Completed No litigation declared Residential / Group Housing project

NEELKANTH TIRTH CO. OP. HOUSING SOC. LTD.

By MAVERICK REALTORS

RG-MH-88973 · RERA P51800012145 · Last updated on MahaRERA portal: 13 Mar 2024

Source: official MahaRERA filing

Red flags

  • Completion date moved by 28 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Oct 2023Possession promisedregistration recorded completed
10 of 11Construction stages donefurthest along: Installation of Lifts, 90%
0Complaints at MahaRERAon this registration
Jump to the 53 documents Report an error

NEELKANTH TIRTH CO. OP. HOUSING SOC. LTD. is a Residential / Group Housing project by MAVERICK REALTORS in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800012145 on 1 Sep 2017. The registration is recorded completed; possession was promised by 31 Oct 2023. The completion date has moved by 28 months from the original filing.

At a glance

Project

  • NameNEELKANTH TIRTH CO. OP. HOUSING SOC. LTD.
  • TypeResidential / Group Housing
  • Location
    • MULUND
    • MUMBAI
    • Kurla
    • Mumbai Suburban
    • 400080
  • Pincode400080
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800012145
  • ReraGenie IDRG-MH-88973

Builder

  • NameMAVERICK REALTORS
  • Entity typeOthers
  • PartnersHARSH PARESH SHAH, TUSHAR BABULAL KUVADIA
  • Named personsPARESH KANTILAL SHAH, HARSH PARESH SHAH, TUSHAR BABULAL KUVADIA, Maverick Real Estate Pvt Ltd
  • Other registrations8 more →
  • Completed2 of 9
  • No longer live3 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

this monthRegisteredSep 2017First promiseJun 2021Revised toOct 2023Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on1 Sep 2017
  • Promised completion31 Oct 2023
  • Revised completionRevised to 31 Oct 2023 (originally 30 Jun 2021)
  • Buildings1 building record
  • Documents filed53 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
NEELKANTH TIRTH CHS LTDNA250000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 13 Mar 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 90%.

NEELKANTH TIRTH CHS LTD: 99% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%

Progress on shared amenities15

As on 13 Mar 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%

Parking filed65

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots65
Closed/Covered65

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,588 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI5360.27
Proposed, not sanctioned4,943 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHANKARDHAN PLAZA,OPP MEHUL CINEMA,JUNCTION OF M M ROAD AND NAHUR ROADMULUND WESTMUMBAI-400 080

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectV. S. VAIDYA & ASSOCIATES
EngineerGAUTAM CHANDE
EngineerPravin Pitale Corporate Engineers
Chartered AccountantS K RAMBHIA & ASSOCIATES
Chartered AccountantSachin Sunil and Associates
PartnerRole in project
MAVERICK REALTORS-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800009516Jun 2021 → Jun 2022

Reason as filed by the promoterOn account of restrictions imposed on Construction activities and Real Estate sector due to Covid 19 since Mar’ 2020 & thereafter due to low demand & overall slowdown in economy, in Real Estate Sector there is a delay in completion of Project. And due to the same it is expected that Project would get completed by Sep 2021 and Occupancy Certificate shall be obtained on or before 31st May 2022. Kindly, therefore, grant extension till 30th June, 2022

EXT51800012932Jun 2021 → Oct 2023

Reason as filed by the promoterIt’s a redevelopment project on account of restrictions imposed on Construction activities and Real Estate sector due to Covid 19 since Mar’ 2020 & thereafter due to low demand & overall slowdown in economy, in Real Estate Sector there is a delay in completion of Project. And due to the same it is expected that Project would get completed by Aug’ 2023 and Occupancy Certificate shall be obtained on or before 30th Sep’ 2023. Kindly, therefore, grant extension till 31st Oct, 2023.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 26 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 28 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 28 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 12 Dec 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 29 Feb 2024

Documents filed53

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate on Completion of Project (Form 4)File: NKT From 4 Sign Done.pdf13 Mar 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: NEELKANTH TRITH.pdf29 Feb 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: NEELKANTH TRITH.pdf29 Feb 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: NEELKANTH TRITH DSC.pdf29 Feb 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: NEELKANTH TRITH DSC.pdf29 Feb 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: From 2 NKT 31122022 comp.pdf29 Feb 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 NKT comp.pdf29 Feb 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 NeelkanthTirth com.pdf29 Feb 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: NKT Mar23 Form2Acompressed.pdf29 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: RERA Form-5_FY22-23_Neelkanth.pdf29 Feb 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: NEELKANTH TIRTH FULL OC20231228.pdf29 Feb 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form1NKT30092022.pdf31 Mar 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: NKTFrom230092022.pdf31 Mar 2023
Certificates of CA (Form 3)File: Form3Neelkanth30092022.pdf31 Mar 2023
Commencement Certificates / NA Order for plotted developmentFile: NKT CC.pdf12 Dec 2022
Declaration about Commencement CertificateFile: Declaration about CC NKT.pdf12 Dec 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A - 2020 NKT.pdf12 Dec 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A - 2021 NKT.pdf12 Dec 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A - 2022 NKT.pdf12 Dec 2022
Disclosure of sold/ booked inventoryFile: Disclosure of Inventory NKT.pdf12 Dec 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 Neelkanth (2018-19).pdf12 Dec 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 Neelkanth (2019-20).pdf12 Dec 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 Neelkanth (2020-21).pdf12 Dec 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 Neelkanth (2021-22).pdf12 Dec 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: NKT - J5148 C11 LS Certificate DT 31 03 2022 Form 1.pdf16 Jul 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: NKT Mar22 From2.pdf16 Jul 2022
Certificates of CA (Form 3)File: Neelkanth 31 03 22 Form 3.pdf16 Jul 2022
Details of encumbrancesFile: NKT RERA ENCUMBRANCES DECLARATION.pdf29 Nov 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 NKT.pdf9 Mar 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 NKT.pdf9 Mar 2021
Certificates of CA (Form 3)File: Form 3 - NKT.pdf3 Feb 2021
Certificates of CA (Form 3)File: Form 3.pdf14 Dec 2019
Certificates of CA (Form 5)File: Form 5 Neelkanth (2018-19).pdf6 Dec 2019
Certificates of CA (Form 5)File: Neelkanth Tirth CHS.pdf26 Oct 2018
Details of encumbrancesFile: No encumbrances NT.pdf29 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERT NT.pdf29 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: NEELKANTH TIRTH.pdf29 Jul 2017
Certificates of CA (Form 3)File: From 3 Neelkanth Tirth.pdf29 Jul 2017
Proforma of Allotment letterFile: Declaration of no Allotment Letter.pdf29 Jul 2017
Proforma of Allotment letterFile: Draft Agreement NT.PDF29 Jul 2017
Layout approvalFile: NEELKANTH C.pdf28 Jul 2017
Building plan approvalFile: CC.pdf28 Jul 2017
Building plan approvalFile: NEELKANTH C.pdf28 Jul 2017
Copy of Layout Approval (in case of layout)File: NEELKANTH C.pdf28 Jul 2017
Building Plan Approval (IOD)File: CC.pdf28 Jul 2017
Building Plan Approval (IOD)File: NEELKANTH C.pdf28 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: NEELKANTH C.pdf28 Jul 2017
Declaration in FORM BFile: Form B Neelkanth Tirth.pdf28 Jul 2017
Building plan approvalFile: IOA.pdf26 Jul 2017
PAN CardFile: PAN CARD_MAVERICK REALTORS.pdf26 Jul 2017
Copy of the legal title reportFile: TITLE CERTIFICATES-NEELKANTH TIRTH.pdf26 Jul 2017
Building Plan Approval (IOD)File: IOA.pdf26 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf26 Jul 2017

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
OM SAKTHIVALJI LADDHA ROAD MULUND WEST MUMBAI-40008031CompletedNov 2015Late, Dec 2019

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 28 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is completed

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep NEELKANTH TIRTH CO. OP. HOUSING SOC. LTD. on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near MUMBAI6,700+ in Mumbai Suburban

2 kmNEELKANTH TIRTH CO. OP. Completed 124Lapsed / revoked 97Other 153Dot size: filed unitsN

Filed coordinates, straight-line distance. 374 registered projects within 2 km.

Builder: MAVERICK REALTORS

MAVERICK REALTORS has 9 registrations on MahaRERA, including NEELKANTH TIRTH CO. OP. HOUSING SOC. LTD. and MAVERICK MOOLDEEP. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if NEELKANTH TIRTH CO. OP. HOUSING SOC. LTD. is delayed beyond 31 Oct 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of NEELKANTH TIRTH CO. OP. HOUSING SOC. LTD.?

The registered promoter entity is MAVERICK REALTORS, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in NEELKANTH TIRTH CO. OP. HOUSING SOC. LTD.?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for NEELKANTH TIRTH CO. OP. HOUSING SOC. LTD.?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at NEELKANTH TIRTH CO. OP. HOUSING SOC. LTD.?

The professionals named in the filing: Architect: V. S. VAIDYA & ASSOCIATES; Engineer: GAUTAM CHANDE; Engineer: Pravin Pitale Corporate Engineers; Chartered Accountant: S K RAMBHIA & ASSOCIATES; Chartered Accountant: Sachin Sunil and Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in NEELKANTH TIRTH CO. OP. HOUSING SOC. LTD.?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About NEELKANTH TIRTH CO. OP. HOUSING SOC. LTD.. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save NEELKANTH TIRTH CO. OP. HOUSING SOC. LTD. to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.