ReraGenieLog inGet a buyer report

Home / Browse projects / Aurangabad, Maharashtra / Nandan Vatika Wing B

Registered No litigation declared Residential / Group Housing project

Nandan Vatika Wing B

By Nandan Constructions

RG-MH-13427 · RERA P51500047993 · Last updated on MahaRERA portal: 19 Jul 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 15 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Aurangabad registration emailed to you, free during the pilot beta.
Mar 2027Possession promisedmoved 15 months from the original
7 of 11Construction stages donefurthest along: Sanitary Fittings within the flats /..., 85%
29 of 32Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 89 documents Report an error

Nandan Vatika Wing B is a Residential / Group Housing project by Nandan Constructions in Aurangabad, Maharashtra, registered with MahaRERA as P51500047993 on 7 Dec 2022. Possession is promised by 31 Mar 2027. The completion date has moved by 15 months from the original filing. 3 of the 32 units on this registration are recorded sold or booked, and 7 of 11 construction stages are filed complete.

At a glance

Project

  • NameNandan Vatika Wing B
  • TypeResidential / Group Housing
  • Location
    • Darga Road
    • Osmanpura
    • Aurangabad (M Corp.)
    • Aurangabad
    • 431001
  • Pincode431001
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51500047993
  • ReraGenie IDRG-MH-13427

Builder

  • NameNandan Constructions
  • Entity typePartnership
  • PartnersVallabh Nandlal Bagla, Subhashchandra Bansidhar Lahoti
  • Other registrations2 more →
  • Completed1 of 3

Key dates

this monthRegisteredDec 2022First promiseDec 2025Revised toMar 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on7 Dec 2022
  • Promised completion31 Mar 2027
  • Revised completionRevised to 31 Mar 2027 (originally 31 Dec 2025)
  • Buildings1 building record
  • Documents filed89 files

Current status

9%3 of 32 units booked
83.7%Work done, per cost certificate

Figures as on 19 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Wing BNA10832032

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 19 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 11 construction stages are filed complete. The stage furthest along is Sanitary Fittings within the flats / premises, at 85%.

Wing B: 86% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises85%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%

Progress on shared amenities15

As on 19 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes75%
Water SupplyYes70%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes60%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes80%
Street LightingYes60%
Community BuildingsYes90%
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes70%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes60%
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,036 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityAURANGABAD MUNICIPAL CORPORATION, AURANGABAD
Permissible FSI3128.08
Proposed, not sanctioned2,928 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchAurangabad
Estimated costRs 8.10 cr
Cost incurredRs 6.78 cr
Work done83.72%
BuildingWingEstimatedIncurred
Wing BNARs 7.35 crRs 6.17 cr
-NARs 75.00 lakhRs 60.75 lakh

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectManoj Kala & Associates
EngineerCore Consultants
EngineerADITYA ANIL PAWAR
Chartered AccountantD GABSS & Associates
Chartered AccountantJAIN & GANGWAL
PartnerRole in project
Nandan Constructions-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA16022619857Dec 2025 → Mar 2027

Reason as filed by the promoterdue to technial issues the project is delayed and it is near to completion and there is no sale in the project.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 4 Oct 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 4 Oct 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 4 Oct 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 6 Oct 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Mar 2027

Documents filed89

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 89 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: ARCHITECT CERT WING B.pdf19 Jul 2026
Withdrawal Update Form 2File: ENGINEERS CERT WING B.pdf19 Jul 2026
Withdrawal Update Form 3File: SELF DECLARATION WING B.pdf19 Jul 2026
Withdrawal Update Form 1File: W-B Form-1 March 26.pdf27 Jun 2026
Withdrawal Update Form 2File: W-B Form-2 March 26.pdf27 Jun 2026
Withdrawal Update Form 3File: W-B Form-3 March 26.pdf27 Jun 2026
Withdrawal Update Form 1File: 1 Form-1.pdf14 Feb 2026
Withdrawal Update Form 2File: 2 Form-2.pdf14 Feb 2026
Withdrawal Update Form 3File: 3 Form-3.pdf14 Feb 2026
Form 5 (FY 2022-2023)File: VATIKA WING B - FORM 5 22-23.pdf31 Jan 2026
Form 5 (FY 2023-2024)File: Nandan Vatika W-B Form-5 CA March 2024.pdf6 Nov 2025
Form 5 (FY 2024-2025)File: Nandan Vatika W- BForm-5 CA March 2025.pdf6 Nov 2025
Form 1File: Nandan Vatika W-B Form-1 Sep 2025.pdf5 Nov 2025
Form 2File: NAndan Vatika W-B Form-2 Sep 2025.pdf5 Nov 2025
Form 3File: Nandan Vatika W-B Form-3 Sep 2025.pdf5 Nov 2025
Disclosure of Sold and Booked InventoryFile: Nandan Vatika W-B Sold Sep 2025.pdf5 Nov 2025
Form 1File: 1 Form-1 June 25.pdf6 Aug 2025
Form 2File: 2 Form-2 June 25.pdf6 Aug 2025
Form 3File: 3 Form-3 June 25.pdf6 Aug 2025
Disclosure of Sold and Booked InventoryFile: 4 Sold June 25.pdf6 Aug 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 FORM 1 MAR 25.pdf3 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3 FORM 3 MAR 25.pdf3 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2 FORM 2 MAR 25.pdf3 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: B Form 1 Nandan Vatika W-B Form-1 19-01-25.pdf28 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: B Nandan Vatika W-B Form-3 Declaration 19-01-25.pdf28 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: B Form 2 Nandan Vatika W-B Form-2 19-01-25.pdf28 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Nandan Vatika W-B Form-Architects 19-Oct-24.pdf4 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Nandan Vatika W-B Form-3 Declaration 20-Oct-24.pdf4 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Nandan Vatika W-B Form-2 19-Oct-24.pdf4 Nov 2024
Disclosure of sold/ booked inventoryFile: Nandan Vatika W-B Sold 30-Sep-24.pdf4 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Nandan Vatika W-B Form-1 18-Jul-24.pdf18 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Nandan Vatika W-B Form-2 18-Jul-24.pdf18 Aug 2024
Disclosure of sold/ booked inventoryFile: Nandan Vatika W-B Sold 30-Jun-24.pdf18 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Nandan Vatika W-B Form-3 18-Jul-24.pdf18 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Nandan Vatika Form-1 14-April-24.pdf27 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Nandan Vatika Form-2 14-April-24.pdf27 Apr 2024
Disclosure of sold/ booked inventoryFile: Nandan Vatika Discloser 31-March-24.pdf27 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Nandan Vatika Form-3 14-April-24.pdf27 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 ( Wing B ) 11-01-2024.pdf19 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 ( Wing B ).pdf19 Jan 2024
Disclosure of sold/ booked inventoryFile: Sold Unsold ( Wing B ).pdf19 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Self Declaration ( Wing B ).pdf19 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architects Certificate Wing 'B'.pdf20 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Wing 'B' Form -2.pdf20 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Wing 'B' Form - 2A.pdf20 Oct 2023
Disclosure of sold/ booked inventoryFile: Disclosure Of Sold Wing 'B'.pdf20 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Wing B Form - 3.pdf20 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Wing 'B' Form 5.pdf20 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Wing B Architect certificate.pdf23 Sep 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Wing B Form- 2.pdf23 Sep 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Wing B Form -2A.pdf23 Sep 2023
Disclosure of sold/ booked inventoryFile: Wing B Disclosure Of Sold.pdf23 Sep 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Wing B chartered accountant certificate.pdf23 Sep 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Nandan vatika architect certificate_0003_1.pdf14 Sep 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Nandan vatika B_1.pdf14 Sep 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Nandan vatika architect certificate_0003_2.pdf14 Sep 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Nandan vatika B_2.pdf14 Sep 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Nandan vatika architect certificate_0003_3.pdf14 Sep 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Nandan vatika B_3.pdf14 Sep 2023
Disclosure of sold/ booked inventoryFile: Nandan vatika architect certificate_0003_4.pdf14 Sep 2023
Disclosure of sold/ booked inventoryFile: Nandan vatika B_4.pdf14 Sep 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form -3 Wing B.pdf14 Sep 2023
CERSAI detailsFile: CERSAI_Search_Report_200253159184_For_Asset_Based_Search_25_11_2022_11_26_43_214.pdf25 Nov 2022
Details of encumbrances concerned to FinanceFile: ENCUMB.pdf21 Oct 2022
Details of encumbrances concerned to FinanceFile: LEGAL ENCUMB.pdf21 Oct 2022
Details of encumbrances concerned to LegalFile: ENCUMB.pdf21 Oct 2022
Details of encumbrances concerned to LegalFile: LEGAL ENCUMB.pdf21 Oct 2022
Declaration about Commencement CertificateFile: DEC CC.pdf21 Oct 2022
Declaration in FORM BFile: Wing B_FORM B.pdf21 Oct 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Wing B_CA.pdf21 Oct 2022
Proforma of Allotment letterFile: allotmrnt letter new format.pdf21 Oct 2022
Proforma of Agreement for saleFile: model-agreement-to-be-entered-into-between-promoter-and-alottees-annexure-a.pdf21 Oct 2022
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: FORMAT A.pdf21 Oct 2022
Deviation Report with respect to Allotment letterFile: DEV IN ALLO.pdf21 Oct 2022
Deviation Report with respect to model copy of AgreementFile: DEVI IN AFS.pdf21 Oct 2022
Commencement Certificates / NA Order for plotted developmentFile: DOC-20220930-WA0036_220930_122532.pdf6 Oct 2022
Layout approvalFile: Building Permission 1-3.pdf4 Oct 2022
Building plan approvalFile: Building Permission 1-3.pdf4 Oct 2022
Building plan approvalFile: Building Permission 2-3.pdf4 Oct 2022
Building plan approvalFile: Building Permission 3-3.pdf4 Oct 2022

How this compares with Aurangabad

9%of this project is bookeddistrict median 6%
14%of Aurangabad projects moved their completion datethis one moved by 15 months
32%of Aurangabad registrations have lapsed or been cancelledthis one is on the register

Computed across the 1,400+ Aurangabad projects on ReraGenie, from their own filings.

Keep Nandan Vatika Wing B on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Osmanpura1,400+ in Aurangabad

2 kmNandan Vatika Wing BCompleted 31Lapsed / revoked 20Other 42Dot size: filed unitsN

Filed coordinates, straight-line distance. 93 registered projects within 2 km.

Builder: Nandan Constructions

Nandan Constructions has 3 registrations on MahaRERA, including Nandan Vatika Wing C and Nandan Vatika Wing B. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Aurangabad district page.

Frequently asked questions

What are my rights if Nandan Vatika Wing B is delayed beyond 31 Mar 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Nandan Vatika Wing B?

The registered promoter entity is Nandan Constructions, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Nandan Vatika Wing B?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Nandan Vatika Wing B?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Nandan Vatika Wing B?

The professionals named in the filing: Architect: Manoj Kala & Associates; Engineer: Core Consultants; Engineer: ADITYA ANIL PAWAR; Chartered Accountant: D GABSS & Associates; Chartered Accountant: JAIN & GANGWAL. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Nandan Vatika Wing B?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Nandan Vatika Wing B. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Nandan Vatika Wing B to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.