Completed No litigation declared Residential / Group Housing project

NABHRAJ ADWAIT

By Nabhraj Construction

RG-MH-37994 · RERA P51500054571 · Last updated on MahaRERA portal: 3 Dec 2025

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA
  • All 4 earlier projects delivered on promise

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 4 other registrations and every project registered within 2 km.

See what the report covers Free either way: or have every new Aurangabad registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedregistration recorded completed
0 of 11Construction stages donefurthest along: Excavation, 0%
15 of 15Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 43 documents Report an error

NABHRAJ ADWAIT is a Residential / Group Housing project by Nabhraj Construction in Aurangabad, Maharashtra, registered with MahaRERA as P51500054571 on 31 Jan 2024. The registration is recorded completed; possession was promised by 31 Dec 2027. 0 of the 15 units on this registration are recorded sold or booked, and 0 of 11 construction stages are filed complete.

At a glance

Project

  • NameNABHRAJ ADWAIT
  • TypeResidential / Group Housing
  • Location
    • DARGA ROAD
    • SHAHNOORWADI
    • Aurangabad (M Corp.)
    • Aurangabad
    • 431005
  • Pincode431005
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51500054571
  • ReraGenie IDRG-MH-37994

Builder

  • NameNabhraj Construction
  • Entity typePartnership
  • PartnerAkash Rajesh Butole
  • Other registrations4 more →
  • Completed3 of 5
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects4 →

Key dates

this monthRegisteredJan 2024PromisedDec 2027Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on31 Jan 2024
  • Promised completion31 Dec 2027
  • Revised completionNone
  • Buildings1 building record
  • Documents filed43 files

Current status

0%0 of 15 units booked
9.0%Work done, per cost certificate

Figures as on 3 Dec 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
NABHRAJ ADWAITNA7615015

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 3 Dec 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 11 construction stages are filed complete. The stage furthest along is Excavation, at 0%.

NABHRAJ ADWAIT: 0% average across the applicable activities

ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 3 Dec 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed11

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots11
Closed/Covered1
Open Space10

Land and ownership12

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area578 sq m
Land owned byThe promoter, with other names on the file
Named landowners12
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on19 Sep 2024
LandownerVillageDistrict
GANESH LAXMAN JOSHIAurangabad (M Corp.)Aurangabad
PADMAJA PANKAJ KUBERKARAurangabad (M Corp.)Aurangabad
ANJALI DAMODAR CHIMANPUREAurangabad (CB)Aurangabad
ARUN LAXMANRAO PUNDEAurangabad (CB)Aurangabad
NARENDRA GANESH TODEWALEAurangabad (M Corp.)Aurangabad
NILKANTH BHAGWAN JOSHIAurangabad (M Corp.)Aurangabad
PRADNYA PRADEEP TAMHANKARAurangabad (M Corp.)Aurangabad
NITIN KHANDERAO HAMINEAurangabad (M Corp.)Aurangabad
MUKUND DATTATRAY SARAFAurangabad (M Corp.)Aurangabad
VAISHALI CHANDRASHEKHAR VIDYASAGARAurangabad (M Corp.)Aurangabad
NIKHIL CHANDRASHEKHAR VIDYASAGARAurangabad (M Corp.)Aurangabad
NUPUR CHANDRASHEKHAR VIDYASAGARAurangabad (M Corp.)Aurangabad

Approvals and building plan

Sanctioning authorityChhatrapati Sambhaji Nagar Municipal Corporation
Permissible FSI2407.44
Proposed, not sanctioned1,830 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHOP NO 25, PLOT NO4, N 4, PUNDLIK NAGAR, CIDCO, AURANGABAD
Estimated costRs 2.55 cr
Cost incurredRs 22.93 lakh
Work done8.97%
BuildingWingEstimatedIncurred
NABHRAJ ADWAITNARs 2.29 crRs 22.93 lakh
-NARs 26.20 lakh-

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectANURAG RAJESH BUTOLE
EngineerCore Consultant
EngineerAmol Patil
Chartered AccountantSudarhan Karwa and Co
Chartered AccountantR. B. Sharma & Co
PartnerRole in project
Nabhraj Construction-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 25 Dec 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 28 Dec 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 25 Dec 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 25 Dec 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed43

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupational CertificateFile: Occupancy Certificate.pdf3 Dec 2025
Form 1File: Form 1 Arch Adwait Sep 25.pdf23 Nov 2025
Form 2File: Form 2 Egg Sep 25 Adwait.pdf23 Nov 2025
Form 3File: Form 3 Adwait Sep 2025.pdf23 Nov 2025
Disclosure of Sold and Booked InventoryFile: SoldUnsold Adwait Sep 25.pdf23 Nov 2025
Form 1File: Form 01 Arch Adwait.pdf2 Aug 2025
Form 2File: Form 02 Engg Adwait.pdf2 Aug 2025
Form 3File: Form 03 Adwait.pdf2 Aug 2025
Disclosure of Sold and Booked InventoryFile: Sold UnSold Adwait.pdf2 Aug 2025
Form 1File: 2 Form-1 Dec 24.pdf22 May 2025
Form 2File: 5 Form 2 Dec 24.pdf22 May 2025
Form 3File: 8 Form 3 Dec 24.pdf22 May 2025
Form 1File: 3 Form-1 March 25.pdf22 May 2025
Form 2File: 6 Form 2 March 25.pdf22 May 2025
Form 3File: 9 Form 3 March 25.pdf22 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch Adwait March 2024.pdf19 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Adwait June arch 2024.pdf19 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Adwait March 24 Eng C.pdf19 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Adwait June 24 Eng C.pdf19 Aug 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Adwait March 24 Q A.pdf19 Aug 2024
Other - TechnicalFile: CC REA51500151398 Verification Mail.pdf17 Jan 2024
Layout approvalFile: BP PLAN (2).pdf28 Dec 2023
PAN CardFile: 1 PAN Card.pdf28 Dec 2023
Copy of Layout Approval (in case of layout)File: BP PLAN (2).pdf28 Dec 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CCF_000015 (1).pdf28 Dec 2023
Building plan approvalFile: 17 BP PLAN.pdf25 Dec 2023
Copy of the legal title reportFile: 3 Adwait Search Report.pdf25 Dec 2023
Details of encumbrances concerned to FinanceFile: 10 NO ENC FIN.pdf25 Dec 2023
Details of encumbrances concerned to FinanceFile: 11 NO ENC LEGAL.pdf25 Dec 2023
Details of encumbrances concerned to LegalFile: 10 NO ENC FIN.pdf25 Dec 2023
Details of encumbrances concerned to LegalFile: 11 NO ENC LEGAL.pdf25 Dec 2023
Building Plan Approval / NA Order for plotted developmentFile: 17 BP PLAN.pdf25 Dec 2023
Commencement Certificates / NA Order for plotted developmentFile: 16 BP CERTF.pdf25 Dec 2023
Declaration about Commencement CertificateFile: 5 Format-D.pdf25 Dec 2023
Declaration in FORM BFile: 1 Nabhraj Form-B.pdf25 Dec 2023
CERSAI detailsFile: 9 CERSAI Declareation.pdf25 Dec 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: 12 Disclosure - Akash Butole.pdf25 Dec 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: 13 Disclosure - Rajesh Butole.pdf25 Dec 2023
Proforma of Agreement for saleFile: 18 ATS Draft RERA.pdf25 Dec 2023
Proforma of Allotment letterFile: 8 Allotment Letter Format.pdf25 Dec 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: 4 Format-A.pdf25 Dec 2023
Deviation Report with respect to Allotment letterFile: 7 Allotment Letter.pdf25 Dec 2023
Deviation Report with respect to model copy of AgreementFile: 6 Agreement to Sale.pdf25 Dec 2023

Promoter's earlier projects4

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

4 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
Nabhraj Nandanvan Phase IIgut no. 734 opp. airport Chikalthana Aurangabad56CompletedMay 2018May 2018
NABHRAJ LALITYACTS NO 145141 AND 145145 OSMANPURA AURANGABAD14CompletedDec 2016Dec 2016
NABHRAJ NANDANVANGUT NO 735 CHIKALTHANA AURANGABAD16CompletedApr 2015Apr 2015
NABHRAJ NESTCTS NO 16624 SBH OSMANPURA AURANGABAD7CompletedJun 2013Jun 2013

How this compares with Aurangabad

0%of this project is bookeddistrict median 6%
14%of Aurangabad projects moved their completion datethis one has not
32%of Aurangabad registrations have lapsed or been cancelledthis one is completed

Computed across the 1,400+ Aurangabad projects on ReraGenie, from their own filings.

Keep NABHRAJ ADWAIT on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near SHAHNOORWADI1,400+ in Aurangabad

2 kmNABHRAJ ADWAITCompleted 48Lapsed / revoked 39Other 53Dot size: filed unitsN

Filed coordinates, straight-line distance. 140 registered projects within 2 km.

Builder: Nabhraj Construction

Nabhraj Construction has 5 registrations on MahaRERA, including SHREE BALAJI ENCLAVE and Nabhraj Nandanvan Phase II. Its filings disclose 4 earlier MahaRERA projects: declares 4 of 4 past projects completed on time. Read the full track record. See more projects on the Aurangabad district page.

Frequently asked questions

What are my rights if NABHRAJ ADWAIT is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of NABHRAJ ADWAIT?

The registered promoter entity is Nabhraj Construction, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in NABHRAJ ADWAIT?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for NABHRAJ ADWAIT?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at NABHRAJ ADWAIT?

The professionals named in the filing: Architect: ANURAG RAJESH BUTOLE; Engineer: Core Consultant; Engineer: Amol Patil; Chartered Accountant: Sudarhan Karwa and Co; Chartered Accountant: R. B. Sharma & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in NABHRAJ ADWAIT?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About NABHRAJ ADWAIT. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save NABHRAJ ADWAIT to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.