MODIREALTY DEVELOPERS PVT LTD: RERA track record
CIN U70109MH2020PTC350147 · GSTIN 27AAOCM0584E1ZB · Company · attribution by exact filing name, entity resolution in progress
MODIREALTY DEVELOPERS PVT LTD has 6 registrations on MahaRERA, including MODIREALTY KALPVRIKSH and MODIREALTY WISTERIA. Its filings disclose 3 earlier MahaRERA projects: declares 3 of 3 past projects completed on time.
Projects by this developer
Showing all 6 projects.
Largest first, by the unit count in the filing.
| Project | Location | Units | Booked | Registered | Status |
|---|---|---|---|---|---|
| MODIREALTY ASHVATTHAP51800051189 | DAHISAR EAST, Mumbai Suburban, 400068 | 159 | 25% | 1 Jun 2023 | Registered |
| MODIREALTY ACACIAP51800056150 | Dahisar East, Mumbai Suburban, 400068 | 135 | 24% | 16 May 2024 | Registered |
| MODIREALTY WISTERIAP51800034890 | KANDIVALI WEST, Mumbai Suburban, 400067 | 107 | 60% | 28 Apr 2022 | Completed |
| Modirealty VatvrikshP51800047278 | Goregaon West, Mumbai Suburban, 400062 | 99 | 64% | 17 Oct 2022 | Completed |
| Modirealty AsopalavPM1180002502111 | Kandivali West, Mumbai Suburban, 400067 | 23 | 0% | 20 Jan 2026 | Registered |
| MODIREALTY KALPVRIKSHP51800034375 | ANDHERI WEST, Mumbai Suburban, 400058 | - | - | 4 Apr 2022 | Completed |
What this promoter declares as its own experience
MODIREALTY DEVELOPERS PVT LTD declares experience on 3 earlier projects. 2 of them carry a registration number we could match on MahaRERA, all under this promoter's own name.
2 of these declarations can be compared with the dates those projects' own registrations hold. Every one of them gives the same original completion date its registration holds.
From the promoter experience table each promoter files with MahaRERA, matched to the register by registration number. A declaration naming another promoter's project is a claim of involvement, and involvement takes several shapes: a parent and its project company, one firm re-registering under a second name, or a joint venture between two separate developers. We publish the claim as filed and do not treat it as proof that the entities are one builder.
Past projects, as disclosed in RERA filings
| Project | Promised completion | Actual completion | Delivery |
|---|---|---|---|
| MODIREALTY KALPVRIKSH | 31 Mar 2025 | 26 Oct 2023 | On time |
| MODIREALTY WISTERIA P51800034890 | 31 Mar 2026 | 4 Feb 2025 | On time |
| Modirealty Vatvriksh P51800047278 | 30 Sep 2026 | 9 Apr 2025 | On time |
Frequently asked questions
How do I verify MODIREALTY DEVELOPERS PVT LTD as a legal entity before signing?
Your agreement for sale must name the exact entity registered for the project, not a group brand. Cross-check its CIN U70109MH2020PTC350147 and GSTIN 27AAOCM0584E1ZB on the MCA and GST portals before signing anything. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.
How should I use this delivery record when booking with MODIREALTY DEVELOPERS PVT LTD?
Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.
The record above looks clean. What should I still check?
A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.
Spotted a project attributed to the wrong developer, or something else wrong on this page? Projects are grouped by the promoter name as filed, so a firm that registers under two spellings can split across two pages. Tell us and we will check it against the filings.
Report an errorShare feedbackData from official MahaRERA filings. How we handle corrections is on the about page.