Home / Browse projects / Mumbai Suburban, Maharashtra / Neumec Srushti

Registered No litigation declared Residential / Group Housing project

Neumec Srushti

By NEUMEC ESTATE DEVELOPER LLP

RG-MH-01009 · RERA P51800002532 · Last updated on MahaRERA portal: 2 Jul 2025

Source: official MahaRERA filing

Red flags

  • Completion date moved by 66 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedmoved 66 months from the original
10 of 22Construction stages doneacross 2 buildings; furthest along: Internal walls, 93%
182 of 293Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 133 documents Report an error

Neumec Srushti is a Residential / Group Housing project by NEUMEC ESTATE DEVELOPER LLP in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800002532 on 1 Aug 2017. Possession is promised by 31 Dec 2027. The completion date has moved by 66 months from the original filing. 111 of the 293 units on this registration are recorded sold or booked, and 10 of 22 construction stages are filed complete.

At a glance

Project

  • NameNeumec Srushti
  • TypeResidential / Group Housing
  • Location
    • Ram Joshi Marg
    • Barve Nagar Bhatwadi
    • Kurla
    • Mumbai Suburban
    • 400084
  • Pincode400084
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800002532
  • ReraGenie IDRG-MH-01009

Builder

  • NameNEUMEC ESTATE DEVELOPER LLP
  • Entity typeOthers
  • GSTIN27AAHFN6978R1Z2
  • GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • PartnersRAJESH JAIN, NILESH GUNJAL, NEUMEC DEVELOPMENT AND ALLIED SERVICES PVT LTD, DIYUG CONSTRUCTION PVT LTD
  • Other registrations1 more →
  • Declared earlier projects1 →

Key dates

this monthRegisteredAug 2017First promiseJun 2022Revised toDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on1 Aug 2017
  • Promised completion31 Dec 2027
  • Revised completionRevised to 31 Dec 2027 (originally 30 Jun 2022)
  • Buildings2 building records
  • Documents filed133 files

Current status

38%111 of 293 units booked

Figures as on 2 Jul 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
NEUMEC SRUSHTI SALE BUILDINGNA1191078115
NEUMEC SRUSHTI REHAB BUILDINGNA10101780178

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 2 Jul 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Internal walls, at 93%.

NEUMEC SRUSHTI SALE BUILDING65%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure63%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises48%
Sanitary Fittings within the flats / premises45%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks15%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.40%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.5%
NEUMEC SRUSHTI REHAB BUILDING81%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure92%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises93%
Sanitary Fittings within the flats / premises85%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks30%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%

Progress on shared amenities15

As on 2 Jul 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes10%
Water SupplyYes33%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes75%
Storm Water DrainsYes58%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntYes0%
Fire protection and fire safety requirementsYes17%
Electrical meter room, sub-station, receiving stationYes33%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed58

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots58
Closed/Covered27
Open Space31
BuildingClosed/CoveredOpen SpaceTotal
NEUMEC SRUSHTI SALE BUILDING263157
NEUMEC SRUSHTI REHAB BUILDING101

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area5,262 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authoritySlum Rehabilitation Authority
Permissible FSI10279.44
Proposed, not sanctioned7,325 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchFort, Mumbai - 400001

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
Chartered AccountantPranav Bhaskaran & Associates
PartnerRole in project
NEUMEC ESTATE DEVELOPER LLP-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800011026Jun 2022 → Jun 2023

Reason as filed by the promoterIn accordance with circular no 28, we hereby apply for extension of the project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of pandemic of Covid-19.

EXT51800017330Jun 2022 → Jun 2025

Reason as filed by the promoterIn accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 56.76% allottees for purpose of extension of RERA registration period of the said project.

EXT51800028410Jun 2022 → Dec 2027

Reason as filed by the promoterI, hereby apply for extension as per Order No. 40 Dated 27/12/2022 of the registered project bearing vide no P51800002532 .As per HEARING DATED 25th June 2025, Hon'ble Shri Manoj Saunik Sir granted Extension upto 31/12/2027. The order is uploaded in Other Tab for your reference

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 25 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 25 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 25 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 25 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed133

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 133 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Declaration in FORM BFile: Form B 2027.pdf2 Jul 2025
Other - TechnicalFile: PERT_Overview.pdf2 Jul 2025
Declaration in FORM BFile: Affidavit_cum_declaration.pdf30 May 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM_1 (1).pdf30 May 2025
Certificates of CA (Form 3)File: Form_3_11zon.pdf30 May 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM_2_11zon.pdf30 May 2025
Disclosure of sold/ booked inventoryFile: Circular_29.pdf30 May 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: Format_A.pdf30 May 2025
Other - TechnicalFile: PERT Chart - NS.pdf30 May 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure_-_A.pdf30 May 2025
Certificates of CA (Form 3)File: Form 3 (December 2024)_compressed.pdf18 Feb 2025
Certificates of CA (Form 3)File: Form 3 - Sept 2024_compressed.pdf18 Feb 2025
Certificates of CA (Form 3)File: Form 3 - June 2024_compressed.pdf18 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Dec 2024_compressed.pdf18 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Dec 2024_compressed.pdf18 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Sept 2024_compressed.pdf18 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - June 2024_compressed.pdf18 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - June 2024 - Neumec Srushti.pdf17 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Sept 2024_compressed.pdf17 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Dec 2024_compressed.pdf17 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - March 2024_11zon.pdf17 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A 2019-20.pdf17 Feb 2025
Disclosure of sold/ booked inventoryFile: Circular 29 - Dec 2024.pdf17 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 2022-23 compressed.pdf17 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A 2023-24.pdf17 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 2023-24_compressed.pdf17 Feb 2025
Certificates of CA (Form 3)File: Form 3 of Neumec Srushti as on 30-09-2024_compressed.pdf3 Feb 2025
Certificates of CA (Form 3)File: Form 3 of Neumec Srushti as on 31-12-2024_compressed.pdf3 Feb 2025
Certificates of CA (Form 3)File: Form 3 of Neumec Srushti as on 30-06-2024_compressed.pdf3 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Neumec Srushti as on June 2024.pdf3 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Neumec Srushti as on Dec 2024.pdf3 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Neumec Srushti as on Sep 2024.pdf3 Feb 2025
Certificates of CA (Form 3)File: DECLARATION - to be uploaded before Form 3.pdf27 Jan 2025
Certificates of CA (Form 3)File: Dec 2024_compressed.pdf20 Jan 2025
Certificates of CA (Form 3)File: Sep 2024.pdf20 Jan 2025
Certificates of CA (Form 3)File: June 2024.pdf20 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 Neumec Srushti FY 2023-24.pdf22 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 Neumec Srushti FY 2023-24.pdf22 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project).pdf16 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 17 Certificates of Engineer (Form 2)(Mandatory for only ongoing project).pdf16 Jul 2024
Certificates of CA (Form 3)File: 20 Certificates of CA (Form 3).pdf16 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Neumec Srushti - March 2024.pdf4 Jun 2024
Certificates of CA (Form 3)File: Form 3 of Neumec Srushti as on 31-03-2024.pdf4 Jun 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Neumec Srushti as on Dec 2023.pdf30 Mar 2024
Certificates of CA (Form 3)File: Form 3 - Neumec Srushti as on Dec 2023.pdf30 Mar 2024
Certificates of CA (Form 3)File: March 18.pdf20 Mar 2024
Certificates of CA (Form 3)File: March 19.pdf20 Mar 2024
Certificates of CA (Form 3)File: March 20.pdf20 Mar 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1- Neumec Srushti as on September 2023.pdf30 Nov 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2- Neumec Srushti as on 30-06-2023.pdf7 Nov 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2- Neumec Srushti as on 30-09-2023.pdf7 Nov 2023
Certificates of CA (Form 3)File: Form 3 of Neumec Srushti as on 30-06-2023.pdf2 Nov 2023
Certificates of CA (Form 3)File: Form 3 of Neumec Srushti as on 30-09-2023.pdf2 Nov 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 Neumec Srushti FY 2022-23_Final.pdf29 Sep 2023
Declaration about Commencement CertificateFile: Declaration_about_CC.pdf11 Aug 2023
Declaration in FORM BFile: Affidavit_Cum_Declartion.pdf11 Aug 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf11 Aug 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A 22-23.pdf11 Aug 2023
Disclosure of sold/ booked inventoryFile: Circular_29_-_sold___unsold_srushti.pdf11 Aug 2023
Certificates of CA (Form 3)File: CA Certificate.pdf11 Aug 2023
Annual Audit Report of Statutory CA (Form 5)File: FORM 5 17-18.pdf11 Aug 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5 18-19.pdf11 Aug 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 5 19-20.pdf11 Aug 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5 20-21.pdf11 Aug 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5 20-21.pdf11 Aug 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5 21-22.pdf11 Aug 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A Neumec Srushti- 2021-22.pdf25 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2- Neumec Srushti as on 31-03-2023.pdf17 Jun 2023
Certificates of CA (Form 3)File: Form 3- Neumec Srushti as on 31-03-2023.pdf17 Jun 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5- Neumec Srushti as on 2018-19.pdf8 Apr 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2- Neumec Srushti as on December 2022.pdf2 Feb 2023
Certificates of CA (Form 3)File: Form 3- Neumec Srushti as on December 2022.pdf2 Feb 2023
Disclosure of sold/ booked inventoryFile: Circular 29- Neumec Srushti_compressed.pdf11 Jan 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2- Neumec Srushti as on September 2022.pdf25 Nov 2022
Certificates of CA (Form 3)File: Form 3- Neumec Srushti as on September 2022.pdf25 Nov 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1- Neumec Srushti.pdf24 Nov 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Neumec Srushti Form 5.pdf1 Oct 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 31st March 2022.pdf30 Aug 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 30th June 2022.pdf30 Aug 2022
Certificates of CA (Form 3)File: Form 3 Certificate 192.pdf30 Aug 2022

How this compares with Mumbai Suburban

38%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 66 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Neumec Srushti on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Barve Nagar Bhatwadi6,700+ in Mumbai Suburban

2 kmNeumec SrushtiCompleted 71Lapsed / revoked 49Other 72Dot size: filed unitsN

Filed coordinates, straight-line distance. 192 registered projects within 2 km.

Builder: NEUMEC ESTATE DEVELOPER LLP

NEUMEC ESTATE DEVELOPER LLP has 2 registrations on MahaRERA, including Neumec Srushti and Neumec godawari. Its filings disclose 1 earlier MahaRERA project, none completed yet. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if Neumec Srushti is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Neumec Srushti?

The registered promoter entity is NEUMEC ESTATE DEVELOPER LLP, an others as per the filing. Its GSTIN 27AAHFN6978R1Z2 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Neumec Srushti?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Neumec Srushti?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Neumec Srushti?

The professionals named in the filing: Chartered Accountant: Pranav Bhaskaran & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Neumec Srushti?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Neumec Srushti. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Neumec Srushti to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.