Home / Browse projects / Mumbai Suburban, Maharashtra / NAHUR GAONTHAN SHIV SHAKTI CHS LTD

Registered No litigation declared Residential / Group Housing project

NAHUR GAONTHAN SHIV SHAKTI CHS LTD

By OM BUILDERS AND DEVELOPERS

RG-MH-72397 · RERA P51800031723 · Last updated on MahaRERA portal: 9 Apr 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 51 months
  • 4 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Mar 2027Possession promisedmoved 51 months from the original
21 of 33Construction stages doneacross 3 buildings; furthest along: Installation of Lifts, 98%
246 of 270Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 78 documents Report an error

NAHUR GAONTHAN SHIV SHAKTI CHS LTD is a Residential / Group Housing project by OM BUILDERS AND DEVELOPERS in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800031723 on 8 Nov 2021. Possession is promised by 31 Mar 2027. The completion date has moved by 51 months from the original filing. 24 of the 270 units on this registration are recorded sold or booked, and 21 of 33 construction stages are filed complete.

At a glance

Project

  • NameNAHUR GAONTHAN SHIV SHAKTI CHS LTD
  • TypeResidential / Group Housing
  • Location
    • NAHUR GAONTHAN ROAD MULUND
    • MULUND WEST
    • Kurla
    • Mumbai Suburban
    • 400080
  • Pincode400080
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800031723
  • ReraGenie IDRG-MH-72397

Builder

  • NameOM BUILDERS AND DEVELOPERS
  • Entity typePartnership
  • PartnersMILIND ASHOK YADAV, ASHOK TUKARAM YADAV, SACHIN ASHOK YADAV
  • Other registrations8 more →
  • Completed3 of 9
  • No longer live2 lapsed, de-registered or revoked

Key dates

this monthRegisteredNov 2021First promiseDec 2022Revised toMar 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on8 Nov 2021
  • Promised completion31 Mar 2027
  • Revised completionRevised to 31 Mar 2027 (originally 31 Dec 2022)
  • Buildings3 building records
  • Documents filed78 files

Current status

9%24 of 270 units booked

Figures as on 9 Apr 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
WING ANA25231800180
WING BNA11981081
WING CNA119909

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 9 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

21 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Installation of Lifts, at 98%.

WING A73%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.98%
WING B73%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.98%
WING C73%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.98%

Progress on shared amenities15

As on 9 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes0%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes99%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed44

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots44
Closed/Covered24
Open Space20
BuildingClosed/CoveredOpen SpaceTotal
WING A121022
WING B8614
WING C448

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,577 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on1 Jul 2025

Approvals and building plan

Sanctioning authoritySlum Rehabilation Authority
Permissible FSI9611.06
Proposed, not sanctioned9,611 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHOP NO 3 NAVBHAGYA SOCIETY MAHATMA PHULE ROAD MULUND EAST MUMBAI 400081

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSACHIN GAIKWAD
EngineerVINAYAK CHOPDEKAR & ASSOCIATES
Chartered AccountantEsha Bhanushali
Chartered AccountantIqbal A Sayyid
PartnerRole in project
OM BUILDERS AND DEVELOPERS-

Extensions applied for4

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800018852Dec 2022 → Jun 2024

Reason as filed by the promoterApplied for OC (project is Almost in completion phase with Majority Work Done). We request to kindly approve the extension application as we have already submitted the consent of allottees as per the requirement of the act. We have received a comment from desk 2 stating recommended for approval and at the same time there is a detail of the consent percentage-53.85. Kindly clarify.

EXT51800013153Dec 2022 → Dec 2023

Reason as filed by the promoterShortage of material , Covid-19 situation , Labour shortage

EXT51800025062Dec 2022 → Jun 2025

Reason as filed by the promoterThere is a delay in the completion of the project Nahur Gaonthan Shiv Shakti CHS Ltd, which has MahaRERA registration No P51800031723. The following factors have contributed to this delay: 1. We procured financing from Kotak Mahindra Bank Ltd by pledging unsold units in the project. Due to non-payment of consecutive instalments, our flats were highlighted in an auction, putting us under financial burden. 2. Payments that we were supposed to receive according to the construction-linked payment plan were halted by banks following instructions from buyers due to the auction news. 3. Our main cont

EA09042620594Dec 2022 → Mar 2027

Reason as filed by the promoterOn account of Shortage of Funds & Road With Issue the building is clear all rehab mebers are occupying allottes as well are occupying water supply connection based on humanitarian grounds...

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 28 Oct 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 28 Oct 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 28 Oct 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 14 Jun 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Mar 2027

Documents filed78

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 30-06-2025.pdf9 Apr 2026
Withdrawal Update Form 2File: FORM 21.pdf9 Apr 2026
Withdrawal Update Form 3File: FORM 3 310524 CERTIFICATE OF NAHUR GAONTHAN.pdf9 Apr 2026
Declaration in FORM BFile: AFFIDAVIT Form B.pdf15 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 ANNUAL REPORT.pdf6 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: From 3 C A Certifificate 31-12-24.pdf29 Jan 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: Interest in other Organization.pdf29 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 31-12-2024.pdf23 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 - 31 12 2024 new.pdf23 Jan 2025
CERSAI detailsFile: CERSAI Decl final.pdf23 Jan 2025
Declaration in FORM BFile: Form B.pdf15 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: From 3 C A Certifificate 30-06-24.pdf15 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: From 3 C A Certifificate 30-09-24.pdf15 Nov 2024
Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory fINAL 151124.pdf15 Nov 2024
Deviation Report with respect to Allotment letterFile: Deviation Report-Allotment Letter.pdf14 Nov 2024
Deviation Report with respect to model copy of AgreementFile: Deviation Report-Agreement Sale.pdf14 Nov 2024
Disclosure for secured/unsecured finance availed for the projectFile: Disclosure for Secured Unsecured finance.pdf14 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECH'S CERTIFICATE 300624.pdf13 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECH'S CERTIFICATE 300924.pdf13 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 300624.pdf13 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 300924.pdf13 Nov 2024
Commencement Certificates / NA Order for plotted developmentFile: Reval cc.pdf14 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECH'S CERTIFICATE.pdf14 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECH'S CERTIFICATEs.pdf14 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf14 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 21.pdf14 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: ANNEXURE C FORM 2A Signed.pdf14 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 310524 CERTIFICATE OF NAHUR GAONTHAN.pdf10 Jun 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Seperate Bank Account Declaration.pdf10 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Final Rehab Form 3.pdf15 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architech certificate-Rehab-31-12-2023.pdf12 Feb 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A FY 2022-23.pdf12 Feb 2024
Disclosure of sold/ booked inventoryFile: Nahur Gaothan sold unsold.pdf12 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 2122 for upload.pdf12 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 22-23 Nahur Gaonthan for upload.pdf12 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERTIFICATE.pdf9 Feb 2024
CERSAI detailsFile: CERSAI_Search_Report_200294483069_For_Asset_Based_Search_23_01_2024_16_28_54_436.pdf9 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf9 Feb 2024
Details of encumbrances concerned to FinanceFile: Encumbrance nahur gaothan.pdf6 Feb 2024
Details of encumbrances concerned to LegalFile: Encumbrance nahur gaothan.pdf6 Feb 2024
Commencement Certificates / NA Order for plotted developmentFile: Reendoesed cc declaration mulund gaothan.pdf6 Feb 2024
Declaration in FORM BFile: Affidavit Cum Declaration Mulund Gaonthan.pdf6 Feb 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Int in oth org.pdf6 Feb 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank Account Declaration.pdf6 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: FY 17-18.pdf16 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate (2).pdf20 Jan 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Document 29.pdf20 Jan 2023
Disclosure of sold/ booked inventoryFile: Nahur Gaonthan Sold Inventory.pdf6 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Declaration Rera.pdf6 Jan 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf5 Jan 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate.pdf5 Jan 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA certificate for RERA.pdf5 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Engineer Certificate 20 (Nahur).pdf19 Dec 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Engineer Certificate 21 (Nahur).pdf19 Dec 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Enginner Certificate 22 (Nahur).pdf19 Dec 2022
Disclosure of sold/ booked inventoryFile: Sold Flats.pdf19 Dec 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FY 18-19 (1).pdf19 Dec 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FY 19-20.pdf19 Dec 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FY 20-21.pdf19 Dec 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FY 21-22.pdf19 Dec 2022
Layout approvalFile: Layout Plan_compressed (1).pdf28 Oct 2021
Building plan approvalFile: IOD NAHUR REhaab-1-6_compressed.pdf28 Oct 2021
Building plan approvalFile: IOD NAHUR REhaab-7-13_compressed (1).pdf28 Oct 2021
PAN CardFile: Pan Card-Om Builders.pdf28 Oct 2021
Copy of the legal title reportFile: Title Certificate Ms Om Builders Developers compressed.pdf28 Oct 2021
Details of encumbrancesFile: Encumbrance Certificate Nahur Gaontan.pdf28 Oct 2021
Copy of Layout Approval (in case of layout)File: Layout Plan_compressed (1).pdf28 Oct 2021
Building Plan Approval / NA Order for plotted developmentFile: IOD NAHUR REhaab-1-6_compressed.pdf28 Oct 2021
Building Plan Approval / NA Order for plotted developmentFile: IOD NAHUR REhaab-7-13_compressed (1).pdf28 Oct 2021
Commencement Certificates / NA Order for plotted developmentFile: CC- RERA- Nahur.pdf28 Oct 2021
Declaration about Commencement CertificateFile: Form D.pdf28 Oct 2021
Declaration in FORM BFile: affidavit cum declaration Nahur Goantan.pdf28 Oct 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA certificate.pdf28 Oct 2021
Proforma of Allotment letterFile: Agreement for Sale - Rehab Nahur-1_compressed.pdf28 Oct 2021
Proforma of Allotment letterFile: Agreement for Sale - Rehab Nahur-2_compressed.pdf28 Oct 2021
Proforma of Allotment letterFile: Agreement for Sale - Rehab Nahur-3_compressed.pdf28 Oct 2021
Proforma of Allotment letterFile: Agreement for Sale - Rehab Nahur-4_compressed.pdf28 Oct 2021
Proforma of Allotment letterFile: Letter Of Allotment_compressed.pdf28 Oct 2021

How this compares with Mumbai Suburban

9%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 51 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep NAHUR GAONTHAN SHIV SHAKTI CHS LTD on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near MULUND WEST6,700+ in Mumbai Suburban

2 kmNAHUR GAONTHAN SHIV SHAKCompleted 121Lapsed / revoked 99Other 155Dot size: filed unitsN

Filed coordinates, straight-line distance. 375 registered projects within 2 km.

Builder: OM BUILDERS AND DEVELOPERS

OM BUILDERS AND DEVELOPERS has 9 registrations on MahaRERA, including Om Heights and ASHOKA HEIGHTS. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if NAHUR GAONTHAN SHIV SHAKTI CHS LTD is delayed beyond 31 Mar 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of NAHUR GAONTHAN SHIV SHAKTI CHS LTD?

The registered promoter entity is OM BUILDERS AND DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in NAHUR GAONTHAN SHIV SHAKTI CHS LTD?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for NAHUR GAONTHAN SHIV SHAKTI CHS LTD?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at NAHUR GAONTHAN SHIV SHAKTI CHS LTD?

The professionals named in the filing: Architect: SACHIN GAIKWAD; Engineer: VINAYAK CHOPDEKAR & ASSOCIATES; Chartered Accountant: Esha Bhanushali; Chartered Accountant: Iqbal A Sayyid. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in NAHUR GAONTHAN SHIV SHAKTI CHS LTD?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About NAHUR GAONTHAN SHIV SHAKTI CHS LTD. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save NAHUR GAONTHAN SHIV SHAKTI CHS LTD to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.