Registration lapsed No litigation declared Residential / Group Housing project

MORYA HEIGHTS

By BEEJAY REALTORS PRIVATE LIMITED

RG-MH-96191 · RERA P51800009796 · Last updated on MahaRERA portal: 17 Nov 2024

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 27 months past the filed date
  • 2 complaints at MahaRERA
  • Completion date moved by 18 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Jul 2024Possession promised27 months past this date
0 of 22Construction stages doneacross 2 buildings; furthest along: Excavation, 60%
2Complaints at MahaRERAon this registration
Jump to the 40 documents Report an error

MORYA HEIGHTS is a Residential / Group Housing project by BEEJAY REALTORS PRIVATE LIMITED in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800009796 on 22 Aug 2017. Possession was promised by 31 Jul 2024 and is now 27 months past that date. The completion date has moved by 18 months from the original filing. 2 complaints are on record with the regulator.

At a glance

Project

  • NameMORYA HEIGHTS
  • TypeResidential / Group Housing
  • Location
    • HANUMAN ROAD
    • AKURLI ROAD
    • KANDIVALI
    • Borivali
    • Mumbai Suburban
    • 400101
  • Pincode400101
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800009796
  • ReraGenie IDRG-MH-96191

Builder

  • NameBEEJAY REALTORS PRIVATE LIMITED
  • Entity typeCompany
  • CINU45200MH1995PTC161143
  • Managing DirectorsUTTAM JHAVAR, DHRUV JHAVAR, PRADEEP JHAVAR
  • Declared earlier projects1 →

Key dates

27 months past promisethis monthRegisteredAug 2017First promiseJan 2023Revised toJul 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on22 Aug 2017
  • Promised completion31 Jul 2024
  • Revised completionRevised to 31 Jul 2024 (originally 31 Jan 2023)
  • Buildings2 building records
  • Documents filed40 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUILDING TOWARDS WESTNA230000
BUILDING TOWARDS EASTNA230000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 17 Nov 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Excavation, at 60%.

BUILDING TOWARDS WEST5%
ActivityProgress
Excavation60%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING TOWARDS EAST5%
ActivityProgress
Excavation60%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities16

As on 17 Nov 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%
Nalla DevelopmentYes0%

Parking filed195

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots195
Closed/Covered2
Open Space193
BuildingClosed/CoveredOpen SpaceTotal
BUILDING TOWARDS WEST19697
BUILDING TOWARDS EAST19798

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area6,884 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
KAY FOAM LTDMumbai CityMumbai City

Approvals and building plan

Permissible FSI16327.34
Proposed, not sanctioned5,432 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchPRATAP PALACE, GROUND FLOOR, JN ROAD, MULUND W, MUMBAI 400080

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVIVEK BHOLE
EngineerACHYUT WATVE
Chartered AccountantN.S. SHETTY & CO.
Chartered AccountantM.R. Sharma & Co.
PartnerRole in project
BEEJAY REALTORS PRIVATE LIMITED-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800010868Jan 2023 → Jan 2024

Reason as filed by the promoterDPCR 14(b) as per which conversion of Industrial user to Residential user requires providing 10% amenity space to M.C.G.M. We already have change of User Permission from Industrial to Residential as per which we are to handover 5% amenity space to MCGM and this 5% amenity space has been demarcated in the change of user permission. After having received this permission our entire layout, Open Spaces, Building Coverage, Plinth, Parking areas, RG Area and other areas have been planned accordingly in the IOD plan. Altering plans at this stage to accommodate handing over 10% amenity space has requi

Complaints filed with MahaRERA2

Case no.ComplainantRespondentFiled
CC006000000012349Karan SukhaniBeejay Realtors Pvt. Ltd.09/12/2017
CC006000000209607Mr Dilip BhatiaBeejay Realtors Pvt Ltd03/01/2022

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 31 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 31 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed40

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: BJR ANNUAL REPORT.pdf17 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: BJR ANNUAL REPORT.pdf17 Nov 2024
Disclosure of sold/ booked inventoryFile: disclosure_of_sold_or_booked_inventory.pdf26 Jul 2024
Certificates of CA (Form 3)File: ca_certificate_2024_compressed.pdf26 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: morya_heights_site_supervisor_quality_assurance_2023__2024.pdf30 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: quality_assurance_bjr_site_supervisor_2022_2023.pdf29 Sep 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: bjr_ca_certificate_2022_2023.pdf29 Sep 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: quality_assurance_bjr_site_supervisor_2022_2023.pdf25 Jul 2023
Details of encumbrances concerned to FinanceFile: reliance_no_dues_certificate.pdf22 Apr 2023
Details of encumbrances concerned to LegalFile: reliance_no_dues_certificate.pdf22 Apr 2023
CERSAI detailsFile: morya_heights_cersai.pdf22 Apr 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: beejay_realtors_pvt_ltd_disclosure_of_interest.pdf22 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: quality_assurance_bjr_site_supervisor_2021_2022.pdf21 Apr 2023
Proforma of Agreement for saleFile: sample_agreement.pdf20 Apr 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: separate_account_declaration_bjr_0001.pdf20 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: BJR ANNUAL REPORT ON STATEMENT OF ACCOUNTS.pdf30 Sep 2022
Disclosure of sold/ booked inventoryFile: sold_unsold_list_for_upload_compresssed.pdf7 Sep 2021
Declaration about Commencement CertificateFile: declaration_About_commencement_certificate_upload.pdf6 Sep 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: quality_assurance_bjr_site_supervisor_2019_2020.pdf1 Sep 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: quality_assurance_bjr_site_supervisor_2020_2021.pdf1 Sep 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: morya_heights_rera_ca_certificate_form_5_2018_2019.pdf1 Sep 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: morya_heights_rera_ca_certificate_form_5_2019_2020.pdf1 Sep 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: morya_heights_rera_ca_certificate_form_5_2020_2021.pdf1 Sep 2021
Certificates of CA (Form 5)File: FORM_5_BJR_YEAR_18_19.pdf30 Sep 2019
Certificates of CA (Form 3)File: cost_beejay_realtors_morya_heights.pdf21 Oct 2018
Certificates of CA (Form 5)File: form_5_morya_heights_13_10_2018.pdf13 Oct 2018
Building plan approvalFile: IOD_MORYA_HEIGHTS.pdf31 Jul 2017
Layout approvalFile: layout.pdf31 Jul 2017
PAN CardFile: BEEJAY REALTORS_PAN CARD.pdf31 Jul 2017
Copy of the legal title reportFile: Title_certificate_MORYA HEIGHTS.pdf31 Jul 2017
Details of encumbrancesFile: Title_certificate_MORYA HEIGHTS.pdf31 Jul 2017
Copy of Layout Approval (in case of layout)File: layout.pdf31 Jul 2017
Building Plan Approval (IOD)File: IOD_MORYA_HEIGHTS.pdf31 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: C_C_2017_MORYA HEIGHTS.pdf31 Jul 2017
Declaration in FORM BFile: Affidavit cum declaration_Beejay_Rera.pdf31 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT_CERTIFICATE_RERA.pdf31 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFICATE_ATUL KOTHARI_BJ_M_RERA.pdf31 Jul 2017
Certificates of CA (Form 3)File: New Doc 2017-07-31 (2).pdf31 Jul 2017
Proforma of Allotment letterFile: allotment_agreement.pdf31 Jul 2017
OtherFile: I2R_MORYA Heights.pdf31 Jul 2017

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
MORYA BLUE MOONNew Link Road Andheri west mumbai 40005360CompletedDec 2013Late, Apr 2014

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 18 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep MORYA HEIGHTS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near KANDIVALI6,700+ in Mumbai Suburban

2 kmMORYA HEIGHTSCompleted 32Lapsed / revoked 22Other 61Dot size: filed unitsN

Filed coordinates, straight-line distance. 115 registered projects within 2 km.

Builder: BEEJAY REALTORS PRIVATE LIMITED

BEEJAY REALTORS PRIVATE LIMITED has 1 registration on MahaRERA, including MORYA HEIGHTS. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that MORYA HEIGHTS shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if MORYA HEIGHTS is delayed beyond 31 Jul 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of MORYA HEIGHTS?

The registered promoter entity is BEEJAY REALTORS PRIVATE LIMITED, a company as per the filing. Its CIN U45200MH1995PTC161143 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in MORYA HEIGHTS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against MORYA HEIGHTS?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for MORYA HEIGHTS?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at MORYA HEIGHTS?

The professionals named in the filing: Architect: VIVEK BHOLE; Engineer: ACHYUT WATVE; Chartered Accountant: N.S. SHETTY & CO.; Chartered Accountant: M.R. Sharma & Co.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MORYA HEIGHTS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MORYA HEIGHTS. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MORYA HEIGHTS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.