ReraGenieLog inGet a buyer report

Home / Browse projects / Aurangabad, Maharashtra / Millenia Heights

Completed No litigation declared Others project

Millenia Heights

By Laxminarayan Shriramji Attal

RG-MH-02384 · RERA P51500014763 · Last updated on MahaRERA portal: 20 Oct 2022

Source: official MahaRERA filing

Red flags

  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Aurangabad registration emailed to you, free during the pilot beta.
Dec 2019Possession promisedregistration recorded completed
10 of 11Construction stages donefurthest along: Installation of Lifts, 80%
0Complaints at MahaRERAon this registration
Jump to the 46 documents Report an error

Millenia Heights is a Others project by Laxminarayan Shriramji Attal in Aurangabad, Maharashtra, registered with MahaRERA as P51500014763 on 2 Jan 2018. The registration is recorded completed; possession was promised by 15 Dec 2019.

At a glance

Project

  • NameMillenia Heights
  • TypeOthers
  • Location
    • Ashoka Layout
    • Bhagyanagar
    • Aurangabad (M Corp.)
    • Aurangabad
    • 431001
  • Pincode431001
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51500014763
  • ReraGenie IDRG-MH-02384

Builder

  • NameLaxminarayan Shriramji Attal
  • Entity typeIndividual

Key dates

this monthRegisteredJan 2018PromisedDec 2019Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on2 Jan 2018
  • Promised completion15 Dec 2019
  • Revised completionNone
  • Buildings1 building record
  • Documents filed46 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Millenia HeightsNA70000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 20 Oct 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 80%.

Millenia Heights: 98% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%

Progress on shared amenities15

As on 20 Oct 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes50%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes100%

Parking filed16

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots16
Closed/Covered10
Open Space6

Land and ownership2

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area579 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
LandownerVillageDistrict
Sunita AttalAurangabad (M Corp.)Aurangabad
Laxminarayan S AttalAurangabad (M Corp.)Aurangabad

Approvals and building plan

Permissible FSI1186.75
Proposed, not sanctioned792 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchAmarpreet Chowk, Jalna Road

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectInnerspace DesignStudio
ArchitectSachin Sangshetty Architects
EngineerAnil Datar & Associates
PartnerRole in project
Laxminarayan Shriramji Attal-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51500012524Dec 2019 → Sep 2022

Reason as filed by the promoterLockdown due to Covid-19 pandemic in Maharashtra. Unable to complete work due to the same.

EXT51500003905Dec 2019 → Dec 2020

Reason as filed by the promoterThe building is 90% ready with internal work going on. Due to the poor demand conditions, we wish to extend the completion of the project by an year.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 12 Dec 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 28 Jul 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 28 Jul 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 27 Jul 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 18 Jul 2022

Documents filed46

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate on Completion of Project (Form 4)File: Form 4 signed copy.pdf20 Oct 2022
Details of encumbrances concerned to LegalFile: Free from encumberances letter.pdf5 Sep 2022
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked inventory.pdf5 Sep 2022
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Separate bank account declaration.pdf5 Sep 2022
Layout approvalFile: Permission_March 1 of 2_compressed.pdf28 Jul 2022
Layout approvalFile: Permission_March 2 of 2_compressed.pdf28 Jul 2022
Layout approvalFile: Final Permission 1 of 2_compressed.pdf28 Jul 2022
Layout approvalFile: Final Permission_2 of 2_compressed.pdf28 Jul 2022
Building plan approvalFile: Permission_March 1 of 2_compressed.pdf28 Jul 2022
Building plan approvalFile: Permission_March 2 of 2_compressed.pdf28 Jul 2022
Building plan approvalFile: Final Permission 1 of 2_compressed.pdf28 Jul 2022
Building plan approvalFile: Final Permission_2 of 2_compressed.pdf28 Jul 2022
Copy of Layout Approval (in case of layout)File: Permission_March 1 of 2_compressed.pdf28 Jul 2022
Copy of Layout Approval (in case of layout)File: Permission_March 2 of 2_compressed.pdf28 Jul 2022
Copy of Layout Approval (in case of layout)File: Final Permission 1 of 2_compressed.pdf28 Jul 2022
Copy of Layout Approval (in case of layout)File: Final Permission_2 of 2_compressed.pdf28 Jul 2022
Building Plan Approval (IOD)File: Permission_March 1 of 2_compressed.pdf28 Jul 2022
Building Plan Approval (IOD)File: Permission_March 2 of 2_compressed.pdf28 Jul 2022
Building Plan Approval (IOD)File: Final Permission 1 of 2_compressed.pdf28 Jul 2022
Building Plan Approval (IOD)File: Final Permission_2 of 2_compressed.pdf28 Jul 2022
Declaration about Commencement CertificateFile: Deed of Correction 2.pdf28 Jul 2022
Declaration about Commencement CertificateFile: Deed of Correction_Final.pdf28 Jul 2022
Commencement Certificates / NA Order for plotted developmentFile: Last commencement.pdf27 Jul 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: DocScanner Jul 13, 2022 3-38 PM.pdf18 Jul 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Part Completion_compressed.pdf12 Jan 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Millenia Heights_Form 5_FY 19-20.pdf4 Dec 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Millenia Heights_Form 5_FY 20-21.pdf4 Dec 2021
Building plan approvalFile: Combined Revised plan_compressed (1).pdf28 Apr 2021
Building Plan Approval (IOD)File: Combined Revised plan_compressed (1).pdf28 Apr 2021
Commencement Certificates / NA Order for plotted developmentFile: Revised Commencement certificate.pdf28 Apr 2021
Disclosure of sold/ booked inventoryFile: Disclosure of sold booked inventory_compressed.pdf28 Apr 2021
Proforma of Allotment letterFile: AGREEMENT TO SALE.pdf27 Jan 2020
OtherFile: DECLARATION.pdf27 Jan 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: CA Form 5 FY18-19.pdf28 Dec 2019
Certificates of CA (Form 5)File: Form 5.pdf29 Sep 2018
Layout approvalFile: Scanned_Approved_plan_Resized.pdf27 Dec 2017
Copy of Layout Approval (in case of layout)File: Scanned_Approved_plan_Resized.pdf27 Dec 2017
Declaration in FORM BFile: Form B_Affidavit_Resized.pdf23 Dec 2017
Certificates of CA (Form 3)File: Form 3_CA.pdf20 Dec 2017
Proforma of Allotment letterFile: Model Agreement to sale_Rera.pdf20 Dec 2017
Details of encumbrancesFile: Latest_PR Card.pdf19 Dec 2017
Building plan approvalFile: Scanned_Approved_plan_Resized.pdf12 Dec 2017
Copy of the legal title reportFile: Search report_Legal.pdf12 Dec 2017
Building Plan Approval (IOD)File: Scanned_Approved_plan_Resized.pdf12 Dec 2017
Commencement Certificates / NA Order for plotted developmentFile: Construction Permission.pdf12 Dec 2017
PAN CardFile: PAN_Ind.pdf28 Nov 2017

How this compares with Aurangabad

14%of Aurangabad projects moved their completion datethis one has not
32%of Aurangabad registrations have lapsed or been cancelledthis one is completed

Computed across the 1,400+ Aurangabad projects on ReraGenie, from their own filings.

Keep Millenia Heights on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Bhagyanagar1,400+ in Aurangabad

2 kmMillenia HeightsCompleted 21Lapsed / revoked 19Other 28Dot size: filed unitsN

Filed coordinates, straight-line distance. 68 registered projects within 2 km.

Builder: Laxminarayan Shriramji Attal

Laxminarayan Shriramji Attal has 1 registration on MahaRERA, including Millenia Heights. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Aurangabad district page.

Frequently asked questions

What are my rights if Millenia Heights is delayed beyond 15 Dec 2019?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Millenia Heights?

The registered promoter entity is Laxminarayan Shriramji Attal, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Millenia Heights?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Millenia Heights?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Millenia Heights?

The professionals named in the filing: Architect: Innerspace DesignStudio; Architect: Sachin Sangshetty Architects; Engineer: Anil Datar & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Millenia Heights?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Millenia Heights. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Millenia Heights to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.