Alpine Primo

By ALPINE INFRAHEIGHTS LLP

RG-MH-30581 · RERA P51800030851 · Last updated on MahaRERA portal: 20 Jun 2026

Source: official MahaRERA filing

Red flags

  • 4 complaints at MahaRERA
  • Completion date moved by 24 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 24 months from the original
12 of 33Construction stages doneacross 3 buildings; furthest along: Podiums (if any), 95%
133 of 219Units unsoldnot recorded sold or booked
4Complaints at MahaRERAon this registration
Jump to the 96 documents Report an error

Alpine Primo is a Others project by ALPINE INFRAHEIGHTS LLP in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800030851 on 20 Sep 2021. Possession is promised by 31 Dec 2026. The completion date has moved by 24 months from the original filing. 86 of the 219 units on this registration are recorded sold or booked, and 12 of 33 construction stages are filed complete. 4 complaints are on record with the regulator.

At a glance

Project

  • NameAlpine Primo
  • TypeOthers
  • Location
    • J P Road & S N Patil Marg
    • Andheri West
    • Andheri
    • Mumbai Suburban
    • 400058
  • Pincode400058
  • RERA no.P51800030851
  • ReraGenie IDRG-MH-30581

Builder

  • NameALPINE INFRAHEIGHTS LLP
  • Entity typePartnership
  • PartnersVickash Rajendra Chowdhury, Aniket Rohidas Mhatre

Key dates

this monthRegisteredSep 2021First promiseDec 2024Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on20 Sep 2021
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 31 Dec 2024)
  • Buildings3 building records
  • Documents filed96 files

Current status

39%86 of 219 units booked
77.1%Work done, per cost certificate

Figures as on 20 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Alpine Primo -A WingNA1711542882
Alpine Primo -B WingNA1711391857
Alpine Primo - C WingNA1812522880

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 20 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

12 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Podiums (if any), at 95%.

Alpine Primo -A Wing76%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)95%
Plinth100%
Stilt Floor95%
Slabs of Super Structure82%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises40%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks40%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.30%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Alpine Primo -B Wing76%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)95%
Plinth100%
Stilt Floor95%
Slabs of Super Structure82%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises40%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks40%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.30%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Alpine Primo - C Wing76%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)95%
Plinth100%
Stilt Floor95%
Slabs of Super Structure82%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises40%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks40%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.30%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 20 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed99

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots99
Closed/Covered99
BuildingClosed/CoveredTotal
Alpine Primo -A Wing6262
Alpine Primo -B Wing1717
Alpine Primo - C Wing2020

Land and ownership2

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area3,625 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on19 Dec 2025
LandownerVillageDistrict
Sunil Shopping Centre Co Op Hsg Soc LtdAndheriMumbai Suburban
ALPINE INFRAHEIGHTS LLPMaladMumbai Suburban

Approvals and building plan

Sanctioning authorityMCGM
Permissible FSI11462.58
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMAKER MAHAL, TURNER ROAD BRANCH
Estimated costRs 87.67 cr
Cost incurredRs 67.55 cr
Work done77.06%
BuildingWingEstimatedIncurred
Alpine Primo -A WingNARs 59.00 crRs 46.66 cr
Alpine Primo -B WingNARs 14.33 crRs 10.45 cr
Alpine Primo - C WingNARs 14.33 crRs 10.45 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAshim Khatri
EngineerMohammed Afzal Haque
EngineerMohammad Shakir Ansari
Chartered AccountantUTSAV MILAN SHAH
Chartered AccountantAvin K Shah & Associates
PartnerRole in project
ALPINE INFRAHEIGHTS LLP-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800023040Dec 2024 → Dec 2025

Reason as filed by the promoterWe understand the importance of adhering to project timelines as per MahaRERA regulations, and we assure you that our team is working diligently to mitigate these challenges. However, in the interest of transparency and to ensure the successful completion of the project in accordance with the quality standards set by MahaRERA, we kindly request an extension of 12 months to the original project completion date.

EA26122519033Dec 2024 → Dec 2026

Reason as filed by the promoterdue to delay in sanctioned plans from concerned authority, therefore there was delay in completing the project, hence we request you to kindly grant us extension for further period of 12 months, so shall we complete and comply with MahaRERA norms.

Complaints filed with MahaRERA4

Case no.ComplainantRespondentFiled
CC12400893Aniket MhatreRishabh Rakesh Yadav26/11/2024
CC12601728Sandeep SinghALPINE INFRAHEIGHTS LLP25/03/2026
CC12601868Anil GoyalALPINE INFRAHEIGHTS LLP30/03/2026
CC12604795Prabhat ChandraALPINE INFRAHEIGHTS LLP30/07/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 3 Sep 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 3 Sep 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 27 Nov 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 29 Mar 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed96

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 96 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: q3 form 1 .pdf20 Jun 2026
Withdrawal Update Form 1File: Form 1 Q4 FY 2526 (1).pdf20 Jun 2026
Withdrawal Update Form 2File: form 2 q3.pdf20 Jun 2026
Withdrawal Update Form 2File: form 2 q4.pdf20 Jun 2026
Withdrawal Update Form 3File: FORM 3.pdf20 Jun 2026
Withdrawal Update Form 3File: Form 3 Mar-26 Rev.pdf20 Jun 2026
Form 2A (FY 2024-2025)File: Form 2A (1).pdf27 Dec 2025
Form 2A (FY 2023-2024)File: Form 2A 24.pdf27 Dec 2025
Form 5 (FY 2023-2024)File: Form 5 n24.pdf27 Dec 2025
Withdrawal Update Form 1File: Form 1 Q1 25-26.pdf24 Dec 2025
Withdrawal Update Form 1File: Form 1 FY 25-26.pdf24 Dec 2025
Withdrawal Update Form 2File: Form 2 Q1 25-26.pdf24 Dec 2025
Withdrawal Update Form 2File: Form 2 25-26.pdf24 Dec 2025
Withdrawal Update Form 3File: Form 3 Q1 25-26.pdf24 Dec 2025
Withdrawal Update Form 3File: Form 3 FY 25-26.pdf24 Dec 2025
Form 5 (FY 2024-2025)File: Form 5 FY 24-25.pdf22 Dec 2025
Form 1File: Form 2 Q1 2025.pdf15 Jul 2025
Form 2File: Form 2 Q1 2025.pdf15 Jul 2025
Form 3File: Form 3 Q1 2025.pdf15 Jul 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Unsold Inventory Q1 2025.pdf15 Jul 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf19 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Dec 2024.pdf19 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Dec 2024.pdf19 Mar 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory.pdf19 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q2.pdf6 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q3.pdf6 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Q2 24.pdf6 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Q3 24.pdf6 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Q2.pdf6 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Q3 2024.pdf6 Dec 2024
Disclosure of sold/ booked inventoryFile: Sold n Unsold Inventory Q2.pdf6 Dec 2024
Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory List Q3.pdf6 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf27 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A.pdf27 Jun 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory.pdf27 Jun 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Discloser Annexure A Mr VIckash Chowdhury.pdf27 Jun 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Discloser Annexure A Mr Aniket Mhatre.pdf27 Jun 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5.pdf27 Jun 2024
Proforma of Agreement for saleFile: Draft of Agreement for Sale.pdf27 Jun 2024
Status of Formation of Legal Entity (Society/Co Op etc.)File: Registration Certificate.pdf27 Jun 2024
Deviation Report with respect to Allotment letterFile: Deviation Report With Respect to Allotment Letter.pdf27 Jun 2024
Deviation Report with respect to model copy of AgreementFile: Deviation Report With Respect to Allotment Letter.pdf27 Jun 2024
Deviation Report with respect to model copy of AgreementFile: Deviation Report With Respect to Agreement For Sa.pdf27 Jun 2024
Declaration in FORM BFile: FORM B Affidavit cum Declarationcompressed.pdf18 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer.pdf7 May 2024
Disclosure of sold/ booked inventoryFile: sold unsold inventories.pdf7 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 31 12 2023.pdf7 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 31 03 24.pdf7 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 31 12 2023.pdf7 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 31 03 24.pdf7 May 2024
Status of ConveyanceFile: Conveyance.pdf12 Apr 2024
Details of encumbrances concerned to FinanceFile: Non Encumbrance certificate.pdf8 Apr 2024
Details of encumbrances concerned to LegalFile: Non Encumbrance certificate.pdf8 Apr 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5.pdf8 Apr 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration separate bank.pdf8 Apr 2024
Disclosure of sold/ booked inventoryFile: sold unsold Inventory.pdf4 Apr 2024
Commencement Certificates / NA Order for plotted developmentFile: Further CC.pdf29 Mar 2024
Commencement Certificates / NA Order for plotted developmentFile: Further CC.pdf29 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate.pdf29 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf29 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate.pdf20 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer’s certificate .pdf20 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 - Signed (1).pdf13 Mar 2024
Disclosure of sold/ booked inventoryFile: sold unsold.pdf2 Feb 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A as on 31st March 2022.pdf17 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A as on 31st March 2023.pdf17 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 -Alpine - Signed (1).pdf28 Dec 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf7 Dec 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf7 Dec 2023
Building plan approvalFile: Building Plan upto 4th Flooe.pdf27 Nov 2023
Building Plan Approval / NA Order for plotted developmentFile: Building Plan upto 4th Flooe.pdf27 Nov 2023
Commencement Certificates / NA Order for plotted developmentFile: CC upto 4th floor.pdf20 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1795 RERA CERTIFICATE 31072023.pdf1 Aug 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_compressed.pdf3 May 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Alpine (2).pdf2 May 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1795 RERA CERTIFICATE.pdf26 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 Signed_compressed.pdf26 Apr 2023
PAN CardFile: Alpine Infra Heights LLP Pan Card.pdf13 Feb 2023
CERSAI detailsFile: Alpine Primo.pdf24 May 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- Alpine Primo - 31 Dec 2021.pdf23 May 2022

How this compares with Mumbai Suburban

39%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 24 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Alpine Primo on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Andheri West6,700+ in Mumbai Suburban

Builder: ALPINE INFRAHEIGHTS LLP

ALPINE INFRAHEIGHTS LLP has 1 registration on MahaRERA, including Alpine Primo. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if Alpine Primo is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Alpine Primo?

The registered promoter entity is ALPINE INFRAHEIGHTS LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Alpine Primo?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Alpine Primo?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Alpine Primo?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Alpine Primo?

The professionals named in the filing: Architect: Ashim Khatri; Engineer: Mohammed Afzal Haque; Engineer: Mohammad Shakir Ansari; Chartered Accountant: UTSAV MILAN SHAH; Chartered Accountant: Avin K Shah & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Alpine Primo?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Alpine Primo. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Alpine Primo to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.