Home / Browse projects / Pune, Maharashtra / Monte Rosa
Monte Rosa
By Tushar Builders & BKP Infra LLP
RG-MH-26121 · RERA P52100013442 · Last updated on MahaRERA portal: 2 Dec 2024
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 34 months past the filed date
- 2 complaints at MahaRERA
Clear
- No litigation declared
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Monte Rosa is a Others project by Tushar Builders & BKP Infra LLP in Pune, Maharashtra, registered with MahaRERA as P52100013442 on 7 Oct 2017. Possession was promised by 30 Dec 2023 and is now 34 months past that date. 2 complaints are on record with the regulator.
At a glance
Project
- NameMonte Rosa
- TypeOthers
- Location
- Sinhgad Road
- Hingane Kh
- Haveli
- Pune
- 411051
- Pincode411051
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100013442
- ReraGenie IDRG-MH-26121
Builder
- NameTushar Builders & BKP Infra LLP
- Entity typePartnership
- PartnersJaswandi Lalitkumar Kudale, Tushar Sambhaji Gosavi, Vijaya Sambhaji Gosavi, Sandeep Sonba Jagade, Sameer Sonba Jagade, Sanjay Shantaram Dhankawade, Shreeniwas Sopan Londhe, Satish Mohan Bhide, Abhijit Prakash Bankar, Dilip Nivrutti Bhoj
- Declared earlier projects6 →
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on7 Oct 2017
- Promised completion30 Dec 2023
- Revised completionNone
- Buildings1 building record
- Documents filed43 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Monte Rosa | NA | 40 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 2 Dec 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
10 of 11 construction stages are filed complete. The stage furthest along is Sanitary Fittings within the flats / premises, at 95%.
Monte Rosa: 100% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 95% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 2 Dec 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | Yes | 100% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 100% |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 100% |
| Open Parking | No | Not applicable |
Parking filed681
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership2
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Tushar Gosavi | Sinhgad Road | Pune |
| Ketan Gosavi | Sinhgad Road | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Vilas Yele |
| Engineer | Nitin Londhe |
| Chartered Accountant | SPCM & Associates |
| Partner | Role in project |
|---|---|
| Tushar Builders & BKP Infra LLP | - |
Complaints filed with MahaRERA2
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC005000000269507 | Vyankatesh Jagnnath Pharande | TUSHAR BUILDERS AND BKP INFRA LLP | 02/10/2023 |
| CC005000000340730 | Ravindra Gopal Shahane | Tushar Builder & BKP Infra LLP | 05/04/2024 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 28 Sep 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 28 Sep 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 28 Sep 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 25 Dec 2018Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 2 Dec 2024
Documents filed43
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Architect’s Certificate on Completion of Project (Form 4)File: RERA Architect Form 4 Completion.pdf | 2 Dec 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Part OC.pdf | 2 Dec 2024 |
| Certificates of CA (Form 3)File: Form3Tushar.pdf | 17 Apr 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form5Tushar.pdf | 17 Apr 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Completion Certificate.pdf | 27 Dec 2023 |
| Certificates of CA (Form 3)File: FORM 3 (20-21).pdf | 15 Feb 2023 |
| Certificates of CA (Form 3)File: FORM 3 (21-22).pdf | 15 Feb 2023 |
| Certificates of CA (Form 5)File: RERA FORM 5 (20-21).pdf | 15 Feb 2023 |
| Certificates of CA (Form 5)File: RERA FORM 5 (21-22).pdf | 15 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: RERA FORM 5 (20-21).pdf | 15 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: RERA FORM 5 (21-22).pdf | 15 Feb 2023 |
| Certificates of CA (Form 3)File: CA FORM 03 March 2021_compressed.pdf | 14 Sep 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5 BKP INFRA-2019-FY-2018-2019_compressed.pdf | 10 May 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 5-Monte Rosa- FY-2019-2020_compressed (1).pdf | 10 May 2021 |
| OtherFile: CREDAI Certificate.pdf | 10 Jan 2020 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Monte Rosa Self Declairation.pdf | 7 Jan 2020 |
| OtherFile: Monte Rosa Self Declairation.pdf | 7 Jan 2020 |
| Proforma of Allotment letterFile: RERA Draft Agreement-min.pdf | 6 Jan 2020 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Monte Rosa Architect RERA Form-1_compressed.pdf | 12 Oct 2019 |
| Form 2AFile: Monte Rosa Form-2A- Engineer Certificate Sept-19-compressed.pdf | 2 Oct 2019 |
| OtherFile: Monte Rosa Form-2- Engineer Certificate.pdf | 2 Oct 2019 |
| Form 2AFile: MONTE ROSA RERA FORM -A_compressed.pdf | 27 Jun 2019 |
| Certificates of CA (Form 5)File: CA RERA Form No 5.pdf | 4 Jan 2019 |
| OtherFile: Road Agreement.pdf | 26 Dec 2018 |
| PAN CardFile: PAN Card Tushar Builders BKP Infra LLP.pdf | 25 Dec 2018 |
| Details of encumbrancesFile: Encumbarancess Declairation.pdf | 25 Dec 2018 |
| Details of encumbrancesFile: Mortgage Index.pdf | 25 Dec 2018 |
| Commencement Certificates / NA Order for plotted developmentFile: Revised CC MonteRosa.pdf | 25 Dec 2018 |
| Commencement Certificates / NA Order for plotted developmentFile: Revised CC MonteRosa.pdf | 25 Dec 2018 |
| Declaration in FORM BFile: RERA Form B 251218-compressed.pdf | 25 Dec 2018 |
| Certificates of CA (Form 5)File: CA RERA Form No 5.pdf | 25 Dec 2018 |
| OtherFile: LLP Certificate of Conversion of Firm into LLP.pdf | 25 Dec 2018 |
| OtherFile: EC Monterosa.pdf | 31 Mar 2018 |
| Details of encumbrancesFile: DECLARATION FORM B 2.pdf | 6 Oct 2017 |
| Declaration in FORM BFile: Form B_1MB.pdf | 6 Oct 2017 |
| Building plan approvalFile: IOD.pdf | 28 Sep 2017 |
| Layout approvalFile: Layout.pdf | 28 Sep 2017 |
| Copy of the legal title reportFile: Title-ilovepdf-compressed (1).pdf | 28 Sep 2017 |
| Copy of Layout Approval (in case of layout)File: Layout.pdf | 28 Sep 2017 |
| Building Plan Approval (IOD)File: IOD.pdf | 28 Sep 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: CC.pdf | 28 Sep 2017 |
| Certificates of CA (Form 3)File: CA.pdf | 28 Sep 2017 |
| Proforma of Allotment letterFile: MONTEROSA RERA DRAFT TO BE UPLOAD .pdf | 28 Sep 2017 |
Promoter's earlier projects5
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| Viviana | Panchawati Nashik | 92 | Completed | Sep 2017 | Jul 2017 |
| Ramrajya Sankul A and B wing | Panchawati Nashik | 70 | Completed | Mar 2017 | Late, Jul 2017 |
| Abelone Wing B | Ambegaon Pune | 64 | Completed | Mar 2016 | Jan 2016 |
| Bhargav House | Hingne KH | 6 | Completed | Mar 2014 | Mar 2014 |
| Bharagav Palace | Vadgaon | 72 | Completed | Mar 2008 | Mar 2008 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 43 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep Monte Rosa on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Hingane Kh13,700+ in Pune
Filed coordinates, straight-line distance. 100 registered projects within 2 km.
Aura Waters Phase II
Ranawat Properties
OM PARADISE
OM GHULE LEGACIES LLP
Aura Waters Phase -I
Ranawat Properties
RAMANA PRIMAVISTA
RAJENDRA VINAYAK PATAHRE
VENKATESH SKYDALE PHASE 4
Shree Venkatesh Buildcon
Kanchan Heights
Orbiz Estate
Builder: Tushar Builders & BKP Infra LLP
Tushar Builders & BKP Infra LLP has 1 registration on MahaRERA, including Monte Rosa. Its filings disclose 6 earlier MahaRERA projects: declares 5 of 6 past projects completed on time. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What does it mean that Monte Rosa shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Monte Rosa is delayed beyond 30 Dec 2023?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Monte Rosa?
The registered promoter entity is Tushar Builders & BKP Infra LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Monte Rosa?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Monte Rosa?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Monte Rosa?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Monte Rosa?
The professionals named in the filing: Architect: Vilas Yele; Engineer: Nitin Londhe; Chartered Accountant: SPCM & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Monte Rosa?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback