ReraGenieLog inGet a buyer report

Home / Browse projects / Thane, Maharashtra / Metropolis - RIVERA

Completed No litigation declared Residential / Group Housing project

Metropolis - RIVERA

By ANANT SQUARE

RG-MH-14385 · RERA P51700022700 · Last updated on MahaRERA portal: 24 Nov 2024

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA
  • All 2 earlier projects delivered on promise

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 8 other registrations and every project registered within 2 km.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Mar 2025Possession promisedregistration recorded completed
10 of 11Construction stages donefurthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 29 documents Report an error

Metropolis - RIVERA is a Residential / Group Housing project by ANANT SQUARE in Thane, Maharashtra, registered with MahaRERA as P51700022700 on 12 Oct 2019. The registration is recorded completed; possession was promised by 30 Mar 2025.

At a glance

Project

  • NameMetropolis - RIVERA
  • TypeResidential / Group Housing
  • Location
    • Ghodbunder Road
    • Kasarvadavali
    • Thane (M Corp.)
    • Thane
    • 400607
  • Pincode400607
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700022700
  • ReraGenie IDRG-MH-14385

Builder

  • NameANANT SQUARE
  • Entity typeOthers
  • Named personsAnant Estates, Square Feet Land Developers LLP
  • Other registrations8 more →
  • Completed6 of 9
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects11 →

Key dates

this monthRegisteredOct 2019PromisedMar 2025Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on12 Oct 2019
  • Promised completion30 Mar 2025
  • Revised completionNone
  • Buildings1 building record
  • Documents filed29 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
RIVERANA200000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 24 Nov 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

RIVERA: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities21

As on 24 Nov 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%
Open sit outYes100%
Kids Play AreaYes100%
Indoor gamesYes100%
Fitness CenterYes100%
DG power back up for common areasYes100%
CCTV in Entrance LobbyYes100%

Parking filed105

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots105
Closed/Covered105

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,620 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI6000.0
Proposed, not sanctioned5,885 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchThane-W

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectScapes
EngineerAjay Mahale
Chartered AccountantAmit Biyani
PartnerRole in project
ANANT SQUARE-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 2 Oct 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 1 Oct 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 25 Jan 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 3 Dec 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 11 Nov 2023

Documents filed29

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate on Completion of Project (Form 4)File: FORM 4_RIVERA.pdf24 Nov 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Rivera Oc.pdf11 Nov 2023
Status of Formation of Legal Entity (Society/Co Op etc.)File: Metropolis Rivera Co Op Hsg COMPRESSED.pdf11 Nov 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Metropolis Rivera - Annual Report SOA.pdf18 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Annual Report on statement of accounts Rivera 1st April 2021 To 31 st March 2022.pdf13 Oct 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Annual Report on statement of accounts Rivera_1st April 2020 To 31st March 2021.pdf15 Apr 2022
Commencement Certificates / NA Order for plotted developmentFile: S06_0275_18-compressed (1)_11zon.pdf3 Dec 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: June_2021_Rivera_Architect_Certificate.pdf18 Aug 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: June_2021_Rivera_Engineer_certificate.pdf18 Aug 2021
Disclosure of sold/ booked inventoryFile: June_2021_Rivera_Sold_Unsold_Disclosure.pdf18 Aug 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: June_2021_Rivera_CA_certificate_Form_3.pdf18 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: March_2020_Rivera_Form_5_Annual_CA_certificate.pdf18 Aug 2021
Building plan approvalFile: Plan_latest_CC.PDF25 Jan 2020
Building Plan Approval / NA Order for plotted developmentFile: Plan_latest_CC.PDF25 Jan 2020
Commencement Certificates / NA Order for plotted developmentFile: CC- RIVERA-LATEST.pdf25 Jan 2020
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3_compressed.pdf4 Oct 2019
Details of encumbrancesFile: Rivera_No Encumbrance Certificate.pdf3 Oct 2019
Declaration in FORM BFile: Rivera_Form -B_compressed.pdf3 Oct 2019
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate-RIVERA.pdf3 Oct 2019
Proforma of Allotment letterFile: ALLOTMENT LETTER.pdf3 Oct 2019
Proforma of Allotment letterFile: Rivera_Flat Sale Agreement Declaration.pdf3 Oct 2019
PAN CardFile: ANANT SQUARE pan card.pdf2 Oct 2019
Copy of the legal title reportFile: Legal Tittle Report.pdf2 Oct 2019
Layout approvalFile: RIVERA PLAN.PDF1 Oct 2019
Building plan approvalFile: RIVERA PLAN.PDF1 Oct 2019
Copy of Layout Approval (in case of layout)File: RIVERA PLAN.PDF1 Oct 2019
Building Plan Approval / NA Order for plotted developmentFile: RIVERA PLAN.PDF1 Oct 2019
Commencement Certificates / NA Order for plotted developmentFile: CC-Rivera.PDF1 Oct 2019
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Rivera_Engineer_certificate.pdf1 Oct 2019

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
Joy SquareKasarvadavali Ghodbunder Road Thane-W112CompletedDec 2019May 2019
Ace Square Phase 1kasarvadavali Ghodbunder Road Thane-W145CompletedDec 2017Oct 2017

How this compares with Thane

24%of Thane projects moved their completion datethis one has not
23%of Thane registrations have lapsed or been cancelledthis one is completed

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Metropolis - RIVERA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Kasarvadavali7,600+ in Thane

2 kmMetropolis - RIVERACompleted 81Lapsed / revoked 23Other 46Dot size: filed unitsN

Filed coordinates, straight-line distance. 150 registered projects within 2 km.

Builder: ANANT SQUARE

ANANT SQUARE has 9 registrations on MahaRERA, including Joy Square and ACE SQUARE PHASE 1. Its filings disclose 11 earlier MahaRERA projects: declares 9 of 9 past projects completed on time. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if Metropolis - RIVERA is delayed beyond 30 Mar 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Metropolis - RIVERA?

The registered promoter entity is ANANT SQUARE, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Metropolis - RIVERA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Metropolis - RIVERA?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Metropolis - RIVERA?

The professionals named in the filing: Architect: Scapes; Engineer: Ajay Mahale; Chartered Accountant: Amit Biyani. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Metropolis - RIVERA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Metropolis - RIVERA. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Metropolis - RIVERA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.