 2025-2026)File: Form-5 Neumec Godawari For FY 2025-26.pdf28 Sep 2026
Withdrawal Update Form 1File: Form 1 - Neumec Godawari as on March 2026.pdf17 Sep 2026
Withdrawal Update Form 1File: Form 1 - Neumec Godawari June 2026.pdf17 Sep 2026
Withdrawal Update Form 2File: Form 2 - Neumec Godawari as on March 2026.pdf17 Sep 2026
Withdrawal Update Form 2File: Form 2 - Neumec Godawari June 2026.pdf17 Sep 2026
Withdrawal Update Form 3File: Form 3 - Neumec Godawari as on March 2026.pdf17 Sep 2026
Withdrawal Update Form 3File: Form 3 - Neumec Godawari June 2026.pdf17 Sep 2026
Form 5 (FY 2024-2025)File: Neumec_Godawari_Form5_2024-25_07-08-2026_11-45.pdf8 Sep 2026
Form 2A (FY 2024-2025)File: Form 2A FY 2024-25.pdf10 Aug 2026
Form 2A (FY 2025-2026)File: Form 2A FY 2025-26.pdf10 Aug 2026
Withdrawal Update Form 1File: Form 1 - Neumec Godawari as on March 2026.pdf31 Jul 2026
Withdrawal Update Form 1File: Form 1 - Neumec Godawari as on March 2026.pdf31 Jul 2026
Withdrawal Update Form 1File: Form 1 - Neumec Godawari as on March 2026.pdf31 Jul 2026
Withdrawal Update Form 2File: Form 2 - Neumec Godawari as on March 2026.pdf31 Jul 2026
Withdrawal Update Form 2File: Form 2 - Neumec Godawari as on March 2026.pdf31 Jul 2026
Withdrawal Update Form 2File: Form 2 - Neumec Godawari as on March 2026.pdf31 Jul 2026
Withdrawal Update Form 3File: Form 3 - Neumec Godawari as on June 2025.pdf31 Jul 2026
Withdrawal Update Form 3File: Form 3 - Neumec Godawari as on Sep 2025.pdf31 Jul 2026
Withdrawal Update Form 3File: Form 3 - Neumec Godawari as on Dec 2025.pdf31 Jul 2026
Certificates of CA (Form 3)File: Form 3 - Neumec Godawari as on March 2025.pdf5 May 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Neumec Godawari as on March 2025.pdf5 May 2025
Certificates of CA (Form 3)File: Form 3 of Neumec Godawari as on 31-12-2024.pdf18 Jan 2025
Certificates of CA (Form 3)File: Form 3 of Neumec Godawari as on 31-12-2024.pdf18 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Neumec Godawari as on 31-12-2024.pdf18 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Neumec Godawari Sept 2024.pdf17 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM_1_Neumec_Godawari-20243.pdf16 Oct 2024
Certificates of CA (Form 3)File: Form 3 Sep 24.pdf15 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Sep 24.pdf15 Oct 2024
Disclosure of sold/ booked inventoryFile: Circular 29 30-09-2024.pdf15 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 23-24.pdf15 Oct 2024
Certificates of CA (Form 3)File: Form 3 of Neumec Godawari as on 30-06-2024.pdf14 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Neumec Godawari June 2024.pdf14 Oct 2024
Disclosure of sold/ booked inventoryFile: Document 135.pdf8 Oct 2024
Certificates of CA (Form 3)File: Form_3_-_Neumec_Godawari_as_on_March_2024_11zon.pdf7 Oct 2024
Certificates of CA (Form 3)File: Form 3 Signed.pdf7 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form_2_-_Neumec_Godawari_as_on_March_2024_11zon.pdf7 Oct 2024
Declaration in FORM BFile: AFFIDAVIT_CUM_DECLARATION_-_NEDLLP.pdf10 Aug 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form2A_2019-20-1.pdf10 Aug 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form2A_2022-23-1.pdf10 Aug 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form2A_2023-24-1.pdf10 Aug 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: ANNEXURE_A___FORMAT_N.pdf10 Aug 2024
Declaration about all RERA Designated Bank Accounts (Format A)File: FORMAT_A.pdf10 Aug 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 2404141_OC_signed_240712_182640 Neumec Godawari.pdf7 Aug 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project) (1).pdf16 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 16 Certificates of Engineer (Form 2)(Mandatory for only ongoing project).pdf16 Jul 2024
Certificates of CA (Form 3)File: 16 Certificates of CA (Form 3).pdf16 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Neumec Godawari as on March 2024.pdf4 Jun 2024
Certificates of CA (Form 3)File: Form 3 - Neumec Godawari as on March 2024.pdf4 Jun 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Dec.pdf29 Feb 2024
Certificates of CA (Form 3)File: Form 3 Dec.pdf29 Feb 2024
Certificates of CA (Form 5)File: Form 5 2017-18.pdf29 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 2018-19.pdf29 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 2019-20.pdf29 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 2020-21.pdf29 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 2021-22.pdf29 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 2022-23.pdf29 Feb 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Neumec Godawari Dec 2023.pdf17 Jan 2024
Certificates of CA (Form 3)File: Form 3 of Neumec Godawari as on 31-12-2023 (1).pdf17 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Neumec Godawari Sep 2023 - Form 2.pdf7 Nov 2023
Certificates of CA (Form 3)File: Form 3 of Neumec Godawari as on 30-09-2023.pdf2 Nov 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 FY22-23 - Neumec Godawari.pdf22 Sep 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A Neumec Godawari- 2021-22.pdf25 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2- Neumec Godawari as on June 2023.pdf21 Jul 2023
Certificates of CA (Form 3)File: Form 3 of Neumec Godawari as on 30-06-2023.pdf21 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Neumec Godawari Mar 23 - Form 2.pdf28 Apr 2023
Certificates of CA (Form 3)File: Form 3- Neumec Godawari as on 31-03-2023.pdf28 Apr 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2- Neumec Godawari as on December 2022.pdf2 Feb 2023
Certificates of CA (Form 3)File: Form 3- Neumec Godawari as on December 2022.pdf2 Feb 2023
Disclosure of sold/ booked inventoryFile: Circular 29- Neumec Godawari.pdf11 Jan 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Neumec Godawari Form 2- September 2022.pdf25 Nov 2022
Certificates of CA (Form 3)File: Form 3- Neumec Godawari as on September 2022.pdf25 Nov 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5_Neumec Godawari_FY 2021-22.pdf1 Oct 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Neumec Godawari Form 2- March 2022.pdf1 Sep 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Neumec Godawari Form 2- June 2022.pdf1 Sep 2022
Certificates of CA (Form 3)File: Form 3 Certificate 191.pdf1 Sep 2022
Certificates of CA (Form 3)File: Form 3 Neumec Godawari- June 2022.pdf1 Sep 2022
Declaration about Commencement CertificateFile: Godawari-_Form_D_2022.pdf27 Apr 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT_CERTIFICATE -Godawari.pdf8 Apr 2022
Building plan approvalFile: Further Drawing.pdf10 Mar 2022
Building Plan Approval (IOD)File: Further Drawing.pdf10 Mar 2022

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 not delivered by the promised date
ProjectLocationFlatsRegisteredStatusPromisedDelivered
Neumec SrushtiP51800002532Barve Nagar Bhatwadi, Mumbai Suburban133Aug 2017OngoingJun 2025Registered original: Jun 2022Not delivered

How this compares with Mumbai Suburban

37%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 93 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Neumec godawari on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Vile Parle6,700+ in Mumbai Suburban

2 kmNeumec godawariCompleted 156Lapsed / revoked 73Other 144Dot size: filed unitsN

Filed coordinates, straight-line distance. 373 registered projects within 2 km.

Builder: NEUMEC ESTATE DEVELOPER LLP

NEUMEC ESTATE DEVELOPER LLP has 2 registrations on MahaRERA, including Neumec Srushti and Neumec godawari. Its filings disclose 1 earlier MahaRERA project, none completed yet. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if Neumec godawari is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Neumec godawari?

The registered promoter entity is NEUMEC ESTATE DEVELOPER LLP, an others as per the filing. Its GSTIN 27AAHFN6978R1Z2 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Neumec godawari?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Neumec godawari?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Neumec godawari?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Neumec godawari?

The professionals named in the filing: Architect: Synergy Architects and Consultants; Architect: Vikas Abhang & Associates; Architect: Premal Gogri; Engineer: Nexus Consultants and Engineers; Engineer: S K Consultants & Engineers; Chartered Accountant: N B Sayed & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Neumec godawari?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Neumec godawari. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Neumec godawari to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.