Home / Browse projects / Aurangabad, Maharashtra / MY WORLD PLOT NO 3

Registered Litigation declared Others project

MY WORLD PLOT NO 3

By SIMAR PRIDE VENTURES LLP

RG-MH-07810 · RERA P51500015899 · Last updated on MahaRERA portal: 10 Dec 2025

Source: official MahaRERA filing

Red flags

  • Litigation declared, 12 cases

Clear

  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • All 10 earlier projects delivered on promise

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Aurangabad registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedno revision filed
73 of 99Construction stages doneacross 9 buildings; furthest along: Podiums (if any), 0%
34 of 127Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 373 documents Report an error

MY WORLD PLOT NO 3 is a Others project by SIMAR PRIDE VENTURES LLP in Aurangabad, Maharashtra, registered with MahaRERA as P51500015899 on 4 Apr 2018. Possession is promised by 30 Dec 2026. 93 of the 127 units on this registration are recorded sold or booked, and 73 of 99 construction stages are filed complete.

At a glance

Project

  • NameMY WORLD PLOT NO 3
  • TypeOthers
  • Location
    • JALNA ROAD
    • CHIKALTHANA
    • Aurangabad (M Corp.)
    • Aurangabad
    • 431210
  • Pincode431210
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51500015899
  • ReraGenie IDRG-MH-07810

Builder

  • NameSIMAR PRIDE VENTURES LLP
  • Entity typePartnership
  • PartnersNITIN VENUPRASAD BAGADIYA, RAJENDRA SING DHARAM SINGH RAJPAL
  • Other registrations9 more →
  • Completed8 of 10
  • Declared earlier projects10 →

Key dates

this monthRegisteredApr 2018PromisedDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on4 Apr 2018
  • Promised completion30 Dec 2026
  • Revised completionNone
  • Buildings9 building records
  • Documents filed373 files

Current status

73%93 of 127 units booked

Figures as on 10 Dec 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUILDING C1NA121020020
BUILDING C2NA121019019
BUILDING C3NA12918018
BUILDING C4NA121120020
BUILDING C5NA121119019
CLUB HOUSENA6602525
COMMERCIAL BUILDINGNA116066
BUILDING C8NA120000
BUILDING C9NA120000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building9

As on 10 Dec 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

73 of 99 construction stages are filed complete across 9 buildings. The stage furthest along is Podiums (if any), at 0%.

BUILDING C1100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
BUILDING C2100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
BUILDING C3100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
BUILDING C4100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
BUILDING C5100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
CLUB HOUSE82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
COMMERCIAL BUILDING82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
BUILDING C80%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING C90%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities21

As on 10 Dec 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%
WiFi CONNECTIVITY IN CAMPUSYes0%
VIDEO DOOR PHONEYes0%
TEMPLEYes100%
KIDS PLAY AREAYes100%
EPBAX FOR COMMUNICATIONYes0%
CLUB HOUSEYes100%

Parking filed288

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots288
Closed/Covered288
BuildingClosed/CoveredTotal
BUILDING C14848
BUILDING C24444
BUILDING C34242
BUILDING C43838
BUILDING C53838
CLUB HOUSE11
COMMERCIAL BUILDING11
BUILDING C83838
BUILDING C93838

Land and ownership3

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area9,377 sq m
Land owned byThe promoter, with other names on the file
Named landowners3
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on28 Nov 2025
LandownerVillageDistrict
HIRAMAN RAMCHANDRA RITHEAurangabad (M Corp.)Aurangabad
YAMAJI RAMCHANDRA RITHEAurangabad (M Corp.)Aurangabad
SHANTILAL BABAN RITHEAurangabad (M Corp.)Aurangabad

Approvals and building plan

Sanctioning authorityAurangabad Mahanagarpalika
Permissible FSI32054.53
Proposed, not sanctioned32,055 sq m
Buildings approved9
Buildings sanctioned9

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchKRANTI CHOWK AURANGABAD

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAKW ASSOCIATES
EngineerMilind Wadekar
Chartered AccountantNarendra Navandar and co
Chartered AccountantCA Sachin Lathi
PartnerRole in project
SIMAR PRIDE VENTURES LLP-

Litigation declared12

CaseCourtStatus
RCS 128/2020/2020Ninth Civil Judge Senior division Aurangabad Mr Rajendra TuwarPending
486/2020/2020Civil Judge Senior divisionPending
38/2021/2021Civil Judge Senior DivisionDisposed
RCS/538/2020/2020Civil Judge Senior division AurangabadDisposed
RCS/729/2020/2020Civil Judge Senior division AurangabadDisposed
RCS-546/2021/2021Civil Judge Senior DivisionPending
RCS-550/2021/2021Civil Judge Senior DivisionPending
RCS-847/2021/2021Civil Judge Senior DivisionPending
RCS-1596/2022/2022Civil Judge Senior DivisionPending
90/2021/2021Sub Division Officer AurangabadPending
7171/2020/2020Honourable High Court of Bombay AuranagabadPending
RCS 128/2020/2020Ninth Civil Judge Senior division Aurangabad Mr Rajendra TuwarOngoing

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 23 Mar 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 23 Mar 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 29 Nov 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 20 Jun 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Dec 2026

Documents filed373

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 373 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 5 (FY 2023-2024)File: 23-24.pdf10 Dec 2025
Form 5 (FY 2024-2025)File: 24-25.pdf10 Dec 2025
Building plan approvalFile: HPSCANNER0024.pdf29 Nov 2025
Building plan approvalFile: HPSCANNER0025.pdf29 Nov 2025
Building plan approvalFile: HPSCANNER0026.pdf29 Nov 2025
Building plan approvalFile: HPSCANNER0027.pdf29 Nov 2025
Building plan approvalFile: HPSCANNER0028.pdf29 Nov 2025
Building plan approvalFile: HPSCANNER0029.pdf29 Nov 2025
Building plan approvalFile: HPSCANNER0030.pdf29 Nov 2025
Building plan approvalFile: HPSCANNER0031.pdf29 Nov 2025
Building plan approvalFile: HPSCANNER0032.pdf29 Nov 2025
Building plan approvalFile: HPSCANNER0033.pdf29 Nov 2025
Building plan approvalFile: HPSCANNER0034.pdf29 Nov 2025
Building plan approvalFile: HPSCANNER0035.pdf29 Nov 2025
Building plan approvalFile: HPSCANNER0036.pdf29 Nov 2025
Building plan approvalFile: HPSCANNER0037.pdf29 Nov 2025
Building plan approvalFile: HPSCANNER0038.pdf29 Nov 2025
Building plan approvalFile: HPSCANNER0039.pdf29 Nov 2025
Building plan approvalFile: HPSCANNER0040.pdf29 Nov 2025
Building plan approvalFile: HPSCANNER0041.pdf29 Nov 2025
Building plan approvalFile: HPSCANNER0042.pdf29 Nov 2025
Building plan approvalFile: HPSCANNER0043.pdf29 Nov 2025
Building plan approvalFile: HPSCANNER0044.pdf29 Nov 2025
Building plan approvalFile: HPSCANNER0045.pdf29 Nov 2025
Building plan approvalFile: HPSCANNER0046.pdf29 Nov 2025
Building plan approvalFile: HPSCANNER0047.pdf29 Nov 2025
Building plan approvalFile: HPSCANNER0048.pdf29 Nov 2025
Building plan approvalFile: HPSCANNER0049.pdf29 Nov 2025
Building plan approvalFile: HPSCANNER0050.pdf29 Nov 2025
Building plan approvalFile: HPSCANNER0051.pdf29 Nov 2025
Building plan approvalFile: HPSCANNER0052.pdf29 Nov 2025
Building plan approvalFile: HPSCANNER0053.pdf29 Nov 2025
Building plan approvalFile: HPSCANNER0054.pdf29 Nov 2025
Building plan approvalFile: HPSCANNER0055.pdf29 Nov 2025
Building plan approvalFile: HPSCANNER0056.pdf29 Nov 2025
Building plan approvalFile: HPSCANNER0057.pdf29 Nov 2025
Building plan approvalFile: HPSCANNER0058.pdf29 Nov 2025
Building plan approvalFile: HPSCANNER0059.pdf29 Nov 2025
Building plan approvalFile: HPSCANNER0060.pdf29 Nov 2025
Building plan approvalFile: HPSCANNER0061.pdf29 Nov 2025
Building plan approvalFile: HPSCANNER0062.pdf29 Nov 2025
Building plan approvalFile: HPSCANNER0063.pdf29 Nov 2025
Building plan approvalFile: HPSCANNER0064.pdf29 Nov 2025
Building plan approvalFile: HPSCANNER0065.pdf29 Nov 2025
Building plan approvalFile: HPSCANNER0066.pdf29 Nov 2025
Building plan approvalFile: HPSCANNER0067.pdf29 Nov 2025
Building plan approvalFile: HPSCANNER0068.pdf29 Nov 2025
Building plan approvalFile: HPSCANNER0069.pdf29 Nov 2025
Building plan approvalFile: HPSCANNER0070.pdf29 Nov 2025
Building plan approvalFile: HPSCANNER0071.pdf29 Nov 2025
Building plan approvalFile: HPSCANNER0072.pdf29 Nov 2025
Building plan approvalFile: HPSCANNER0073.pdf29 Nov 2025
Building plan approvalFile: HPSCANNER0074.pdf29 Nov 2025
Building plan approvalFile: HPSCANNER0075.pdf29 Nov 2025
Building plan approvalFile: HPSCANNER0076.pdf29 Nov 2025
Building plan approvalFile: HPSCANNER0077.pdf29 Nov 2025
Building plan approvalFile: HPSCANNER0077.pdf29 Nov 2025
Building plan approvalFile: HPSCANNER0078.pdf29 Nov 2025
Building plan approvalFile: HPSCANNER0079.pdf29 Nov 2025
Form 1File: 1.pdf24 Nov 2025
Form 2File: 2.pdf24 Nov 2025
Form 3File: CA Certificate Simar Pride Dt-30-06-2023_0001.pdf24 Nov 2025
Disclosure of Sold and Booked InventoryFile: Discl.pdf24 Nov 2025
OthersFile: 2A.pdf24 Nov 2025
Form 1File: 1.pdf24 Nov 2025
Form 2File: 2.pdf24 Nov 2025
Form 3File: CA Certificate Simar Pride Dt-30-09-2023_0001.pdf24 Nov 2025
Disclosure of Sold and Booked InventoryFile: Discl.pdf24 Nov 2025
OthersFile: 2A.pdf24 Nov 2025
Form 2File: 2.pdf24 Nov 2025
Form 3File: CA Certificate Simar Pride Dt-31-12-2023_0001.pdf24 Nov 2025
Disclosure of Sold and Booked InventoryFile: Discl.pdf24 Nov 2025
OthersFile: 2A.pdf24 Nov 2025
Form 1File: ARCHITECT CERTIFICATE PLOT 3 C1 TO C5-Dec'23.pdf24 Nov 2025
Form 1File: 1.pdf24 Nov 2025
Form 2File: Engineers Certificate Plot no 3 C1 TO C5-Mar'24.pdf24 Nov 2025
Form 3File: CA Certificate Simar Pride Dt-31-03-2024_0001.pdf24 Nov 2025
Disclosure of Sold and Booked InventoryFile: corrigandum My World C1 to C9 Type Building-Mar'24.pdf24 Nov 2025
OthersFile: 2A.pdf24 Nov 2025
Form 1File: 1.pdf24 Nov 2025

Promoter's earlier projects10

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

10 delivered on promise
ProjectLocationFlatsRegisteredStatusPromisedDelivered
MY WORLD PLOT NO 2 BUILDING D1 TO D6P51500015862CHIKALTHANA, Aurangabad-Mar 2018CompletedDec 2026Jan 2023
MY WORLD BUILDING B1-B2-B3P51500015772CHIKALTHANA, Aurangabad-Mar 2018CompletedDec 2024Jan 2023
My World Building B 4-5-6Gut No 708 Chikalthana108-CompletedDec 2023Jul 2022
My World Building B 7-8-9Gut No 708 Chikalthana108-CompletedMar 2023Oct 2021
My World Building A4Gut No 708 Chikalthana36-CompletedMar 2023Oct 2021
My World Building A3Gut No 708 Chikalthana36-CompletedMar 2023Oct 2021
My World Building A1-A2Gut No 708 Chikalthana88-CompletedMar 2023Oct 2021
MANJEET PRIDE GLORYGUT NO 136P DEOLAI ROAD BEED BYPASS AURANGABAD74-CompletedJul 2017Jul 2017
manjeet prideplot no 361 316A 317 317A mahanagar1 cidco waluj aurangabad112-CompletedJul 2016Jun 2016
MANJEET PRIDE PRIMOGUT NO 81 P BEED BYPASS ROAD AURANGABAD70-CompletedMar 2015Mar 2015

How this compares with Aurangabad

73%of this project is bookeddistrict median 6%
14%of Aurangabad projects moved their completion datethis one has not
32%of Aurangabad registrations have lapsed or been cancelledthis one is on the register

Computed across the 1,400+ Aurangabad projects on ReraGenie, from their own filings.

Keep MY WORLD PLOT NO 3 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near CHIKALTHANA1,400+ in Aurangabad

2 kmMY WORLD PLOT NO 3Completed 16Lapsed / revoked 3Other 6Dot size: filed unitsN

Filed coordinates, straight-line distance. 25 registered projects within 2 km.

Builder: SIMAR PRIDE VENTURES LLP

SIMAR PRIDE VENTURES LLP has 10 registrations on MahaRERA, including MY WORLD BUILDING A3 and MY WORLD BUILDING B1-B2-B3. Its filings disclose 10 earlier MahaRERA projects: declares 10 of 10 past projects completed on time. Litigation is declared on 2 of its registrations. Read the full track record. See more projects on the Aurangabad district page.

Frequently asked questions

What are my rights if MY WORLD PLOT NO 3 is delayed beyond 30 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of MY WORLD PLOT NO 3?

The registered promoter entity is SIMAR PRIDE VENTURES LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in MY WORLD PLOT NO 3?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for MY WORLD PLOT NO 3?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at MY WORLD PLOT NO 3?

The professionals named in the filing: Architect: AKW ASSOCIATES; Engineer: Milind Wadekar; Chartered Accountant: Narendra Navandar and co; Chartered Accountant: CA Sachin Lathi. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MY WORLD PLOT NO 3?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MY WORLD PLOT NO 3. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MY WORLD PLOT NO 3 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.