RG-MH-76357 · RERA P51800015811 · Last updated on MahaRERA portal: 11 May 2026

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA
  • Completion date moved by 48 months
  • 4 extensions taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 48 months from the original
10 of 11Construction stages donefurthest along: Podiums (if any), 0%
10 of 30Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 68 documents Report an error

Nahid Heights is a Residential / Group Housing project by M/S Nahid Enterprises in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800015811 on 26 Mar 2018. Possession is promised by 31 Dec 2026. The completion date has moved by 48 months from the original filing. 20 of the 30 units on this registration are recorded sold or booked, and 10 of 11 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameNahid Heights
  • TypeResidential / Group Housing
  • Location
    • Ranisati Marg
    • Pathan Wadi
    • Borivali
    • Mumbai Suburban
    • 400097
  • Pincode400097
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800015811
  • ReraGenie IDRG-MH-76357

Builder

  • NameM/S Nahid Enterprises
  • Entity typePartnership
  • PartnersAbdul Hamid Abdul Majid Gigani, Mohd Imran Rehman Bhati, Naheed Abdul Hamid Gigani

Key dates

this monthRegisteredMar 2018First promiseDec 2022Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on26 Mar 2018
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 30 Dec 2022)
  • Buildings1 building record
  • Documents filed68 files

Current status

67%20 of 30 units booked
98.2%Work done, per cost certificate

Figures as on 11 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Nahid HeightsNA121125530

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 11 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

Nahid Heights: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 11 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes90%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed25

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots25
Closed/Covered25

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area571 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on9 Feb 2026

Approvals and building plan

Sanctioning authorityMUNICIPAL CORPORATION OF GREATER MUMBAI
Permissible FSI1685.9
Proposed, not sanctioned525 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMaharashtra
Estimated costRs 8.62 cr
Cost incurredRs 8.46 cr
Work done98.25%
BuildingWingEstimatedIncurred
Nahid HeightsNARs 5.59 crRs 5.59 cr
-NARs 3.02 crRs 2.87 cr

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAnkit Jain
ArchitectARCHITECT ANKIT JAIN ANKIT JAIN
EngineerCON ARCH INDIA
EngineerYusuf Amin Burgujar
Chartered AccountantCA SWPNIL JADHAV
Chartered AccountantHARIYANI & ASSOCIATES
Chartered AccountantDHANDEKAR METHWANI & CO.
PartnerRole in project
M/S Nahid Enterprises-

Extensions applied for4

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800018691Dec 2022 → Dec 2024

Reason as filed by the promoterWe would like to inform authorities that there is some delay in the completion of our project due to the harsh impact of Covid 19 on the real estate sector. The second wave caused a lot of stress and trouble as our laborers left for their hometowns. Now construction work has regained momentum we would expect work completed in a few months. It is kindly requested to accord an extension of twelve months for the completion of our project. The revised completion date would be 31/12/2024.

EXT51800013186Dec 2022 → Dec 2023

Reason as filed by the promoterTo, The Secretary, Maharashtra Real Estate Regulatory Authority 6th & 7th Floor, House fin Bhavan, Plot No: C - 21, E - Block, Bandra Kurla Complex, Bandra (E), Mumbai 400051 Sub: (Extension of our Project “Nahid Heights”) Dear Sir/Ma’am, We would like to inform authority that there is some delay in completion of our project due to harsh impact of Covid 19 on real estate sector. Second wave has caused a lot of stress and trouble as our labour left for their hometown. Now construction work has regained momentum we would be expecting work complete in few months. It is kindly requested to accord

EXT51800027229Dec 2022 → Dec 2025

Reason as filed by the promoterShortage of Skilled Labor: In addition to the material shortages, the construction industry has also been severely impacted by an acute shortage of skilled labor, including masons, earthworkers, carpenters, plumbers, and other specialized trades. The COVID-19 pandemic has resulted in the migration of a large proportion of the labor force, particularly migrant workers, back to their native regions due to lockdowns, health concerns, and other social and economic factors. As a consequence, a substantial number of workers previously engaged on-site have been unable to return, thereby halting criti

EA10022619778Dec 2022 → Dec 2026

Reason as filed by the promoterImpact of Pandemic and Rising Construction Material Costs: The COVID-19 pandemic has had a profound and far-reaching impact on the construction industry, both locally and globally. As a direct consequence of the pandemic, there has been a significant and sustained increase in the prices of essential construction materials, including but not limited to cement, steel, copper, electrical components, plumbing materials, and paints. This escalation in material costs has resulted in severe financial strain, disrupting the supply chain and leading to delays in procurement and delivery of these materi

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC006000000354507saniya tofficNahid Enterprises25/02/2023

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 16 Mar 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 16 Mar 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 16 Jun 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 19 Mar 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed68

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: FORM 1_ MARCH 26_ NAHID HEIGHTS.pdf11 May 2026
Withdrawal Update Form 2File: FORM 2_ MARCH 26_ NAHID HEIGHTS.pdf11 May 2026
Withdrawal Update Form 3File: FORM 3_ MARCH 26_ NAHID HEIGHTS.pdf11 May 2026
Form 1File: FORM 1_ MARCH 25_ NAHID HEIGHTS.pdf9 Feb 2026
Form 2File: FORM 2_ MARCH 25_ NAHID HEIGHTS.pdf9 Feb 2026
Form 3File: FORM 3_ MARCH 25_ NAHID HEIGHTS.pdf9 Feb 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD_ MARCH 25_ NAHID HEIGHTS.pdf9 Feb 2026
Form 1File: FORM 1_ JUNE 25_ NAHID HEIGHTS.pdf9 Feb 2026
Form 2File: FORM 2_ JUNE 25_ NAHID HEIGHTS.pdf9 Feb 2026
Form 3File: FORM 3_ JUNE 25_ NAHID HEIGHTS.pdf9 Feb 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD_JUNE 25_ NAHID HEIGHTS.pdf9 Feb 2026
Form 1File: FORM 1_ SEP 25_ NAHID HEIGHTS.pdf9 Feb 2026
Form 2File: FORM 2_ SEP 25_ NAHID HEIGHTS.pdf9 Feb 2026
Form 3File: FORM 3_ SEP 25_ NAHID HEIGHTS_compressed.pdf9 Feb 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD_ SEP 25_ NAHID HEIGHTS.pdf9 Feb 2026
Withdrawal Update Form 1File: FORM 1_ DEC 25_ NAHID HEIGHTS.pdf9 Feb 2026
Withdrawal Update Form 2File: FORM 2_ DEC 25_ NAHID HEIGHTS.pdf9 Feb 2026
Withdrawal Update Form 3File: FORM 3_ DEC 25_ NAHID HEIGHTS.pdf9 Feb 2026
Form 2A (FY 2024-2025)File: Form 2A_MARCH 25_NAHID HEIGHTS.pdf9 Feb 2026
Form 5 (FY 2024-2025)File: FORM 5_ MARCH 25_ NAHID HEIGHTS.pdf9 Feb 2026
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1_NAHID ENTERPRISES_NAHID HEIGHTS_DECEMBER 2024_compressed.pdf14 Jan 2025
Certificates of CA (Form 3)File: FORM 3_NAHID ENTERPRISES_NAHID HEIGHTS_DECEMBER 2024_compressed.pdf14 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2_NAHID ENTERPRISES_NAHID HEIGHTS_DECEMBER 2024_compressed.pdf14 Jan 2025
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD_NAHID ENTERPRISES_NAHID HEIGHTS_DECEMBER 2024.pdf14 Jan 2025
Disclosure of sold/ booked inventoryFile: new nahid.pdf14 Jan 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: SEPARATE BANK.pdf9 Jul 2024
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD.pdf8 Jul 2024
Certificates of CA (Form 3)File: FORM 3 NAHID_compressed.pdf8 Jul 2024
Declaration in FORM BFile: FORM B.pdf4 Jul 2024
Declaration about Commencement CertificateFile: CC DECLARATION.pdf3 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 FORM 1.pdf3 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2 FORM 2_compressed.pdf3 Jul 2024
CERSAI detailsFile: CERSAI.pdf3 Jul 2024
Disclosure for secured/unsecured finance availed for the projectFile: ID_compressed.pdf3 Jul 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: ID_compressed.pdf3 Jul 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: FORM 5 18-19_compressed.pdf3 Jul 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5 18-19_compressed.pdf3 Jul 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 5 19-20_compressed.pdf3 Jul 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5 20-21_compressed.pdf3 Jul 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5 21-22_compressed.pdf3 Jul 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 22-23_compressed.pdf3 Jul 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 23-24_compressed.pdf3 Jul 2024
Declaration about all RERA Designated Bank Accounts (Format A)File: BANK DECLARATION.pdf3 Jul 2024
Building plan approvalFile: PLAN.pdf16 Jun 2024
Building Plan Approval (IOD)File: PLAN.pdf16 Jun 2024
Declaration in FORM BFile: P51800015811_FileName_2 (1).pdf10 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 .pdf10 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FORM 2A.pdf10 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A.pdf10 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A.pdf10 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A.pdf10 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A.pdf10 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect RERA Certificate 0652.pdf12 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architech Certificates.pdf19 Jan 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT_S_CERTIFICATE_FORM_quaterly march 2022_removed (1).pdf23 Mar 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AC.pdf6 Oct 2021
Building plan approvalFile: IOD.pdf21 Mar 2018
Building Plan Approval (IOD)File: IOD.pdf21 Mar 2018
OtherFile: Building-Plan-Approval.pdf21 Mar 2018
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf19 Mar 2018
Declaration in FORM BFile: Form-B.pdf19 Mar 2018
Layout approvalFile: Layout approval.pdf16 Mar 2018
PAN CardFile: pan card.pdf16 Mar 2018
Copy of the legal title reportFile: Legal Title Report.pdf16 Mar 2018
Details of encumbrancesFile: EC.pdf16 Mar 2018
Copy of Layout Approval (in case of layout)File: Layout approval.pdf16 Mar 2018
Certificates of CA (Form 3)File: CA Certificate.pdf16 Mar 2018
Proforma of Allotment letterFile: Agreement of sale.pdf16 Mar 2018

How this compares with Mumbai Suburban

67%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 48 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Nahid Heights on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Pathan Wadi6,700+ in Mumbai Suburban

2 kmNahid HeightsCompleted 99Lapsed / revoked 66Other 122Dot size: filed unitsN

Filed coordinates, straight-line distance. 287 registered projects within 2 km.

Builder: M/S Nahid Enterprises

M/S Nahid Enterprises has 1 registration on MahaRERA, including Nahid Heights. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if Nahid Heights is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Nahid Heights?

The registered promoter entity is M/S Nahid Enterprises, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Nahid Heights?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Nahid Heights?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Nahid Heights?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Nahid Heights?

The professionals named in the filing: Architect: Ankit Jain; Architect: ARCHITECT ANKIT JAIN ANKIT JAIN; Engineer: CON ARCH INDIA; Engineer: Yusuf Amin Burgujar; Chartered Accountant: CA SWPNIL JADHAV; Chartered Accountant: HARIYANI & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Nahid Heights?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Nahid Heights. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Nahid Heights to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.