Completed No litigation declared Residential / Group Housing project

Mera Ghar

By Parshwa Gruh Nirman LLP

RG-MH-08389 · RERA P51700006760 · Last updated on MahaRERA portal: 27 Nov 2020

Source: official MahaRERA filing

Red flags

  • 10 complaints at MahaRERA
  • Completion date moved by 28 months
  • 2 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Oct 2020Possession promisedregistration recorded completed
22 of 22Construction stages doneacross 2 buildings; every applicable stage filed complete
10Complaints at MahaRERAon this registration
Jump to the 64 documents Report an error

Mera Ghar is a Residential / Group Housing project by Parshwa Gruh Nirman LLP in Thane, Maharashtra, registered with MahaRERA as P51700006760 on 16 Aug 2017. The registration is recorded completed; possession was promised by 30 Oct 2020. The completion date has moved by 28 months from the original filing. 10 complaints are on record with the regulator.

At a glance

Project

  • NameMera Ghar
  • TypeResidential / Group Housing
  • Location
    • Dahisar Waklan Road
    • Old Mumbai -Pune Highway Dist
    • Nighu
    • Thane
    • 400612
  • Pincode400612
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700006760
  • ReraGenie IDRG-MH-08389

Builder

  • NameParshwa Gruh Nirman LLP
  • Entity typePartnership
  • PartnersMitesh Vedprakash Sugla, Pankaj Dahyalal Shah, Meena Rajesh Sanghvi
  • Declared earlier projects1 →

Key dates

this monthRegisteredAug 2017First promiseJun 2018Revised toOct 2020Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on16 Aug 2017
  • Promised completion30 Oct 2020
  • Revised completionRevised to 30 Oct 2020 (originally 30 Jun 2018)
  • Buildings2 building records
  • Documents filed64 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Wing A and DNA60000
Wing B and CNA60000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 27 Nov 2020, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

22 of 22 construction stages are filed complete across 2 buildings.

Wing A and D100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Wing B and C100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 27 Nov 2020, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%

Parking filed49

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots49
Closed/Covered39
Open Space10
BuildingClosed/CoveredOpen SpaceTotal
Wing A and D19524
Wing B and C20525

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,340 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI2961.19
Proposed, not sanctioned2,961 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchVashi

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectP.K. VASTOPATI
EngineerShahnawaz Siddiqui
EngineerSHAIKH SHARUKH
Chartered AccountantKETAN KATARIA AND ASSOCIATES
Chartered AccountantJAIN AND CHAUDHARY
PartnerRole in project
Parshwa Gruh Nirman LLP-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700000434Jun 2018 → Apr 2020

Reason as filed by the promoterOur project “Mera Ghar is Registered under MAha RERA. We would not be able to submit Occupancy Certificate by June 2018 due to Last mile infrastructure is left out. Since Oc application will be given in another 2 months. Kindly allow extension of project till June 2019. Requisite fee for extension of timeline is also paid herewith.

EXT51700005338Jun 2018 → Apr 2020

Reason as filed by the promoterOur project "Mera Ghar" work is completed in all respect and request for Occupancy Certificate has been made to NAINA CIDCO vide request letter dated 23-09-2019. Occupancy Certificate is getting delayed from concerned Authority. Further there is change in approval authority from NAINA CIDCO to MMRDA.

Complaints filed with MahaRERA10

Case no.ComplainantRespondentFiled
CC006000000001845MOHAMMED ASLAM ANSARIPARSHWA GRUH NIRMAN LLP11/11/2017
CC006000000100280M/S PARSHWA GRUH NIRMAN LLPAMARJEET VERMA25/07/2019
CC006000000196184PARSHWA GRUH NIRMAN LLPSANDHYA & JAYWANT BHOIR19/03/2021
CC006000000197894MS Parshwa Gruha Nirman LLPAshok Kumar Yadav15/09/2021
CC006000000397911ALI AHMED SHORAB KHANM/S PARSHWA GRUH MIRMAN LLP19/10/2023
CC006000000398061ABDUL WAHEED KHANMS PARSHWA GRUH NIRMAN LLP04/11/2023
CC12501374Parshwa Gruh Nirman LLPGuddi Amarjeet Verma25/04/2025
CC12501389Parshwa Gruh Nirman LLPKrishna Kumar Ramchandra Prajapati26/04/2025
CC12501475Parshwa Gruh Nirman LLPAbdul Waheed Khan01/05/2025
CC12501476Parshwa Gruh Nirman LLPALI AHMED SHORAB KHAN02/05/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 16 Jan 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 27 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 24 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 13 Nov 2020

Documents filed64

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate on Completion of Project (Form 4)File: Architect Form 4 Nighu.pdf27 Nov 2020
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC mera ghar-min.pdf13 Nov 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 201005_MahaRERA Certificate_Mera Ghar (5).pdf20 Oct 2020
Certificates of CA (Form 5)File: FORM52019-2020_compressed.pdf20 Oct 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM52019-2020_compressed.pdf20 Oct 2020
Details of Restarting of Construction work post lockdownFile: PARSHWA A AND D Mera Ghar P51700006760.pdf3 Jul 2020
Details of Restarting of Construction work post lockdownFile: PARSHWA B AND C Mera Ghar P51700006760.pdf3 Jul 2020
Architect’s Certificate on Completion of Project (Form 4)File: ARCHITECT CERTIFICATE-converted.pdf17 Dec 2019
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: ARCHITECT CERTIFICATE-converted.pdf12 Dec 2019
OtherFile: Extension letter.pdf5 Oct 2019
OtherFile: NOTICE MMRDA-min.pdf5 Oct 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Rera Certificate - form 1 (1).pdf3 Jun 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 7th quaterly updation - form 2.pdf3 Jun 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf11 Feb 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate (1).pdf7 Feb 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect certificate-ilovepdf-compressed.pdf10 Dec 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 30-11-2017 form no 2 enginner certificate.pdf10 Dec 2018
Declaration in FORM BFile: Form B.pdf1 Nov 2018
Details of encumbrancesFile: Encrumbance certificate.pdf22 Oct 2018
Status of Formation of Legal Entity (Society/Co Op etc.)File: Society Letter.pdf22 Oct 2018
Certificates of CA (Form 5)File: Sign Form 5 final.pdf17 Oct 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHTIECT CERT-ilovepdf-compressed.pdf3 Aug 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architect certificate-ilovepdf-compressed.pdf24 Apr 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engineering certificate 1.pdf30 Jan 2018
Layout approvalFile: scan 1.pdf16 Jan 2018
Layout approvalFile: scan 2.pdf16 Jan 2018
Layout approvalFile: scan 3.pdf16 Jan 2018
Layout approvalFile: scan 4.pdf16 Jan 2018
Layout approvalFile: scan 5.pdf16 Jan 2018
Layout approvalFile: scan 6.pdf16 Jan 2018
Layout approvalFile: scan 7.pdf16 Jan 2018
Layout approvalFile: scan 8.pdf16 Jan 2018
Copy of Layout Approval (in case of layout)File: scan 1.pdf16 Jan 2018
Copy of Layout Approval (in case of layout)File: scan 2.pdf16 Jan 2018
Copy of Layout Approval (in case of layout)File: scan 3.pdf16 Jan 2018
Copy of Layout Approval (in case of layout)File: scan 4.pdf16 Jan 2018
Copy of Layout Approval (in case of layout)File: scan 5.pdf16 Jan 2018
Copy of Layout Approval (in case of layout)File: scan 6.pdf16 Jan 2018
Copy of Layout Approval (in case of layout)File: scan 7.pdf16 Jan 2018
Copy of Layout Approval (in case of layout)File: scan 8.pdf16 Jan 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architect certificate.pdf15 Jan 2018
Layout approvalFile: C2_new (1).pdf29 Jul 2017
Layout approvalFile: CC5 plan.pdf29 Jul 2017
Layout approvalFile: CC6 plan.pdf29 Jul 2017
Copy of the legal title reportFile: TITLE_REPORT_PHASE_I.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: CC5 plan.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: CC6 plan.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: C2_new (1).pdf29 Jul 2017
Proforma of Allotment letterFile: Agreement_for_sale_new.pdf29 Jul 2017
Layout approvalFile: CC5 plan.pdf27 Jul 2017
Layout approvalFile: CC6 plan.pdf27 Jul 2017
Layout approvalFile: CC7 plan.pdf27 Jul 2017
Building plan approvalFile: CC_Copy.pdf27 Jul 2017
Details of encumbrancesFile: Encumbrance Certificate.pdf27 Jul 2017
Copy of Layout Approval (in case of layout)File: CC5 plan.pdf27 Jul 2017
Copy of Layout Approval (in case of layout)File: CC6 plan.pdf27 Jul 2017
Copy of Layout Approval (in case of layout)File: CC7 plan.pdf27 Jul 2017
Building Plan Approval (IOD)File: CC_Copy.pdf27 Jul 2017
Declaration in FORM BFile: Affidavit_for_Rera (1).pdf27 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer s Certificate Format Filled 220717 (1).pdf27 Jul 2017
PAN CardFile: Pan Card Parshwa.pdf24 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: CC Copy.pdf24 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate-min less than 1 mb.pdf24 Jul 2017
Certificates of CA (Form 3)File: MERA GHAR CA CERTIFICATE27017.pdf24 Jul 2017

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 not delivered by the promised date
ProjectLocationFlatsRegisteredStatusPromisedDelivered
Shanti LuxuriaP51700012995Village Padle, Thane315Sep 2017OngoingDec 2025Registered original: Jun 2022Not delivered

How this compares with Thane

24%of Thane projects moved their completion datethis one moved by 28 months
23%of Thane registrations have lapsed or been cancelledthis one is completed

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Mera Ghar on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Old Mumbai -Pune Highway Dist7,600+ in Thane

2 kmMera GharLapsed / revoked 1Other 2Dot size: filed unitsN

Filed coordinates, straight-line distance. 3 registered projects within 2 km.

Builder: Parshwa Gruh Nirman LLP

Parshwa Gruh Nirman LLP has 1 registration on MahaRERA, including Mera Ghar. Its filings disclose 1 earlier MahaRERA project, none completed yet. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if Mera Ghar is delayed beyond 30 Oct 2020?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Mera Ghar?

The registered promoter entity is Parshwa Gruh Nirman LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Mera Ghar?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Mera Ghar?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Mera Ghar?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Mera Ghar?

The professionals named in the filing: Architect: P.K. VASTOPATI; Engineer: Shahnawaz Siddiqui; Engineer: SHAIKH SHARUKH; Chartered Accountant: KETAN KATARIA AND ASSOCIATES; Chartered Accountant: JAIN AND CHAUDHARY. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Mera Ghar?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Mera Ghar. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Mera Ghar to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.