Home / Browse projects / Palghar, Maharashtra / NARMADA MOHAN

Completed No litigation declared Residential / Group Housing project

NARMADA MOHAN

By K.M.DEVELOPERS

RG-MH-53920 · RERA P99000012568 · Last updated on MahaRERA portal: 9 Dec 2021

Source: official MahaRERA filing

Red flags

  • 4 complaints at MahaRERA
  • Completion date moved by 53 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA
  • All 1 earlier projects delivered on promise

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Dec 2022Possession promisedregistration recorded completed
9 of 11Construction stages donefurthest along: Installation of Lifts, 99%
4Complaints at MahaRERAon this registration
Jump to the 29 documents Report an error

NARMADA MOHAN is a Residential / Group Housing project by K.M.DEVELOPERS in Palghar, Maharashtra, registered with MahaRERA as P99000012568 on 4 Sep 2017. The registration is recorded completed; possession was promised by 30 Dec 2022. The completion date has moved by 53 months from the original filing. 4 complaints are on record with the regulator.

At a glance

Project

  • NameNARMADA MOHAN
  • TypeResidential / Group Housing
  • Location
    • VASAI LINK RD
    • DON BASCO SCHOOL
    • Vasai-Virar City (M Corp)
    • Vasai
    • Palghar
    • 401202
  • Pincode401202
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P99000012568
  • ReraGenie IDRG-MH-53920

Builder

  • NameK.M.DEVELOPERS
  • Entity typePartnership
  • PartnersREKHA RAMAKANT KADAM, SHWETA ASHISH KADAM
  • Other registrations5 more →
  • Completed3 of 6
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

this monthRegisteredSep 2017First promiseJul 2018Revised toDec 2022Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on4 Sep 2017
  • Promised completion30 Dec 2022
  • Revised completionRevised to 30 Dec 2022 (originally 31 Jul 2018)
  • Buildings1 building record
  • Documents filed29 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
NARMADA MOHANNA160000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 9 Dec 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 99%.

NARMADA MOHAN: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.99%

Progress on shared amenities15

As on 9 Dec 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes100%

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,626 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
SHABANALI JUMMANALI KHANMira-Bhayandar (M Corp.)Thane

Approvals and building plan

Permissible FSI4289.99
Proposed, not sanctioned4,290 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchARIHANT DARSHAN, 90 FT RD, BHAYANDAR WEST, DIST THANE 401101

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSANJAY S NARANG
EngineerSANJAY NARANG
PartnerRole in project
K.M.DEVELOPERS-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT99000002550Jul 2018 → Dec 2021

Reason as filed by the promoterDUE TO WETLANDS NOTIFICATION AS PER WETLAND ATLAS PREPARED BY CENTRAL GOVT. WE ARE NOT GETTING OCCUPATION CERTIFICATE FROM VVCMC (LOCAL MUNICIPAL CORPORATION), HOWEVER WE HAD COMPLETED ENTIRE PROJECT AND ALSO NEEDS TO REGISTER SOME UNSOLD INVENTORY FOR WHICH RERA EXTENDED CERTIFICATE IS COMPULSORY, THEREFORE WE WOULD REQUEST YOU TO PLEASE GRANT US EXTENSION TILL 31/12/2021

Complaints filed with MahaRERA4

Case no.ComplainantRespondentFiled
CC006000000057513Narmada Mohan payment issuesJash Associates/KM Developers03/01/2019
CC006000000079255Adesh TamattaSunil Mehta14/07/2019
CC006000000181989Vinod ErlaSunil Mheta27/12/2019
CC006000000196278Vinod ErlaK M Developers06/03/2021

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 2 Aug 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 2 Aug 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 2 Aug 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 13 Jan 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 9 Dec 2021

Documents filed29

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Narmada Mohan Occupation Certificate_compressed.pdf9 Dec 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: NARMADA MOHAN OCCUPATION CERTIFICATE19021_0002.pdf19 Sep 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Adobe Scan 18 Aug 2021.pdf18 Aug 2021
Disclosure of sold/ booked inventoryFile: INVENTORY DETAILS NM29062021.pdf29 Jun 2021
OtherFile: GOM WETLAND CLEARANCE LETTER.pdf11 Apr 2021
Proforma of Allotment letterFile: DRAFT AGREEMENT NARMADA MOHAN.pdf5 Apr 2021
Status of Formation of Legal Entity (Society/Co Op etc.)File: SOCIETY REGISTRATION CERTIFICATE.pdf5 Apr 2021
Certificates of CA (Form 3)File: Form-3_compressed (1).pdf18 Jan 2021
Architect’s Certificate on Completion of Project (Form 4)File: Adobe Scan Jan 16, 2021 (2).pdf18 Jan 2021
Architect’s Certificate on Completion of Project (Form 4)File: Adobe Scan Jan 16, 2021 (2).pdf18 Jan 2021
Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT CERTIFICATE_compressed_compressed.pdf13 Jan 2021
Annual Audit Report of Statutory CA (Form 5)File: FORM 5 01_compressed.pdf17 Oct 2019
Annual Audit Report of Statutory CA (Form 5)File: FORM 5 02_compressed.pdf17 Oct 2019
Layout approvalFile: LAYOUT NM.pdf2 Aug 2017
Building plan approvalFile: IOD PLAN 1.pdf2 Aug 2017
Building plan approvalFile: IOD PLAN 2.pdf2 Aug 2017
Building plan approvalFile: IOD PLAN 3.pdf2 Aug 2017
PAN CardFile: PAN CARD.pdf2 Aug 2017
Copy of the legal title reportFile: TITLE CERTIFICATE N-MOHAN.pdf2 Aug 2017
Details of encumbrancesFile: SELF DECLARATION REGARDING ENCUMBRANCES.pdf2 Aug 2017
Copy of Layout Approval (in case of layout)File: LAYOUT NM.pdf2 Aug 2017
Building Plan Approval (IOD)File: IOD PLAN 1.pdf2 Aug 2017
Building Plan Approval (IOD)File: IOD PLAN 2.pdf2 Aug 2017
Building Plan Approval (IOD)File: IOD PLAN 3.pdf2 Aug 2017
Declaration in FORM BFile: NM-FORMB DECLARTION.pdf2 Aug 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE FORM1.pdf2 Aug 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFICATE FORM 2.pdf2 Aug 2017
Certificates of CA (Form 3)File: Form 3 C A Certificate.pdf2 Aug 2017
Proforma of Allotment letterFile: NARMADA MOHAN - MOFA AGREEMENT.pdf2 Aug 2017

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
NARMADA MOHANS NO 351 VASAI NAIGAON LINK RD JUCHANDRANNAIGOAN EAST DIST PALGHAR143CompletedJul 2018Jul 2018

How this compares with Palghar

31%of Palghar projects moved their completion datethis one moved by 53 months
26%of Palghar registrations have lapsed or been cancelledthis one is completed

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep NARMADA MOHAN on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near DON BASCO SCHOOL3,200+ in Palghar

2 kmNARMADA MOHANCompleted 46Lapsed / revoked 30Other 56Dot size: filed unitsN

Filed coordinates, straight-line distance. 132 registered projects within 2 km.

Builder: K.M.DEVELOPERS

K M DEVELOPERS has 6 registrations on MahaRERA, including HORIZON PALMS II and NARMADA MOHAN. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What are my rights if NARMADA MOHAN is delayed beyond 30 Dec 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of NARMADA MOHAN?

The registered promoter entity is K.M.DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in NARMADA MOHAN?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against NARMADA MOHAN?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for NARMADA MOHAN?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at NARMADA MOHAN?

The professionals named in the filing: Architect: SANJAY S NARANG; Engineer: SANJAY NARANG. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in NARMADA MOHAN?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About NARMADA MOHAN. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save NARMADA MOHAN to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.