Home / Browse projects / MORAJ OPULENCE

Registered No litigation declared Residential / Group Housing project

MORAJ OPULENCE

By MORAJ AHN DEVELOPERS LLP

RG-MH-39489 · RERA P51900032370 · Last updated on MahaRERA portal: 30 Jul 2026

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA
  • Completion date moved by 36 months
  • 1 extension taken
  • Rs 100.00 crore secured on the land, in favour of IDBI TRUSTEE SHIP SERVICES LTD

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: .
Dec 2029Possession promisedmoved 36 months from the original
3 of 11Construction stages donefurthest along: Slabs of Super Structure, 67%
24 of 46Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 111 documents Report an error

MORAJ OPULENCE is a Residential / Group Housing project by MORAJ AHN DEVELOPERS LLP in MAHIM, 400016, registered with MahaRERA as P51900032370 on 29 Dec 2021. Possession is promised by 31 Dec 2029. The completion date has moved by 36 months from the original filing. 22 of the 46 units on this registration are recorded sold or booked, and 3 of 11 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameMORAJ OPULENCE
  • TypeResidential / Group Housing
  • Location
    • GOPI TANK ROAD
    • MAHIM
    • 400016
  • Pincode400016
  • RERA no.P51900032370
  • ReraGenie IDRG-MH-39489

Builder

  • NameMORAJ AHN DEVELOPERS LLP
  • Entity typePartnership
  • PartnersPRIYAA MOHAN GURNANI, GAJENDRAA SHINDE

Key dates

this monthRegisteredDec 2021First promiseDec 2026Revised toDec 2029

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on29 Dec 2021
  • Promised completion31 Dec 2029
  • Revised completionRevised to 31 Dec 2029 (originally 28 Dec 2026)
  • Buildings1 building record
  • Documents filed111 files

Current status

48%22 of 46 units booked
68.5%Work done, per cost certificate

Figures as on 30 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
MORAJ OPULENCENA282744246

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 30 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 67%.

MORAJ OPULENCE: 38% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure67%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 30 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes45%
Water SupplyYes60%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes70%
Storm Water DrainsYes50%
Landscaping & Tree PlantingYes94%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes55%
Energy managemcntYes11%
Fire protection and fire safety requirementsYes36%
Electrical meter room, sub-station, receiving stationYes60%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed84

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots84
Closed/Covered84

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area2,328 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofIDBI TRUSTEE SHIP SERVICES LTD
Secured amountRs 100.00 crore
CERSAI search filedYes
Declared on25 Jun 2025

Approvals and building plan

Sanctioning authoritySlum rehabilitation authority
Permissible FSI11328.23
Proposed, not sanctioned5,905 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGROUND FLOOR, SHOP. NO. 5, MAHATMA PHULE BHAVAN, PLOT NO.66, SECTOR NO.17, VASHI, NAVI MUMBAI- 400 703
Estimated costRs 125.00 cr
Cost incurredRs 85.62 cr
Work done68.5%
BuildingWingEstimatedIncurred
MORAJ OPULENCENARs 87.50 crRs 61.25 cr
-NARs 37.50 crRs 24.38 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectHITEN SETHI & ASSOCIATES
EngineerKAUSHIK C THACKER
Chartered AccountantHR KHAN & ASSOCIATES
Chartered AccountantCap and co
Chartered AccountantRKAM & CO
PartnerRole in project
MORAJ AHN DEVELOPERS LLP-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51900019361Dec 2026 → Dec 2029

Reason as filed by the promoter1. Application filed u/s 7(3) 2. Consent of 75% of allottees uploaded in format 3. Seeking extension due to lack of demand in the area 4. Variation in Material prices and labour wages 5. Labour shortage

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
SM12600035Bhakti AchrekarMORAJ AHN DEVELOPERS LLP09/01/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 6 Dec 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 13 Nov 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 13 Nov 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 13 Nov 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2029

Documents filed111

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 111 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 Q1 June 2026.pdf30 Jul 2026
Withdrawal Update Form 2File: FORM 2 Q1 June 26.pdf30 Jul 2026
Withdrawal Update Form 3File: Form 3 Q1 June.pdf30 Jul 2026
Withdrawal Update Form 1File: Form 1 Q1 June 2026.pdf29 Jul 2026
Withdrawal Update Form 2File: FORM 2 Q1 June 26.pdf29 Jul 2026
Withdrawal Update Form 3File: Form 3 Q1 June.pdf29 Jul 2026
Withdrawal Update Form 1File: MORAJ OPULENCE FORM 1 Architect Certificate Q4 March 2026.pdf20 Apr 2026
Withdrawal Update Form 2File: MORAJ OPULENCE FORM 2 Engineer Certificate Q4 MAR 26.pdf20 Apr 2026
Withdrawal Update Form 3File: Moraj Opulance CA Certificate FORM-3 Q4 March 2026.pdf20 Apr 2026
Form 2A (FY 2025-2026)File: MORAJ OPULENCE FORM 2A Engineer Quality Assurance Certificate MARCH 26.pdf20 Apr 2026
Withdrawal Update Form 1File: Moraj Opulence Q3 Form 1.pdf22 Jan 2026
Withdrawal Update Form 2File: Moraj Opulence Q3 FORM2 DEC2025.pdf22 Jan 2026
Withdrawal Update Form 3File: Moraj Opulence Q3 Form3.pdf22 Jan 2026
Form 5 (FY 2024-2025)File: Form 5 Moraj Opulence.pdf7 Nov 2025
Withdrawal Update Form 1File: form1 sept25.pdf18 Oct 2025
Withdrawal Update Form 2File: form 2.pdf18 Oct 2025
Withdrawal Update Form 3File: form3_.pdf18 Oct 2025
Form 2A (FY 2024-2025)File: Moraj Form 2A.pdf22 Jul 2025
Withdrawal Update Form 1File: FORM1 Moraj Opulance June 2025.pdf18 Jul 2025
Withdrawal Update Form 2File: Form 2 Moraj Opulance June 2025.pdf18 Jul 2025
Withdrawal Update Form 3File: Form 3 Moraj Opulance June 2025.pdf18 Jul 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Moraj March 2025.pdf14 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Moraj March 2025.pdf14 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Moraj March 2025.pdf14 Apr 2025
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF INVENTORY Moraj March 2025.pdf14 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM1 December 2024.pdf20 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form_3 December 2024.pdf20 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 December 2024.pdf20 Jan 2025
Disclosure of sold/ booked inventoryFile: INVENTORY December 2024.pdf20 Jan 2025
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD BOOKED INVENTORY.pdf31 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM1 MORAJ OPULENCE SEPT-24.pdf26 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf26 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Final Form 3.pdf26 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 ENGG.pdf26 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM2A ENGG CERTIFICATE SEPT24 MORAJ OPULENCE.pdf26 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: form 5 AHN 2024.pdf26 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form1 june 24 moraj opulence (2).pdf12 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form2 june 24 moraj opulence.pdf2 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: MORAJ AHN FORM3 JUNE24.pdf2 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 MAR 24.pdf30 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM1 Mar 24 MORAJ OPULENCE.pdf10 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form2 Mar 24 OPULENCE.pdf10 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM1 NOV 21.pdf23 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM1 MARCH 22.pdf23 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM1 JUNE22.pdf23 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM1 SEPT22.pdf23 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM1 DEC 22.pdf23 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM1 MARCH23.pdf23 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM1 JUNE23.pdf23 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM1 JUNE22.pdf23 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 NOV21.pdf23 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form1 dec 23.pdf21 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form1 sept23.pdf21 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form3 sept23.pdf21 Mar 2024
Declaration in FORM BFile: affidavit.pdf20 Mar 2024
Disclosure of sold/ booked inventoryFile: disclosure sold inventory (1).pdf20 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engineer certicate Mar22.pdf15 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engineer certicate JUNE22.pdf15 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM2 _March 23.pdf15 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form2 june23.pdf15 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM2 - DEC 23.pdf15 Mar 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A 2022.pdf15 Mar 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A 2023.pdf15 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form2 dec 22.pdf11 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Mar22_.pdf11 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Moraj oppulance RERA Sep 22.pdf11 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ca certifocate JUNE 23.pdf11 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM5 MAR23_.pdf11 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM5 MAR23_.pdf11 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM5 21-22.pdf11 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form3 dec23 ahn.pdf18 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Opulence-RERA Arch Cert-311223.pdf10 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM2 .pdf10 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 MAR2023.pdf29 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form3.pdf22 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM2 .pdf13 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate-30-09-2023.pdf10 Oct 2023
Proforma of Agreement for saleFile: DRAFT-AFS.pdf3 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ca certifocate JUNE 23.pdf11 Sep 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Archiect Certificate-30-06-2023.pdf14 Aug 2023

Keep MORAJ OPULENCE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near MAHIM

Builder: MORAJ AHN DEVELOPERS LLP

MORAJ AHN DEVELOPERS LLP has 1 registration on MahaRERA, including MORAJ OPULENCE. Its filings disclose no earlier MahaRERA projects. Read the full track record.

Frequently asked questions

What are my rights if MORAJ OPULENCE is delayed beyond 31 Dec 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of MORAJ OPULENCE?

The registered promoter entity is MORAJ AHN DEVELOPERS LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in MORAJ OPULENCE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against MORAJ OPULENCE?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for MORAJ OPULENCE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at MORAJ OPULENCE?

The professionals named in the filing: Architect: HITEN SETHI & ASSOCIATES; Engineer: KAUSHIK C THACKER; Chartered Accountant: HR KHAN & ASSOCIATES; Chartered Accountant: Cap and co; Chartered Accountant: RKAM & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MORAJ OPULENCE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MORAJ OPULENCE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MORAJ OPULENCE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.