ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai Suburban, Maharashtra / MODIREALTY KALPVRIKSH

Completed No litigation declared Residential / Group Housing project

MODIREALTY KALPVRIKSH

By MODIREALTY DEVELOPERS PVT LTD

RG-MH-74712 · RERA P51800034375 · Last updated on MahaRERA portal: 16 Feb 2024

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA
  • All 3 earlier projects delivered on promise

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 5 other registrations and every project registered within 2 km.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Mar 2025Possession promisedregistration recorded completed
10 of 11Construction stages donefurthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 41 documents Report an error

MODIREALTY KALPVRIKSH is a Residential / Group Housing project by MODIREALTY DEVELOPERS PVT LTD in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800034375 on 4 Apr 2022. The registration is recorded completed; possession was promised by 31 Mar 2025.

At a glance

Project

  • NameMODIREALTY KALPVRIKSH
  • TypeResidential / Group Housing
  • Location
    • LALLUBHAI PARK ROAD
    • ANDHERI WEST
    • Andheri
    • Mumbai Suburban
    • 400058
  • Pincode400058
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800034375
  • ReraGenie IDRG-MH-74712

Builder

  • NameMODIREALTY DEVELOPERS PVT LTD
  • Entity typeCompany
  • CINU70109MH2020PTC350147
  • GSTIN27AAOCM0584E1ZB
  • GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • DirectorsKESHAV Sunil MODI, GAUTAM Sunil MODI
  • Other registrations5 more →
  • Completed3 of 6
  • Declared earlier projects3 →

Key dates

this monthRegisteredApr 2022PromisedMar 2025Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on4 Apr 2022
  • Promised completion31 Mar 2025
  • Revised completionNone
  • Buildings1 building record
  • Documents filed41 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
MODIREALTY KALPVRIKSHNA130000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 16 Feb 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

MODIREALTY KALPVRIKSH: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 16 Feb 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed22

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots22
Closed/Covered22

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area789 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
ORION CHS LTDAndheriMumbai Suburban

Approvals and building plan

Permissible FSI2343.33
Proposed, not sanctioned2,343 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch30, Navyog SOC Krishna Kunj, VL Mehta Rd, Juhu, Vile Parle West, Mumbai, Maharashtra 400056

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMEHUL KANAKIA
EngineerRupesh Chowdhury
Chartered AccountantK C JAIN CO Yash Singhal
PartnerRole in project
MODIREALTY DEVELOPERS PVT LTD-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 25 Mar 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 22 Mar 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 22 Mar 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 20 Jul 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 28 Oct 2023

Documents filed41

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory _ K.pdf16 Feb 2024
Architect’s Certificate on Completion of Project (Form 4)File: Form 4 Architect Certificate.pdf17 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Sept 2023 Kalpvriksh compressed.pdf4 Nov 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 April 23 to Oct 23-1.pdf4 Nov 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Kalpvriksh_OC (1).pdf28 Oct 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: No Encumbrance on Bank Account.pdf23 Jul 2022
Deviation Report with respect to Allotment letterFile: Deviation Letter for Allotment Letter.pdf23 Jul 2022
Deviation Report with respect to model copy of AgreementFile: Deviation Letter for Sale Agreement.pdf23 Jul 2022
Commencement Certificates / NA Order for plotted developmentFile: Further CC_Orion.pdf20 Jul 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - June 2022.pdf20 Jul 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - June 2022.pdf20 Jul 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Kalpavriksh signed.pdf20 Jul 2022
Copy of the legal title reportFile: Legal Title Report_Wisteria.pdf25 Mar 2022
Copy of the legal title reportFile: Flow of Title_Wisteria.pdf25 Mar 2022
Layout approvalFile: IOD Approved Plan 1.pdf22 Mar 2022
Layout approvalFile: IOD Approved Plan 2.pdf22 Mar 2022
Layout approvalFile: IOD Approved Plan 3.pdf22 Mar 2022
Building plan approvalFile: IOD Approved Plan 1.pdf22 Mar 2022
Building plan approvalFile: IOD Approved Plan 2.pdf22 Mar 2022
Building plan approvalFile: IOD Approved Plan 3.pdf22 Mar 2022
Copy of Layout Approval (in case of layout)File: IOD Approved Plan 1.pdf22 Mar 2022
Copy of Layout Approval (in case of layout)File: IOD Approved Plan 2.pdf22 Mar 2022
Copy of Layout Approval (in case of layout)File: IOD Approved Plan 3.pdf22 Mar 2022
Building Plan Approval / NA Order for plotted developmentFile: IOD Approved Plan 1.pdf22 Mar 2022
Building Plan Approval / NA Order for plotted developmentFile: IOD Approved Plan 2.pdf22 Mar 2022
Building Plan Approval / NA Order for plotted developmentFile: IOD Approved Plan 3.pdf22 Mar 2022
CERSAI detailsFile: CERSAI_Search_Report_200233127436_For_Asset_Based_Search.pdf22 Mar 2022
Details of encumbrancesFile: Declaration for Emcumbrances_001.pdf21 Mar 2022
Declaration about Commencement CertificateFile: Declaration for Commencenrt Certificate_001.pdf21 Mar 2022
Declaration in FORM BFile: Form B.pdf21 Mar 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf21 Mar 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Modirealty Developers Private Limited Form 3.pdf21 Mar 2022
Status of ConveyanceFile: Orion Conveyance Deed.pdf21 Mar 2022
OtherFile: 1_PRC 608B.pdf21 Mar 2022
OtherFile: Additionalr Declaration_001.pdf21 Mar 2022
Commencement Certificates / NA Order for plotted developmentFile: FirstCC_signed - Orion.pdf17 Mar 2022
CERSAI detailsFile: CERSAI_Search_Report_For_Debtor_Based_Search.pdf17 Mar 2022
Proforma of Allotment letterFile: Allotment Letter Draft.pdf17 Mar 2022
Proforma of Allotment letterFile: RERA draft Agreement for Sale.pdf17 Mar 2022
Status of Formation of Legal Entity (Society/Co Op etc.)File: T_Registration Certificate _Orion.pdf17 Mar 2022
PAN CardFile: Modirealty PAN.pdf25 Feb 2022

Promoter's earlier projects3

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

3 delivered on promise
ProjectLocationFlatsRegisteredStatusPromisedDelivered
Modirealty VatvrikshP51800047278Goregaon West, Mumbai Suburban99Oct 2022CompletedSep 2026Apr 2025
MODIREALTY WISTERIAP51800034890KANDIVALI WEST, Mumbai Suburban107Apr 2022CompletedMar 2026Feb 2025
MODIREALTY KALPVRIKSHLallubhai Park Andheri west Mumbai 40005811-CompletedMar 2025Oct 2023

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one has not
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is completed

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep MODIREALTY KALPVRIKSH on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near ANDHERI WEST6,700+ in Mumbai Suburban

2 kmMODIREALTY KALPVRIKSHCompleted 170Lapsed / revoked 105Other 173Dot size: filed unitsN

Filed coordinates, straight-line distance. 448 registered projects within 2 km.

Builder: MODIREALTY DEVELOPERS PVT LTD

MODIREALTY DEVELOPERS PVT LTD has 6 registrations on MahaRERA, including MODIREALTY KALPVRIKSH and MODIREALTY WISTERIA. Its filings disclose 3 earlier MahaRERA projects: declares 3 of 3 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if MODIREALTY KALPVRIKSH is delayed beyond 31 Mar 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of MODIREALTY KALPVRIKSH?

The registered promoter entity is MODIREALTY DEVELOPERS PVT LTD, a company as per the filing. Its CIN U70109MH2020PTC350147 and GSTIN 27AAOCM0584E1ZB can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in MODIREALTY KALPVRIKSH?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for MODIREALTY KALPVRIKSH?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at MODIREALTY KALPVRIKSH?

The professionals named in the filing: Architect: MEHUL KANAKIA; Engineer: Rupesh Chowdhury; Chartered Accountant: K C JAIN CO Yash Singhal. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MODIREALTY KALPVRIKSH?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MODIREALTY KALPVRIKSH. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MODIREALTY KALPVRIKSH to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.