Home / Browse projects / Mumbai Suburban, Maharashtra / MONTICELLO

Registration lapsed No litigation declared Residential / Group Housing project

MONTICELLO

By SAMUDRA DEVELOPERS PRIVATE LIMITED

RG-MH-09954 · RERA P51800002198 · Last updated on MahaRERA portal: 17 Nov 2018

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 49 months past the filed date
  • Completion date moved by 34 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Sep 2022Possession promised49 months past this date
5 of 11Construction stages donefurthest along: Staircases, 95%
0Complaints at MahaRERAon this registration
Jump to the 41 documents Report an error

MONTICELLO is a Residential / Group Housing project by SAMUDRA DEVELOPERS PRIVATE LIMITED in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800002198 on 31 Jul 2017. Possession was promised by 29 Sep 2022 and is now 49 months past that date. The completion date has moved by 34 months from the original filing.

At a glance

Project

  • NameMONTICELLO
  • TypeResidential / Group Housing
  • Location
    • Kane Road
    • Bandra Reclamation
    • Andheri
    • Mumbai Suburban
    • 400051
  • Pincode400051
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800002198
  • ReraGenie IDRG-MH-09954

Builder

  • NameSAMUDRA DEVELOPERS PRIVATE LIMITED
  • Entity typeCompany

Key dates

49 months past promisethis monthRegisteredJul 2017First promiseNov 2019Revised toSep 2022

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on31 Jul 2017
  • Promised completion29 Sep 2022
  • Revised completionRevised to 29 Sep 2022 (originally 30 Nov 2019)
  • Buildings1 building record
  • Documents filed41 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
MONTICELLONA260000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 17 Nov 2018, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 95%.

MONTICELLO: 74% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor90%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.25%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.25%

Progress on shared amenities15

As on 17 Nov 2018, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes10%
Storm Water DrainsYes10%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes10%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes50%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed19

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots19
Closed/Covered19

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area919 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI1802.06
Proposed, not sanctioned1,802 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch36, CRYSTAL BUILDING KEMPS CORNER ALTAMOUNT ROAD TARDEO MUMBAI 400026

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectGVS ARCHITECTS & ASSOCIATES
PartnerRole in project
SAMUDRA DEVELOPERS PRIVATE LIMITED-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800009524Nov 2019 → Mar 2022

Reason as filed by the promoterThe project namely “MONTICELLO” (Project Registration No. P51800002198) on plot bearing/ CTS/ Survey/ Final Plot No. CTS No. B/870-B at Kane Road, Bandra Hill now known as Mount Mary Hill, Bandra South Salsette Taluka, Bombay Suburban 400 050 (hereinafter referred to as the “said Project”) is at 85 % completion stage. RCC work of the building comprised in the said Project is fully complete. Interiors of the building comprised in the said Project are nearing completion. Occupation Certificate (OC) of the building comprised in the said Project shall be applied once the pending work is to be comp

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 26 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 20 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 20 Dec 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 17 Apr 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed41

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of CA (Form 5)File: Form 5_Monticello.pdf17 Nov 2018
Commencement Certificates / NA Order for plotted developmentFile: Architect Letter to Sub-Engineer - CC.pdf17 Apr 2018
Building plan approvalFile: Letter.pdf20 Dec 2017
Building plan approvalFile: Plan 1.pdf20 Dec 2017
Building plan approvalFile: Plan 2.pdf20 Dec 2017
Building plan approvalFile: Plan 3.pdf20 Dec 2017
Building plan approvalFile: Plan 4.pdf20 Dec 2017
Building plan approvalFile: Plan 5.pdf20 Dec 2017
Building plan approvalFile: Plan 6.pdf20 Dec 2017
Building Plan Approval (IOD)File: Letter.pdf20 Dec 2017
Building Plan Approval (IOD)File: Plan 1.pdf20 Dec 2017
Building Plan Approval (IOD)File: Plan 2.pdf20 Dec 2017
Building Plan Approval (IOD)File: Plan 3.pdf20 Dec 2017
Building Plan Approval (IOD)File: Plan 4.pdf20 Dec 2017
Building Plan Approval (IOD)File: Plan 5.pdf20 Dec 2017
Building Plan Approval (IOD)File: Plan 6.pdf20 Dec 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Architect's Certificate - Monticello.pdf26 Oct 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Engineers Certificate - Monticello.pdf26 Oct 2017
Certificates of CA (Form 3)File: CA Certificate_Monticello.pdf26 Oct 2017
Certificates of CA (Form 3)File: CA Certificate Monticello.pdf28 Jul 2017
Details of encumbrancesFile: Declaration.pdf27 Jul 2017
Declaration in FORM BFile: Declaration Form 'B' - Monticello.pdf27 Jul 2017
Proforma of Allotment letterFile: Proforma of Allotment Letter and Agreement for Sale.pdf27 Jul 2017
Copy of the legal title reportFile: Title Certificate - Monticello.pdf26 Jul 2017
Building plan approvalFile: area diagram with calculations.pdf20 Jul 2017
Building plan approvalFile: section A-A and B-B.pdf20 Jul 2017
Layout approvalFile: Layout.pdf20 Jul 2017
Building plan approvalFile: IOD.pdf20 Jul 2017
Building plan approvalFile: 1st and 2nd basement floor plan.PDF20 Jul 2017
Building plan approvalFile: 1st to 4th, 6th to 8th and 10 floor plan.pdf20 Jul 2017
Building plan approvalFile: 5th to 9th, 11th and 12th, terrace floor plan and carpet area statment.PDF20 Jul 2017
PAN CardFile: PAN CARD.pdf20 Jul 2017
Copy of Layout Approval (in case of layout)File: Layout.pdf20 Jul 2017
Building Plan Approval (IOD)File: IOD.pdf20 Jul 2017
Building Plan Approval (IOD)File: 1st and 2nd basement floor plan.PDF20 Jul 2017
Building Plan Approval (IOD)File: 1st to 4th, 6th to 8th and 10 floor plan.pdf20 Jul 2017
Building Plan Approval (IOD)File: 5th to 9th, 11th and 12th, terrace floor plan and carpet area statment.PDF20 Jul 2017
Building Plan Approval (IOD)File: area diagram with calculations.pdf20 Jul 2017
Building Plan Approval (IOD)File: section A-A and B-B.pdf20 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Certificate of Architect (Form 1).pdf20 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Certificate of Engineer (Form 2).pdf20 Jul 2017

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 34 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep MONTICELLO on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Bandra Reclamation6,700+ in Mumbai Suburban

2 kmMONTICELLOCompleted 28Lapsed / revoked 15Other 32Dot size: filed unitsN

Filed coordinates, straight-line distance. 75 registered projects within 2 km.

Builder: SAMUDRA DEVELOPERS PRIVATE LIMITED

SAMUDRA DEVELOPERS PRIVATE LIMITED has 1 registration on MahaRERA, including MONTICELLO. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that MONTICELLO shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if MONTICELLO is delayed beyond 29 Sep 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of MONTICELLO?

The registered promoter entity is SAMUDRA DEVELOPERS PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in MONTICELLO?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for MONTICELLO?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at MONTICELLO?

The professionals named in the filing: Architect: GVS ARCHITECTS & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MONTICELLO?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MONTICELLO. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MONTICELLO to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.