ReraGenieLog inGet a buyer report

Home / Browse projects / Thane, Maharashtra / NASCON MATOSHREE

Registered No litigation declared Residential / Group Housing project

NASCON MATOSHREE

By OMKAR DEVELOPERS

RG-MH-98765 · RERA P51700049858 · Last updated on MahaRERA portal: 4 May 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 16 other registrations and every project registered within 2 km.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedno revision filed
3 of 11Construction stages donefurthest along: Slabs of Super Structure, 80%
44 of 54Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 86 documents Report an error

NASCON MATOSHREE is a Residential / Group Housing project by OMKAR DEVELOPERS in Thane, Maharashtra, registered with MahaRERA as P51700049858 on 6 Mar 2023. Possession is promised by 31 Dec 2026. 10 of the 54 units on this registration are recorded sold or booked, and 3 of 11 construction stages are filed complete.

At a glance

Project

  • NameNASCON MATOSHREE
  • TypeResidential / Group Housing
  • Location
    • Karve Road
    • Navagaon Dombivli East
    • DOMBIVLI
    • Kalyan
    • Thane
    • 421202
  • Pincode421202
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700049858
  • ReraGenie IDRG-MH-98765

Builder

  • NameOMKAR DEVELOPERS
  • Entity typePartnership
  • PartnersArvind R Gupta, Jeetendra keshav Tokare, Mandakini Keshav Tokare, Nassir Akolawala, Varun Shailesh Tokare, Shailesh Keshav Tokare, Prakhar Arvind Gupta, Aziz Nassir Akolawala
  • Other registrations16 more →
  • Completed5 of 17
  • No longer live5 lapsed, de-registered or revoked

Key dates

this monthRegisteredMar 2023PromisedDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on6 Mar 2023
  • Promised completion31 Dec 2026
  • Revised completionNone
  • Buildings1 building record
  • Documents filed86 files

Current status

19%10 of 54 units booked
53.5%Work done, per cost certificate

Figures as on 4 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
NASCON MATOSHREENA1913292554

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 4 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 80%.

NASCON MATOSHREE: 41% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure80%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises15%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks60%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 4 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed82

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots82
Closed/Covered12
Open Space70

Land and ownership3

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area940 sq m
Land owned byThe promoter, with other names on the file
Named landowners3
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on23 Jan 2026
LandownerVillageDistrict
Vijaykumar Ganpatrao KagadePune (M Corp.)Pune
Sanjay Ganpatrao kagadeDOMBIVLIThane
Ajit Ganpatrao KagadeDOMBIVLIThane

Approvals and building plan

Permissible FSI5000.26
Proposed, not sanctioned3,574 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchsamrat vikramaditya bhavan swami vivekanand school ganesh mandir path nr nehru maidan dombivli east
Estimated costRs 14.50 cr
Cost incurredRs 7.75 cr
Work done53.45%
BuildingWingEstimatedIncurred
NASCON MATOSHREENARs 13.50 crRs 7.75 cr
-NARs 1.00 cr-

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSarvesh B Nandgirikar
EngineerAditya Deshmukh
Chartered AccountantCA Sagar Joshi
Chartered AccountantCHHAJED & DOSHI
PartnerRole in project
OMKAR DEVELOPERS-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 27 Dec 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 14 Dec 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 10 Apr 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 10 Apr 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed86

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 86 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form-1 Q4 Signed.pdf4 May 2026
Withdrawal Update Form 2File: Form-2 Q4 Signed.pdf4 May 2026
Withdrawal Update Form 3File: Form-3 Q4 Signed_compressed.pdf4 May 2026
Withdrawal Update Form 1File: Form 1-siged-Q3.pdf29 Apr 2026
Withdrawal Update Form 2File: Form -2-signed Q3.pdf29 Apr 2026
Withdrawal Update Form 3File: Form -3-signed- Q3_compressed.pdf29 Apr 2026
Withdrawal Update Form 1File: Form -1 -Signed-Q2.pdf5 Mar 2026
Withdrawal Update Form 2File: Form 2-Signed-Q2.pdf5 Mar 2026
Withdrawal Update Form 3File: Form 3-Signed-Q2.pdf5 Mar 2026
Withdrawal Update Form 1File: Form -1-Signed.pdf4 Mar 2026
Withdrawal Update Form 2File: Form 2-Signed.pdf4 Mar 2026
Withdrawal Update Form 3File: Form 3-Signed.pdf4 Mar 2026
Form 5 (FY 2024-2025)File: Audit Report And Form 5.pdf4 Oct 2025
Withdrawal Update Form 1File: Form-1 Omkar Q1.pdf30 Jul 2025
Withdrawal Update Form 2File: Form -2 Q1 Signed.pdf30 Jul 2025
Withdrawal Update Form 3File: Ca Certificate_compressed.pdf30 Jul 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-01 Q3.pdf27 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-03 Q3.pdf27 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-02 Q3.pdf27 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 Sep 24 R_compressed.pdf11 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Q2 - Omkar Developers.pdf3 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 (Q-2) Omkar Developers.pdf3 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Q2 - Omkar Developers.pdf3 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: IAR and Form 5 - Omkar Developers_compressed.pdf6 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 (Q-1) Omkar Developers_compressed.pdf12 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 Omkar Q1.pdf2 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate - Form 2 - Q1.pdf2 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECTS CERTIFICATE Q4.pdf26 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERTIFICATE Q4.pdf26 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 Q4.pdf26 Apr 2024
Building plan approvalFile: Omkar Plan-1.pdf10 Apr 2024
Building plan approvalFile: Omkar Plan-2.pdf10 Apr 2024
Building plan approvalFile: Omkar Plan-3.pdf10 Apr 2024
Building plan approvalFile: Omkar Plan-4.pdf10 Apr 2024
Building plan approvalFile: Omkar Plan-5.pdf10 Apr 2024
Building plan approvalFile: Omkar Plan-6.pdf10 Apr 2024
Building plan approvalFile: Omkar Plan-7.pdf10 Apr 2024
Building Plan Approval / NA Order for plotted developmentFile: Omkar Plan-1.pdf10 Apr 2024
Building Plan Approval / NA Order for plotted developmentFile: Omkar Plan-2.pdf10 Apr 2024
Building Plan Approval / NA Order for plotted developmentFile: Omkar Plan-3.pdf10 Apr 2024
Building Plan Approval / NA Order for plotted developmentFile: Omkar Plan-4.pdf10 Apr 2024
Building Plan Approval / NA Order for plotted developmentFile: Omkar Plan-5.pdf10 Apr 2024
Building Plan Approval / NA Order for plotted developmentFile: Omkar Plan-6.pdf10 Apr 2024
Building Plan Approval / NA Order for plotted developmentFile: Omkar Plan-7.pdf10 Apr 2024
Commencement Certificates / NA Order for plotted developmentFile: Commencement CERTIFICATE- REVISED.pdf10 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Omkar Q3.pdf6 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Omkar Q3.pdf2 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Omkar Q3.pdf2 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 Signed.pdf27 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 (Q2) - Omkar Developers.pdf27 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 (Q1) - Omkar Developers.pdf27 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 (Q2) - Omkar Developers.pdf27 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 (Q1) Omkar Developers.pdf27 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 (Q2) Omkar Developers.pdf27 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM-5 Omkar_to upload.pdf8 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Signed Form 01.pdf12 May 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf12 May 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Signed Form 03_compressed.pdf12 May 2023
Proforma of Agreement for saleFile: Draft Agreement.pdf1 Mar 2023
Deviation Report with respect to model copy of AgreementFile: Deviation_certificate_.pdf1 Mar 2023
Building plan approvalFile: 1 Plan Copy.pdf16 Feb 2023
Building plan approvalFile: 2 Plan Copy.pdf16 Feb 2023
Building plan approvalFile: 3 Plan Copy.pdf16 Feb 2023
Building plan approvalFile: 4 Plan Copy.pdf16 Feb 2023
Building plan approvalFile: 5 Plan copy.pdf16 Feb 2023
Building Plan Approval / NA Order for plotted developmentFile: 1 Plan Copy.pdf16 Feb 2023
Building Plan Approval / NA Order for plotted developmentFile: 2 Plan Copy.pdf16 Feb 2023
Building Plan Approval / NA Order for plotted developmentFile: 3 Plan Copy.pdf16 Feb 2023
Building Plan Approval / NA Order for plotted developmentFile: 4 Plan Copy.pdf16 Feb 2023
Building Plan Approval / NA Order for plotted developmentFile: 5 Plan copy.pdf16 Feb 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Scanned Partner Details Combined.pdf4 Jan 2023
Copy of the legal title reportFile: Legal_Title_Report_compressed.pdf27 Dec 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Omkar Developers Form 3.pdf15 Dec 2022
Layout approvalFile: 01.pdf14 Dec 2022
PAN CardFile: PAN Card.pdf14 Dec 2022
Details of encumbrances concerned to FinanceFile: Certificate of Encumbrances.pdf14 Dec 2022
Details of encumbrances concerned to LegalFile: Certificate of Encumbrances.pdf14 Dec 2022
Copy of Layout Approval (in case of layout)File: 01.pdf14 Dec 2022
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate Building Permission Sanction.pdf14 Dec 2022
Declaration about Commencement CertificateFile: Declaration certificate of CC.pdf14 Dec 2022

How this compares with Thane

19%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one has not
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep NASCON MATOSHREE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Navagaon Dombivli East7,600+ in Thane

2 kmNASCON MATOSHREECompleted 88Lapsed / revoked 72Other 115Dot size: filed unitsN

Filed coordinates, straight-line distance. 275 registered projects within 2 km.

Builder: OMKAR DEVELOPERS

Omkar Developers has 17 registrations on MahaRERA, including OMKAR APARTMENT and INDRAPRASTHA. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if NASCON MATOSHREE is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of NASCON MATOSHREE?

The registered promoter entity is OMKAR DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in NASCON MATOSHREE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for NASCON MATOSHREE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at NASCON MATOSHREE?

The professionals named in the filing: Architect: Sarvesh B Nandgirikar; Engineer: Aditya Deshmukh; Chartered Accountant: CA Sagar Joshi; Chartered Accountant: CHHAJED & DOSHI. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in NASCON MATOSHREE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About NASCON MATOSHREE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save NASCON MATOSHREE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.