Home / Browse projects / Mumbai City, Maharashtra / MONTESOUTH TITLIS 4

Registered Litigation declared Residential / Group Housing project

MONTESOUTH TITLIS 4

By SWAYAM REALTORS & TRADERS LLP

RG-MH-34940 · RERA P51900048944 · Last updated on MahaRERA portal: 17 Jun 2026

Source: official MahaRERA filing

Red flags

  • Litigation declared, 2 cases
  • Rs 245.00 crore secured on the land, in favour of INDUSIND BANK

Clear

  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai City registration emailed to you, free during the pilot beta.
Jun 2027Possession promisedno revision filed
6 of 11Construction stages donefurthest along: External plumbing and external plaster, 99%
24 of 59Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 167 documents Report an error

MONTESOUTH TITLIS 4 is a Residential / Group Housing project by SWAYAM REALTORS & TRADERS LLP in Mumbai City, Maharashtra, registered with MahaRERA as P51900048944 on 24 Jan 2023. Possession is promised by 30 Jun 2027. 35 of the 59 units on this registration are recorded sold or booked, and 6 of 11 construction stages are filed complete.

At a glance

Project

  • NameMONTESOUTH TITLIS 4
  • TypeResidential / Group Housing
  • Location
    • BABURAO JAGTAP MARG
    • FIRE BRIDGADE BYCULLA
    • Byculla
    • Ward E
    • Mumbai City
    • 400008
  • Pincode400008
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51900048944
  • ReraGenie IDRG-MH-34940

Builder

  • NameSWAYAM REALTORS & TRADERS LLP
  • Entity typePartnership
  • GSTIN27ACEFS2816A1ZI
  • GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • PartnerSUNIL BALAKRISHNA SHARMA
  • Other registrations8 more →
  • Completed2 of 9
  • No longer live3 lapsed, de-registered or revoked

Key dates

this monthRegisteredJan 2023PromisedJun 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on24 Jan 2023
  • Promised completion30 Jun 2027
  • Revised completionNone
  • Buildings1 building record
  • Documents filed167 files

Current status

59%35 of 59 units booked
92.4%Work done, per cost certificate

Figures as on 17 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUILDING NO 1 / WING ANA101059059

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 17 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 11 construction stages are filed complete. The stage furthest along is External plumbing and external plaster, at 99%.

BUILDING NO 1 / WING A: 96% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises92%
Sanitary Fittings within the flats / premises80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.99%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.93%

Progress on shared amenities15

As on 17 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes40%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes25%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes50%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed52

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots52
Open Space52

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area33,179 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofINDUSIND BANK
Secured amountRs 245.00 crore
CERSAI search filedYes
Declared on4 Dec 2025

Approvals and building plan

Sanctioning authorityMCGM
Permissible FSI7332.3
Proposed, not sanctioned7,332 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGROUND FLOOR, RAGHUVANSHI MILLS COMPOUND, SENAPATI BAPAT MARG, LOWER PAREL (WEST), MUMBAI – 400 013
Estimated costRs 103.74 cr
Cost incurredRs 95.84 cr
Work done92.38%
BuildingWingEstimatedIncurred
BUILDING NO 1 / WING ANARs 91.82 crRs 87.19 cr
-NARs 11.92 crRs 8.64 cr

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSantoshkumar Premchandra Dubey
EngineerUrvesh Virendra Mehta
Chartered AccountantDinesh Ganpat Pai
Chartered AccountantPreeti Singh
Chartered AccountantB R Nagda & Co. Chartered Accountants
Chartered AccountantAnkit Shah
Chartered AccountantKaushal Chaulawala
PartnerRole in project
SWAYAM REALTORS & TRADERS LLP-

Litigation declared2

CaseCourtStatus
2669 /2008BOMBAY HIGH COURTPENDING
1980/2019BOMBAY HIGH COURTPENDING

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Aug 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 26 Feb 2026
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 26 Feb 2026
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 7 Sep 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 17 Aug 2024

Documents filed167

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 167 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Q4_AC_Form-1_Titlis-4_2026.pdf17 Jun 2026
Withdrawal Update Form 2File: Form 2 Engg Cert Tit 4 Mar 2026.pdf17 Jun 2026
Withdrawal Update Form 3File: Form 3 Cert Tit 4 Mar 2026 Sign.pdf17 Jun 2026
Withdrawal Update Form 1File: Q3_AC_Form-1_Titlis-4_2025_Rev 01.pdf28 May 2026
Withdrawal Update Form 1File: Q3_AC_Form-1_Titlis-4_2025_Rev 01.pdf28 May 2026
Withdrawal Update Form 1File: Q3_AC_Form-1_Titlis-4_2025_Rev 01.pdf28 May 2026
Withdrawal Update Form 2File: Form 2 eng cert Titlis 4 Dec 2025.pdf28 May 2026
Withdrawal Update Form 2File: Form 2 eng cert Titlis 4 Dec 2025.pdf28 May 2026
Withdrawal Update Form 2File: Form 2 eng cert Titlis 4 Dec 2025.pdf28 May 2026
Withdrawal Update Form 3File: Form 3 CA Cert Tit 4 Mar 202 pdf portal.pdf28 May 2026
Withdrawal Update Form 3File: Form 3 CA Cert Tit 4 Mar 202 pdf portal.pdf28 May 2026
Withdrawal Update Form 3File: Form 3 CA Cert Tit 4 Dec 2025 pdf portal.pdf28 May 2026
Layout approvalFile: Layout 01_18026.pdf26 Feb 2026
Building plan approvalFile: 2-4.pdf26 Feb 2026
Building plan approvalFile: 5-7.pdf26 Feb 2026
Building plan approvalFile: 8-11.pdf26 Feb 2026
Building plan approvalFile: 12-14.pdf26 Feb 2026
Building plan approvalFile: 15.pdf26 Feb 2026
Building plan approvalFile: 16.pdf26 Feb 2026
Building plan approvalFile: 17_1.pdf26 Feb 2026
Building plan approvalFile: 18.pdf26 Feb 2026
Building plan approvalFile: 19_1.pdf26 Feb 2026
Building plan approvalFile: 20_1.pdf26 Feb 2026
Building plan approvalFile: 21_1.pdf26 Feb 2026
Building plan approvalFile: 22_1.pdf26 Feb 2026
Building plan approvalFile: 23_1.pdf26 Feb 2026
Building plan approvalFile: 24_1.pdf26 Feb 2026
Building plan approvalFile: 25.pdf26 Feb 2026
Building plan approvalFile: 26.pdf26 Feb 2026
Building plan approvalFile: 27.pdf26 Feb 2026
Building plan approvalFile: 28.pdf26 Feb 2026
Building plan approvalFile: 29.pdf26 Feb 2026
Building plan approvalFile: 30.pdf26 Feb 2026
Building plan approvalFile: 31_1.pdf26 Feb 2026
Building plan approvalFile: 32.pdf26 Feb 2026
Building plan approvalFile: 33_1.pdf26 Feb 2026
Building plan approvalFile: 34_1.pdf26 Feb 2026
Building plan approvalFile: 35_1.pdf26 Feb 2026
Building plan approvalFile: 36.pdf26 Feb 2026
Building plan approvalFile: 38.pdf26 Feb 2026
Building plan approvalFile: 37.pdf26 Feb 2026
Building plan approvalFile: 39.pdf26 Feb 2026
Withdrawal Update Form 1File: Q2_AC_Form-1_Titlis-4_2025.pdf10 Feb 2026
Withdrawal Update Form 2File: Form 2_Engineeru0027s Certificate_Monte South-TB-Titlis-4- Sep 2025.pdf10 Feb 2026
Withdrawal Update Form 3File: Form 3 CA Cert Titlis 4 Sep 2025.pdf10 Feb 2026
Layout approvalFile: AMENDED BLOCK PLAN 260225.pdf30 Jan 2026
Building plan approvalFile: AMENDED PLAN FOR 54TH TO 64TH 260225.pdf30 Jan 2026
Withdrawal Update Form 1File: Q2_AC_Form-1_Titlis-4_2025.pdf11 Dec 2025
Withdrawal Update Form 2File: Form 2_Engineeru0027s Certificate_Monte South-TB-Titlis-4- Sep 2025.pdf11 Dec 2025
Withdrawal Update Form 3File: Form 3 CA Cert Titlis 4 Sep 2025.pdf11 Dec 2025
Withdrawal Update Form 1File: Q2_AC_Form-1_Titlis-4_2025.pdf9 Dec 2025
Withdrawal Update Form 2File: Form 2_Engineeru0027s Certificate_Monte South-TB-Titlis-4- Sep 2025.pdf9 Dec 2025
Withdrawal Update Form 3File: 202509 RERA Certificate Montesouth Tower A Titlis 4 Form 3.pdf9 Dec 2025
Form 5 (FY 2024-2025)File: Form 5 Titlis 4 2024-25.pdf9 Dec 2025
Form 1File: Q3_AC_Form-1_Titlis-4_2023.pdf4 Dec 2025
Form 2File: Form 2 Engg Cert Tit 4 Dec 2023.pdf4 Dec 2025
Form 3File: Form 3 Ca Certificate TIT-4 Dec-23.pdf4 Dec 2025
Disclosure of Sold and Booked InventoryFile: Disclosur Sold Unsold Dec 2023.pdf4 Dec 2025
Form 1File: Q1_AC_Form-1_Titlis-4_2024.pdf4 Dec 2025
Form 2File: Form 2 Engg Cert Titlis 4 Jun 2024.pdf4 Dec 2025
Form 3File: Form 3 Montesouh Tit-4 June-24.pdf4 Dec 2025
Disclosure of Sold and Booked InventoryFile: Form 3 Montesouh Tit-4 June-24.pdf4 Dec 2025
Form 1File: Q2_AC_Form-1_Titlis-4_2024.pdf4 Dec 2025
Form 2File: Form 2_Engg Cert Titlis 4 SEP 2024.pdf4 Dec 2025
Form 3File: Form 3 RERA Certificate Titlis 4 Sep 2024.pdf4 Dec 2025
Disclosure of Sold and Booked InventoryFile: Disclosure Sold Unsold Titlis 4 Sep 2024.pdf4 Dec 2025
Form 1File: Q3_AC_Form-1_Titlis-4_2024.pdf4 Dec 2025
Form 2File: Engineer's Certificate_Monte South Titils-4 Dec 2024.pdf4 Dec 2025
Form 3File: Form 3 CA Cert Tit-4 Dec 2024.pdf4 Dec 2025
Disclosure of Sold and Booked InventoryFile: Disclouser Sold Unsold Tit-4 Dec 2024.pdf4 Dec 2025
Form 1File: Q4_AC_Form-1_Titlis-4_2024.pdf4 Dec 2025
Form 2File: Form 2_Engineer's Certificate_ Titlis 4 - March 2024.pdf4 Dec 2025
Form 3File: Form 3 Ca Certficate TIT -4 Mar 24.pdf4 Dec 2025
Disclosure of Sold and Booked InventoryFile: Disclosure Sold Unsold TIT -4 Mar 24.pdf4 Dec 2025
Form 1File: Q1_AC_Form-1_Titlis-4_2024.pdf4 Dec 2025
Form 2File: Form 2 Engg Cert Titlis 4 Jun 2024.pdf4 Dec 2025
Form 3File: Form 3 Ca Cert Tit 4 June 24.pdf4 Dec 2025
Disclosure of Sold and Booked InventoryFile: Form 3 Montesouh Tit-4 June-24.pdf4 Dec 2025
Form 1File: Q2_AC_Form-1_Titlis-4_2024.pdf4 Dec 2025
Form 2File: Form 2 Engg Cert Tit 4 Sep 2024.pdf4 Dec 2025

How this compares with Mumbai City

59%of this project is bookeddistrict median 17%
33%of Mumbai City projects moved their completion datethis one has not
25%of Mumbai City registrations have lapsed or been cancelledthis one is on the register

Computed across the 780+ Mumbai City projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep MONTESOUTH TITLIS 4 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near FIRE BRIDGADE BYCULLA780+ in Mumbai City

2 kmMONTESOUTH TITLIS 4Completed 3Lapsed / revoked 4Other 11Dot size: filed unitsN

Filed coordinates, straight-line distance. 18 registered projects within 2 km.

Builder: SWAYAM REALTORS & TRADERS LLP

SWAYAM REALTORS & TRADERS LLP has 9 registrations on MahaRERA, including MONTESOUTH-1 and MONTESOUTH-2. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 2 of its registrations. Read the full track record. See more projects on the Mumbai City district page.

Frequently asked questions

What are my rights if MONTESOUTH TITLIS 4 is delayed beyond 30 Jun 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of MONTESOUTH TITLIS 4?

The registered promoter entity is SWAYAM REALTORS & TRADERS LLP, a partnership as per the filing. Its GSTIN 27ACEFS2816A1ZI can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in MONTESOUTH TITLIS 4?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for MONTESOUTH TITLIS 4?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at MONTESOUTH TITLIS 4?

The professionals named in the filing: Architect: Santoshkumar Premchandra Dubey; Engineer: Urvesh Virendra Mehta; Chartered Accountant: Dinesh Ganpat Pai; Chartered Accountant: Preeti Singh; Chartered Accountant: B R Nagda & Co. Chartered Accountants; Chartered Accountant: Ankit Shah. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MONTESOUTH TITLIS 4?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MONTESOUTH TITLIS 4. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MONTESOUTH TITLIS 4 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.