Home / Browse projects / Mumbai Suburban, Maharashtra / ARKADE PEARL 1

Registered Litigation declared Residential / Group Housing project

ARKADE PEARL 1

By ARKADE DEVELOPERS LIMITED

RG-MH-07093 · RERA P51800054195 · Last updated on MahaRERA portal: 20 May 2026

Source: official MahaRERA filing

Red flags

  • Litigation declared, 1 case

Clear

  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • All 11 earlier projects delivered on promise

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedno revision filed
15 of 33Construction stages doneacross 3 buildings; furthest along: Internal walls, 98%
54 of 88Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 87 documents Report an error

ARKADE PEARL 1 is a Residential / Group Housing project by ARKADE DEVELOPERS LIMITED in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800054195 on 3 Jan 2024. Possession is promised by 31 Dec 2026. 34 of the 88 units on this registration are recorded sold or booked, and 15 of 33 construction stages are filed complete.

At a glance

Project

  • NameARKADE PEARL 1
  • TypeResidential / Group Housing
  • Location
    • 18.30 M WIDE SHAHAJI RAJE ROAD
    • VILE PARLE
    • Vileparle
    • Andheri
    • Mumbai Suburban
    • 400057
  • Pincode400057
  • RERA no.P51800054195
  • ReraGenie IDRG-MH-07093

Builder

  • NameARKADE DEVELOPERS LIMITED
  • Entity typeCompany
  • DirectorsAMIT MANGILAL JAIN, ARPIT VIKRAM JAIN
  • Other registrations8 more →
  • Declared earlier projects19 →

Key dates

this monthRegisteredJan 2024PromisedDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on3 Jan 2024
  • Promised completion31 Dec 2026
  • Revised completionNone
  • Buildings3 building records
  • Documents filed87 files

Current status

39%34 of 88 units booked
89.8%Work done, per cost certificate

Figures as on 20 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
B WINGNA8824024
C WINGNA8832032
D WINGNA8832032

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 20 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

15 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Internal walls, at 98%.

B WING64%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises31%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.76%
C WING64%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises98%
Sanitary Fittings within the flats / premises31%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.74%
D WING62%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises31%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.97%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.64%

Progress on shared amenities15

As on 20 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes70%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes75%
Storm Water DrainsYes80%
Landscaping & Tree PlantingYes75%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes80%
Water conservation /Rain water harvestingYes75%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes80%
Electrical meter room, sub-station, receiving stationYes85%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area4,153 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on2 Jul 2025
LandownerVillageDistrict
Prachi Co-Operative Housing Society LimitedVileparleMumbai Suburban

Approvals and building plan

Sanctioning authorityMCGM
Permissible FSI12502.14
Proposed, not sanctioned4,511 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchshop no 54 55 saraf choudhary nagar thakur complex mumbai 400101
Estimated costRs 47.85 cr
Cost incurredRs 42.95 cr
Work done89.76%
BuildingWingEstimatedIncurred
D WINGNARs 15.40 crRs 14.87 cr
C WINGNARs 14.98 crRs 14.42 cr
B WINGNARs 9.46 crRs 9.22 cr
-NARs 8.01 crRs 4.43 cr

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectA R DESIGN STUDIO
ArchitectKALAKRUTI ARCHITECT AND PLANNER
EngineerGokani Consultants & Engineers LLP
EngineerJignesh Mohan Patel
Chartered AccountantAmit T JAIN & CO
Chartered AccountantSantosh B Morge & Co
Chartered AccountantMittal & Associates
PartnerRole in project
ARKADE DEVELOPERS LIMITED-

Litigation declared1

CaseCourtStatus
2079/2023Bombay city civil court at dindoshi goregaonOngoing

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 15 Dec 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 10 Nov 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 10 Nov 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 5 Nov 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed87

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 87 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2025-2026)File: Form 2a arkade pearl 1 mar 26.pdf20 May 2026
Withdrawal Update Form 1File: FORM-1 Pearl 1 Mar 26.pdf12 May 2026
Withdrawal Update Form 2File: Form 2 Pearl 1 mar 26.pdf12 May 2026
Withdrawal Update Form 3File: Form 3 Pearl 1 Mar 26_R.pdf12 May 2026
Withdrawal Update Form 1File: Form 1 Pearl 1 Dec 25.pdf30 Jan 2026
Withdrawal Update Form 2File: Form 2 Pearl 1 Dec 25.pdf30 Jan 2026
Withdrawal Update Form 3File: Form 3 Pearl 1 Dec 25_compressed.pdf30 Jan 2026
Form 5 (FY 2024-2025)File: Form 5 Arkade Pearl 1 24-25.pdf17 Dec 2025
Withdrawal Update Form 1File: Form 1 Pearl 1 Sep 25.pdf29 Oct 2025
Withdrawal Update Form 2File: Arkade Pearl 1 Sept 25.pdf29 Oct 2025
Withdrawal Update Form 3File: Arkade Pearl 1Sept 25.pdf29 Oct 2025
Withdrawal Update Form 1File: Form 1 Pearl 1 to June 2025.pdf6 Aug 2025
Withdrawal Update Form 2File: Arkade Pearl 1 Form 2 Jun 25.pdf6 Aug 2025
Withdrawal Update Form 3File: Arkade Pearl 1 - Final.pdf6 Aug 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Pearl 1 Form 3 Mar 25_compressed.pdf28 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Arkade Pearl 1 Mar 25.pdf19 Apr 2025
Disclosure of sold/ booked inventoryFile: Sold and unsold pearl 1 mar 25.pdf11 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form_2A_Pearl1 Mar 25.pdf11 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Pearl BCD wing Mar 25.pdf5 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_Arkade Pearl 1 R Dec 24.pdf5 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_Arkade Pearl 1 Dec 24.pdf12 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Pearl 3 Form 3 Dec 24.pdf28 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Pearl 1 Dec 2024.pdf17 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Pearl 1 Dec 24.pdf14 Jan 2025
Disclosure of sold/ booked inventoryFile: Pearl 1 Inventory declaration dec 24.pdf14 Jan 2025
Disclosure of sold/ booked inventoryFile: Pearl 1 Sep 24.pdf7 Nov 2024
Commencement Certificates / NA Order for plotted developmentFile: CC revalidation Pearl.pdf5 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Pearl 1 Form 3 S_compressed.pdf22 Oct 2024
Commencement Certificates / NA Order for plotted developmentFile: 2439592Amendletter_signed.pdf22 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Pearl 1 Sept 24.pdf19 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Arkade Pearl-Form 5-FY 24.pdf15 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Pearl BCD Sep 2024.pdf14 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Pearl June 2024.pdf30 Jul 2024
Disclosure of sold/ booked inventoryFile: Pearl 1 Sold unsold declaration jun 24.pdf30 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Pearl 1 Jun 24_final_compressed.pdf30 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Pearl 1 Jun 24.pdf13 Jul 2024
Disclosure of sold/ booked inventoryFile: Sold Unsold Mar 24 Pearl 1-_compressed.pdf14 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Arkade Pearl 1 March 24.pdf10 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Peal 1 Mar 24-compressed.pdf10 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Pearl March 2024.pdf11 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A Arkade Pearl March 24.pdf10 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Arkade Pearl Dec 23.pdf31 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Arkade Pearl Dec 23.pdf31 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Dec 23 Pearl 1.pdf24 Jan 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Self Declaration for interest in other real estate_Ketu Jain.pdf26 Dec 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Self Declaration for interest in other real estate_Hiren Tanna.pdf26 Dec 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Self Declaration for interest in other real estate_Neha Huddar.pdf26 Dec 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Self Declaration for interest in other real estate_Abhishek Dev.pdf26 Dec 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Self Declaration for Interest in other org - Amit Jain.pdf21 Dec 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Self Declaration for Interest in other org - Arpit Jain.pdf21 Dec 2023
Copy of the legal title reportFile: Pearl RERA Title Report r.pdf15 Dec 2023
Details of encumbrances concerned to FinanceFile: Financial Encumbrance Letter - Arkade Pearl 1.pdf2 Dec 2023
Details of encumbrances concerned to FinanceFile: Litigation Encumbrance Letter - Arkade Pearl 1.pdf2 Dec 2023
Details of encumbrances concerned to LegalFile: Financial Encumbrance Letter - Arkade Pearl 1.pdf2 Dec 2023
Details of encumbrances concerned to LegalFile: Litigation Encumbrance Letter - Arkade Pearl 1.pdf2 Dec 2023
Declaration about Commencement CertificateFile: Revised CC Declaration - Arkade Pearl 1.pdf2 Dec 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration for Separate Bank Account Details - Arkade Pearl 1.pdf2 Dec 2023
Declaration in FORM BFile: Form B - Declaration by Promoter - New.pdf22 Nov 2023
CERSAI detailsFile: cersai pearl 1.pdf17 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Arkade Pearl 1_compressed.pdf17 Nov 2023
Proforma of Agreement for saleFile: Draft AFS - Pearl part 1.pdf17 Nov 2023
Proforma of Agreement for saleFile: Draft AFS - Pearl - part 2.pdf17 Nov 2023
Proforma of Allotment letterFile: Allotment letter draft - Pearl.pdf17 Nov 2023
Deviation Report with respect to Allotment letterFile: Deviation in Allotment Letter - Pearl.pdf17 Nov 2023
Deviation Report with respect to model copy of AgreementFile: Deviation report - AFS Pearl.pdf17 Nov 2023
Layout approvalFile: 2388248Amendletter_signed.pdf10 Nov 2023
Building plan approvalFile: 1_11zon.pdf10 Nov 2023
Building plan approvalFile: 2_11zon.pdf10 Nov 2023
Building plan approvalFile: 4_11zon.pdf10 Nov 2023
Building plan approvalFile: 5_11zon.pdf10 Nov 2023
Building plan approvalFile: 6_11zon.pdf10 Nov 2023
Building plan approvalFile: 9_11zon.pdf10 Nov 2023
Building plan approvalFile: 10_11zon.pdf10 Nov 2023
Building plan approvalFile: 11_11zon.pdf10 Nov 2023
PAN CardFile: ADL Pan Card.pdf10 Nov 2023
Details of encumbrances concerned to FinanceFile: Litigation Encumbrance Letter - Arkade Pearl.pdf10 Nov 2023
Details of encumbrances concerned to LegalFile: Litigation Encumbrance Letter - Arkade Pearl.pdf10 Nov 2023
Copy of Layout Approval (in case of layout)File: 2388248Amendletter_signed.pdf10 Nov 2023
Building Plan Approval / NA Order for plotted developmentFile: 1_11zon.pdf10 Nov 2023
Building Plan Approval / NA Order for plotted developmentFile: 2_11zon.pdf10 Nov 2023

Promoter's earlier projects11

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

11 delivered on promise
ProjectLocationFlatsRegisteredStatusPromisedDelivered
Arkade SereneP51800029961Sunder Nagar Malad West, Mumbai Suburban-Jul 2021CompletedJun 2024Feb 2023
ARKADE SERENSUNDER NAGAR MALA WEST MUMBAI 6410-CompletedJun 2024Feb 2023
ARKADE EARTH-CARNATIONP51800014422Kanjurmarg East, Mumbai Suburban-Nov 2017CompletedDec 2023Apr 2021
ARKADE EARTH-ASPENP51800006579Kanjurmarg East, Mumbai Suburban-Aug 2017CompletedDec 2023Apr 2021
ARKADE EARTH- BLUEBELLP51800011586Kanjurmarg East, Mumbai Suburban-Aug 2017CompletedDec 2023Apr 2021
DARSHANDARSHAN VILE PARLE EAST MUMBAI 5710-CompletedJun 2023Nov 2022
ARKADE EARTH-DAFFODILP51800004440Kanjurmarg East, Mumbai Suburban-Aug 2017CompletedDec 2022Feb 2020
ARKADE EARTH - HAZELP51800022666KANJURMARG EAST, Mumbai Suburban-Oct 2019CompletedDec 2022Apr 2022
ARKADE EARTH - GARDENIAP51800010074Kanjurmarg East, Mumbai Suburban-Aug 2017Certificate SignedDec 2022Feb 2020
ARKADE EARTH - FERNP51800004750Kanjurmarg East, Mumbai Suburban-Aug 2017Certificate SignedDec 2022Feb 2020
ARKADE EARTH - EBONYP51800008953Kanjurmarg East, Mumbai Suburban-Aug 2017CompletedDec 2022Feb 2020

How this compares with Mumbai Suburban

39%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one has not
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep ARKADE PEARL 1 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near VILE PARLE6,700+ in Mumbai Suburban

Builder: ARKADE DEVELOPERS LIMITED

ARKADE DEVELOPERS LIMITED has 9 registrations on MahaRERA, including ARKADE PEARL 1 and Arkade Eden. Its filings disclose 19 earlier MahaRERA projects: declares 19 of 19 past projects completed on time. Litigation is declared on 7 of its registrations. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if ARKADE PEARL 1 is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of ARKADE PEARL 1?

The registered promoter entity is ARKADE DEVELOPERS LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in ARKADE PEARL 1?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for ARKADE PEARL 1?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at ARKADE PEARL 1?

The professionals named in the filing: Architect: A R DESIGN STUDIO; Architect: KALAKRUTI ARCHITECT AND PLANNER; Engineer: Gokani Consultants & Engineers LLP; Engineer: Jignesh Mohan Patel; Chartered Accountant: Amit T JAIN & CO; Chartered Accountant: Santosh B Morge & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ARKADE PEARL 1?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ARKADE PEARL 1. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ARKADE PEARL 1 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.