Home / Browse projects / Thane, Maharashtra / INFINITY TOWERS
INFINITY TOWERS
By T Bhimjyani Realty Pvt.Ltd.
RG-MH-04402 · RERA P51700021698 · Last updated on MahaRERA portal: 22 Jun 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Litigation declared, 9 cases
- 18 complaints at MahaRERA
- Completion date moved by 16 months
- 1 extension taken
- Rs 450.00 crore secured on the land, in favour of Siddhant Commercials Pvt Ltd
- The declared charge does not appear in the CERSAI report on the filing
Clear
- Separate project account declared
- Allotment letter follows the model form
6 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
INFINITY TOWERS is a Residential / Group Housing project by T Bhimjyani Realty Pvt.Ltd. in Thane, Maharashtra, registered with MahaRERA as P51700021698 on 19 Jul 2019. Possession is promised by 28 Dec 2026. The completion date has moved by 16 months from the original filing. 389 of the 443 units on this registration are recorded sold or booked, and 13 of 33 construction stages are filed complete. 18 complaints are on record with the regulator.
At a glance
Project
- NameINFINITY TOWERS
- TypeResidential / Group Housing
- Location
- MULLABAUG MANPADA GHODBUNDER ROAD
- MAJIWADE
- Thane (M Corp.)
- Thane
- 400610
- Pincode400610
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51700021698
- ReraGenie IDRG-MH-04402
Builder
- NameT Bhimjyani Realty Pvt.Ltd.
- Entity typeCompany
- CINU70100MH2011PTC222048
- GSTIN27SAFCR4733FIZE
- CIN and GSTIN are from this promoter's other MahaRERA registrations. This project's own filing does not repeat them.
- DirectorDEVANG TULSI BHIMJYANI
- Other registrations8 more →
- Completed5 of 9
- No longer live2 lapsed, de-registered or revoked
- Declared earlier projects1 →
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on19 Jul 2019
- Promised completion28 Dec 2026
- Revised completionRevised to 28 Dec 2026 (originally 28 Aug 2025)
- Buildings3 building records
- Documents filed111 files
Current status
Figures as on 22 Jun 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| INFINITY A | NA | 45 | 41 | 160 | 0 | 160 |
| INFINITY B | NA | 45 | 41 | 160 | 0 | 160 |
| INFINITY C | NA | 45 | 41 | 123 | 0 | 123 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building3
As on 22 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
13 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Staircases, at 90%.
INFINITY A78%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 85% |
| Sanitary Fittings within the flats / premises | 60% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 90% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 70% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 50% |
INFINITY B75%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 90% |
| Sanitary Fittings within the flats / premises | 70% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 90% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 70% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
INFINITY C53%
| Activity | Progress |
|---|---|
| Excavation | 85% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 70% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 45% |
| Sanitary Fittings within the flats / premises | 20% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 20% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 45% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 22 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 5% |
| Fire protection and fire safety requirements | Yes | 20% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
Parking filed3
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| INFINITY A | 1 | 1 |
| INFINITY B | 1 | 1 |
| INFINITY C | 1 | 1 |
Land and ownership
A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| INFINITY A | NA | Rs 98.86 cr | Rs 87.44 cr |
| INFINITY B | NA | Rs 98.86 cr | Rs 87.44 cr |
| INFINITY C | NA | Rs 98.86 cr | Rs 87.44 cr |
| - | NA | Rs 2.05 cr | Rs 2.05 cr |
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | SAAKAAR ARCHITECT |
| Engineer | NARROTAM R KUMAR |
| Chartered Accountant | JAYESH S VORA |
| Partner | Role in project |
|---|---|
| T Bhimjyani Realty Pvt.Ltd. | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterPromoter has proposed certain changes in the layout and submitted to corporation.Promoter got approval of Corporation.Because of change in layout area and floors are increased.Promoter need some time to complete the said project.Promoter obtained necessary consent for parties.Promoter hereby assure that grant of extension of the project validity shall not affect.
Litigation declared9
| Case | Court | Status |
|---|---|---|
| 299/2015/2015 | THANE | Ongoing |
| CC12400807/2024 | RERA AUTHORITY BANDRA | Ongoing |
| CC12500102/2025 | RERA AUTHORITY BANDRA | Ongoing |
| CC12500986/2025 | RERA BANDRA AUTHORITY | Ongoing |
| CC12501293/2025 | RERA ATHORITY BANDRA | Ongoing |
| CC12501974/2025 | RERA AUTHORITY BANDRA | Ongoing |
| CC12501975/2025 | RERA AUTHORITY BANDRA | Ongoing |
| CC1250216/2025 | RERA AUTHORITY BANDRA | Ongoing |
| CC12502269/2025 | RERA AUTHORITY BANDRA | Ongoing |
Complaints filed with MahaRERA18
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000196369 | Rahul Tejraj Solanki | T Bhimjyani Realty Pvt Ltd | 20/03/2021 |
| CC12500102 | Tanmaya Mohan Panda | T Bhimjyani Realty Pvt.Ltd. | 11/01/2025 |
| CC12400807 | Dharmesh Nathalal Hirpara | T Bhimjyani Realty Pvt.Ltd. | 17/11/2024 |
| CC12500129 | T BHIMJYANI REALTY PVT LTD | VINAY CHEMBAKASHERI | 14/01/2025 |
| CC12500524 | T Bhimjyani Realty Pvt.Ltd. | RUSTAM PATEL | 15/02/2025 |
| CC12500544 | T Bhimjyani Realty Pvt.Ltd. | RUSTAM PATEL | 17/02/2025 |
| CC12500546 | T Bhimjyani Realty Pvt.Ltd. | RUSTAM PATEL | 17/02/2025 |
| CC12500547 | T Bhimjyani Realty Pvt.Ltd. | RUSTAM PATEL | 17/02/2025 |
| CC12500986 | PARAG PRAFUL LAKHANI | T Bhimjyani Realty Pvt.Ltd. | 21/03/2025 |
| CC12501293 | sujeet phadke | T Bhimjyani Realty Pvt.Ltd. | 19/04/2025 |
| CC12501974 | Ankush Ravibhushan Handa | T Bhimjyani Realty Pvt.Ltd. | 17/06/2025 |
| CC12501975 | Ankush Ravibhushan Handa | T Bhimjyani Realty Pvt.Ltd. | 17/06/2025 |
| CC12502116 | Shailendra Pramod Shekatkar | T Bhimjyani Realty Pvt.Ltd. | 27/06/2025 |
| CC12502269 | Chetan Govindrao Shenvi | T Bhimjyani Realty Pvt.Ltd. | 06/07/2025 |
| CC12503885 | T BHIMJYANI REALTY PVT LTD | PREEETI NAIK | 06/11/2025 |
| CC12603903 | T Bhimjyani Realty Pvt.Ltd. | SUBHAVATI YADAV | 24/06/2026 |
| CC12603906 | T Bhimjyani Realty Pvt.Ltd. | SUYASH SAKHALKAR | 24/06/2026 |
| CC12603914 | T Bhimjyani Realty Pvt.Ltd. | RABINDRANATH CHATTERJEE | 24/06/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 14 Jul 2019 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 9 Feb 2024 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 14 Jul 2019 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 2 Feb 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 28 Dec 2026
Documents filed111
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 111 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1 - Architects Certificate (Infinity).pdf | 22 Jun 2026 |
| Withdrawal Update Form 2File: Infinity Towers Form 2.pdf | 22 Jun 2026 |
| Withdrawal Update Form 3File: Infinity Towers FORM 3 MAR 2026.pdf | 22 Jun 2026 |
| Form 1File: Form 1 Architects Certificate 31-12-2025.pdf | 21 Jan 2026 |
| Form 2File: Form 2 - 15-12-2025.pdf | 21 Jan 2026 |
| Form 3File: RERA Form 3 Infinity Towers- for 31-12-2025 Final.pdf | 21 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Inventory.pdf | 21 Jan 2026 |
| Form 1File: Architects Certificate Form 1 March 2025.pdf | 19 Jan 2026 |
| Form 2File: Form 2 Engineers Certificate Infinity Towers March 2025.pdf | 19 Jan 2026 |
| Form 3File: RERA Form 3 Infinity Towers March.pdf | 19 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Inventory final.pdf | 19 Jan 2026 |
| Form 1File: Architect Certificate Form 1 - Dt 30-6-2025.pdf | 19 Jan 2026 |
| Form 2File: Engineers Certificate Form 2 for 30-06-2025.pdf | 19 Jan 2026 |
| Form 3File: RERA Form 3 Infinity Towers 30-06-2025.pdf | 19 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Inventory final.pdf | 19 Jan 2026 |
| Form 1File: Architect Certificate Form 1 - Dt-30-9-2025.pdf | 19 Jan 2026 |
| Form 2File: Engineers Certificate Form 2 for 30-09-2025.pdf | 19 Jan 2026 |
| Form 3File: RERA Form 3 Infinity Towers for 30-09-2025 final.pdf | 19 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Inventory final.pdf | 19 Jan 2026 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A- March 2024.pdf | 5 May 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A- June 2024.pdf | 5 May 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A- September 2024.pdf | 5 May 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A- March 2025.pdf | 5 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Architects Certificate Mar 25.pdf | 2 May 2025 |
| Certificates of CA (Form 3)File: Form 3 31 Dec 2024.pdf | 11 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 31 Dec 2024.pdf | 11 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 December 2024.pdf | 1 Feb 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A June 2023.pdf | 1 Feb 2025 |
| Certificates of CA (Form 3)File: Form 3 June 2024.pdf | 22 Jan 2025 |
| Certificates of CA (Form 3)File: Form 3 September 2024.pdf | 22 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 June 2024.pdf | 22 Jan 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Infinity Towers - Form 5 23-24.pdf | 7 Jan 2025 |
| Proforma of Agreement for saleFile: Agreement for Sale.pdf | 4 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Architects Certificate.pdf | 16 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Infinity Tower.pdf | 11 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 (Tower DEF) - 9-8-2024.pdf | 13 Aug 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 2AJUNE22.pdf | 26 Mar 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 2A JUNE23.pdf | 26 Mar 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22).pdf | 21 Mar 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22).pdf | 21 Mar 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22).pdf | 21 Mar 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22).pdf | 21 Mar 2024 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: FORMAT A.pdf | 14 Mar 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: 2A-19.pdf | 7 Mar 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 2A-MARCH 21.pdf | 7 Mar 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 2A-SEPT21.pdf | 7 Mar 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 2A-MARCH 22.pdf | 7 Mar 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 2A-SEPT 22.pdf | 7 Mar 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: 2A- 20.pdf | 20 Feb 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: 2A-19.pdf | 20 Feb 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 2A-21.pdf | 20 Feb 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 2A-JUNE 21.pdf | 20 Feb 2024 |
| Layout approvalFile: APPROVED MUNCIPAL PLAN TB.pdf | 9 Feb 2024 |
| Copy of Layout Approval (in case of layout)File: APPROVED MUNCIPAL PLAN TB.pdf | 9 Feb 2024 |
| Layout approvalFile: APPROVED MUNCIPAL PLAN February 2024.pdf | 6 Feb 2024 |
| Copy of Layout Approval (in case of layout)File: APPROVED MUNCIPAL PLAN February 2024.pdf | 6 Feb 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate - Infinity Feb 2024.pdf | 2 Feb 2024 |
| Declaration in FORM BFile: FORM B -Infinity Towers REVISED DATE OF POSSESSION.pdf | 2 Feb 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Infinity tower - Form 5.pdf | 2 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Engineers Certificate (1).pdf | 30 Nov 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A.pdf | 30 Nov 2023 |
| Certificates of CA (Form 3)File: 5 Certificate of CA (Form 3)1-7_compressed.pdf | 24 Nov 2023 |
| Certificates of CA (Form 3)File: 5 Certificate of CA (Form 3)8-14.pdf | 24 Nov 2023 |
| Details of encumbrances concerned to FinanceFile: LEGAL ENCUMBRANCE.pdf | 22 Nov 2023 |
| Details of encumbrances concerned to LegalFile: LEGAL ENCUMBRANCE.pdf | 22 Nov 2023 |
| Details of encumbrances concerned to FinanceFile: Details of Encumbrances.pdf | 20 Nov 2023 |
| Details of encumbrances concerned to LegalFile: Details of Encumbrances.pdf | 20 Nov 2023 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory (2).pdf | 20 Nov 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Engineers Certificate 2021.pdf | 1 Nov 2023 |
| PAN CardFile: Pancard.pdf | 9 Oct 2023 |
| Declaration about Commencement CertificateFile: Declaration - Commencement Certificate.pdf | 9 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architects Certificate April 2023.pdf | 7 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Sept 2019 (RERA).pdf | 7 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Dec 2019_(RERA).pdf | 7 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - March 2020_(RERA).pdf | 7 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 DEF - June 2020_(RERA).pdf | 7 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 DEF - June 2021_(RERA).pdf | 7 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22) .pdf | 7 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM - 5 FY 21-22.pdf | 7 Sep 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Engineers Certificate March 2022.pdf | 29 Aug 2023 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|
| Neelkanth Woods OliviaP51700004591 | Thane (M Corp.), Thane | Aug 2017 | Ongoing | May 2021 | Not delivered |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Thane
Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.
Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 6 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 8 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 111 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep INFINITY TOWERS on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near MAJIWADE7,600+ in Thane
Filed coordinates, straight-line distance. 23 registered projects within 2 km.
OGC Thane Phase 1
Oberoi Realty Limited
Mahavir Spring -Daffodils-P3
Vinayak Developers
Mahavir Spring - Tulip - Phase 1
Vinayak Developers
RAUNAK BLISS B1
UNNATHI ASSOCIATES
Raunak Bliss B4
UNNATHI ASSOCIATES
Raunak Bliss B5
UNNATHI ASSOCIATES
See every Thane project, with the district possession charts
Builder: T Bhimjyani Realty Pvt.Ltd.
T Bhimjyani Realty Pvt.Ltd. has 9 registrations on MahaRERA, including Neelkanth Woods Olivia and Neelkanth Woods Bungalow M 66. Its filings disclose 1 earlier MahaRERA project, none completed yet. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What are my rights if INFINITY TOWERS is delayed beyond 28 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of INFINITY TOWERS?
The registered promoter entity is T Bhimjyani Realty Pvt.Ltd., a company as per the filing. Its CIN U70100MH2011PTC222048 and GSTIN 27SAFCR4733FIZE can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in INFINITY TOWERS?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against INFINITY TOWERS?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for INFINITY TOWERS?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at INFINITY TOWERS?
The professionals named in the filing: Architect: SAAKAAR ARCHITECT; Engineer: NARROTAM R KUMAR; Chartered Accountant: JAYESH S VORA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in INFINITY TOWERS?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback