ReraGenieLog inGet a buyer report

Home / Browse projects / Thane, Maharashtra / Neelkanth Woods Building K 52

Completed No litigation declared Residential / Group Housing project

Neelkanth Woods Building K 52

By T Bhimjyani Realty Pvt.Ltd.

RG-MH-89923 · RERA P51700018023 · Last updated on MahaRERA portal: 17 Sep 2022

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 8 other registrations.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Nov 2021Possession promisedregistration recorded completed
10 of 11Construction stages donefurthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 29 documents Report an error

Neelkanth Woods Building K 52 is a Residential / Group Housing project by T Bhimjyani Realty Pvt.Ltd. in Thane, Maharashtra, registered with MahaRERA as P51700018023 on 5 Oct 2018. The registration is recorded completed; possession was promised by 28 Nov 2021.

At a glance

Project

  • NameNeelkanth Woods Building K 52
  • TypeResidential / Group Housing
  • Location
    • Mullabaug
    • Majiwade
    • Thane (M Corp.)
    • Thane
    • 400610
  • Pincode400610
  • RERA no.P51700018023
  • ReraGenie IDRG-MH-89923

Builder

  • NameT Bhimjyani Realty Pvt.Ltd.
  • Entity typeCompany
  • CINU70100MH2011PTC222048
  • GSTIN27SAFCR4733FIZE
  • CIN and GSTIN are from this promoter's other MahaRERA registrations. This project's own filing does not repeat them.
  • DirectorDEVANG TULSI BHIMJYANI
  • Other registrations8 more →
  • Completed5 of 9
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

this monthRegisteredOct 2018PromisedNov 2021Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on5 Oct 2018
  • Promised completion28 Nov 2021
  • Revised completionNone
  • Buildings1 building record
  • Documents filed29 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Neelkanth Woods Bungalow K 52NA30000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 17 Sep 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

Neelkanth Woods Bungalow K 52: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities24

As on 17 Sep 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingNoNot applicable
Common Mini Basket Ball CourtYes100%
Common Swimming Pool and Common Jacuzzi and Common Kids PoolYes100%
Fitness CentreYes0%
Table Tennis Room in Common Club HouseYes100%
Squash court in Common Club HouseYes100%
Spa with changing facilties in Common Club HouseYes100%
Snooker Room in Common Club HouseYes100%
Multi Purpose Hall with Badminton Court in Common Club HouseYes100%
Gymnasium in Common Club HouseYes100%

Parking filed2

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots2
Closed/Covered2

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area652 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI267.45
Proposed, not sanctioned267 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchB wing, 1st floor, Laxmi Tower, Bandra Kurla Complex, Bandra East, Mumbai 400051

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSaakaar Architects
ArchitectSterling Engg Consultancy Services Pvt Ltd
ArchitectECON Pollution Control Consultants
PartnerRole in project
T Bhimjyani Realty Pvt.Ltd.-

Litigation declared3

CaseCourtStatus
CARBP/75/2017Bombay High CourtConciliation Mediation Agreement has been executed to settle outstanding disputes btwn the parties
CP/401/2016Bombay High CourtConciliation Mediation Agreement has been executed to settle outstanding disputes btwn the parties
SC 5099/2016Supreme Court Of IndiaConciliation Mediation Agreement has been executed to settle outstanding disputes btwn the parties

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Jul 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Jul 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 12 Sep 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 31 Jul 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 16 Aug 2021

Documents filed29

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of Architect (Form 4)File: Form 4 - K 52.pdf17 Sep 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OCCUPANCY CERTIFICATE - Villa 52 - 17 10 2018.pdf16 Aug 2021
Certificates of Architect (Form 4)File: Form 4 - K 52.pdf16 Nov 2018
OtherFile: OCCUPANCY CERTIFICATE - Villa 52- 17 10 2018.pdf16 Nov 2018
Building plan approvalFile: Building layout (1).pdf12 Sep 2018
Building Plan Approval (IOD)File: Building layout (1).pdf12 Sep 2018
Details of encumbrancesFile: Form B - K 52 compressed.pdf29 Aug 2018
Declaration in FORM BFile: Form B - K 52 compressed.pdf29 Aug 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificate.pdf28 Aug 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers certificate.pdf28 Aug 2018
Proforma of Allotment letterFile: Bungalow K 52-AFS Part 1.pdf28 Aug 2018
Proforma of Allotment letterFile: Bungalow K 52-AFS Part 2.pdf28 Aug 2018
OtherFile: Board Resolution K 52.pdf28 Aug 2018
OtherFile: Development Agreement.pdf28 Aug 2018
OtherFile: Power of Attorney.pdf28 Aug 2018
Certificates of CA (Form 3)File: Form 3 - CA Certificate.pdf1 Aug 2018
Building plan approvalFile: IOD-52.PDF31 Jul 2018
Layout approvalFile: Master Layout.pdf31 Jul 2018
Layout approvalFile: ANNEXURE - A- LAYOUT-52.pdf31 Jul 2018
PAN CardFile: T BHIMJYANI-PAN.pdf31 Jul 2018
Copy of the legal title reportFile: Title Certificate.pdf31 Jul 2018
Copy of Layout Approval (in case of layout)File: Master Layout.pdf31 Jul 2018
Copy of Layout Approval (in case of layout)File: ANNEXURE - A- LAYOUT-52.pdf31 Jul 2018
Building Plan Approval (IOD)File: IOD-52.PDF31 Jul 2018
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate 52.pdf31 Jul 2018
OtherFile: Appeal against Society order.pdf31 Jul 2018
OtherFile: Consent Terms.pdf31 Jul 2018
OtherFile: Name Change Certificates.pdf31 Jul 2018
OtherFile: Society Order.pdf31 Jul 2018

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 not delivered by the promised date
ProjectLocationRegisteredStatusPromisedDelivered
Neelkanth Woods OliviaP51700004591Thane (M Corp.), ThaneAug 2017OngoingMay 2021Not delivered

How this compares with Thane

24%of Thane projects moved their completion datethis one has not
23%of Thane registrations have lapsed or been cancelledthis one is completed

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Neelkanth Woods Building K 52 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Majiwade7,600+ in Thane

Builder: T Bhimjyani Realty Pvt.Ltd.

T Bhimjyani Realty Pvt.Ltd. has 9 registrations on MahaRERA, including Neelkanth Woods Olivia and Neelkanth Woods Bungalow M 66. Its filings disclose 1 earlier MahaRERA project, none completed yet. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if Neelkanth Woods Building K 52 is delayed beyond 28 Nov 2021?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Neelkanth Woods Building K 52?

The registered promoter entity is T Bhimjyani Realty Pvt.Ltd., a company as per the filing. Its CIN U70100MH2011PTC222048 and GSTIN 27SAFCR4733FIZE can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Neelkanth Woods Building K 52?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Neelkanth Woods Building K 52?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Neelkanth Woods Building K 52?

The professionals named in the filing: Architect: Saakaar Architects; Architect: Sterling Engg Consultancy Services Pvt Ltd; Architect: ECON Pollution Control Consultants. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Neelkanth Woods Building K 52?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Neelkanth Woods Building K 52. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Neelkanth Woods Building K 52 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.