Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 16 other registrations and every project registered within 2 km.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Mar 2020Possession promisedregistration recorded completed
20 of 22Construction stages doneacross 2 buildings; furthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 28 documents Report an error

Megapolis Mystic Phase 2 is a Residential / Group Housing project by Pegasus Properties Pvt. Ltd. in Pune, Maharashtra, registered with MahaRERA as P52100001391 on 27 Jul 2017. The registration is recorded completed; possession was promised by 1 Mar 2020.

At a glance

Project

  • NameMegapolis Mystic Phase 2
  • TypeResidential / Group Housing
  • Location
    • Megapolis Spleandour Road
    • Hinjewadi
    • Hinjavadi (CT)
    • Mulshi
    • Pune
    • 411057
  • Pincode411057
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100001391
  • ReraGenie IDRG-MH-09472

Builder

  • NamePegasus Properties Pvt. Ltd.
  • Entity typeCompany
  • CINU70102PN2007FTC129540
  • CIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • Managing DirectorManoj Praveenchandra Shah
  • DirectorYogesh Yashwant Bhave
  • Other registrations16 more →
  • Completed13 of 17
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects13 →

Key dates

this monthRegisteredJul 2017PromisedMar 2020Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on27 Jul 2017
  • Promised completion1 Mar 2020
  • Revised completionNone
  • Buildings2 building records
  • Documents filed28 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Type 4A Wing DNA250000
Type 2A Wing ENA250000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 15 Apr 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

20 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Podiums (if any), at 0%.

Type 4A Wing D91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Type 2A Wing E91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 15 Apr 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%

Parking filed299

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots299
Closed/Covered277
Open Space22
BuildingClosed/CoveredOpen SpaceTotal
Type 4A Wing D15218170
Type 2A Wing E1254129

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area10,870 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI19565.99
Proposed, not sanctioned19,566 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchKP Housing Society, General Thimayya Road, East Street, Camp, Pune - 411001

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAr Anil Madhusudan Kulkarni
EngineerNarayan Hanmantgad
Chartered AccountantSupriya Abhijit Mundada
Chartered AccountantMSKA & Associates
PartnerRole in project
Pegasus Properties Pvt. Ltd.-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 6 Aug 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 20 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 20 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 20 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 15 Apr 2023

Documents filed28

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 170929_OC_E.pdf15 Apr 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 190627_OC_D.pdf15 Apr 2023
Certificates of Architect (Form 4)File: 230412_Arch Certificate_Form 4.pdf15 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: 2 Certificates of CA (Form 5).pdf19 Jan 2023
Status of Formation of Legal Entity (Society/Co Op etc.)File: 5_Megapolis Mystic.pdf21 Oct 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: 5_Megapolis Mystic Phase II_compressed.pdf21 Dec 2020
Copy of the legal title reportFile: 200804_Continuation Title Opinion.pdf6 Aug 2020
Certificates of CA (Form 5)File: 190928_Form 5_Annual Audit Report_compressed.pdf28 Sep 2019
Certificates of CA (Form 5)File: 180929_Form 5_Mystic_Phase II.pdf17 Oct 2018
Copy of the legal title reportFile: 2_Mystic_Continuation Legal Title Report.pdf10 Jul 2018
Proforma of Allotment letterFile: 5_Mystic - D and E_Revised Allotment and Agreement.pdf7 Jun 2018
Certificates of Architect (Form 4)File: Mystic_E_Form 4_Architect Certificate.pdf27 Apr 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Megapolis Mystic_Architect's certificate.pdf18 Oct 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Megapolis Mystic_Engineer's Certificate.pdf18 Oct 2017
Certificates of CA (Form 3)File: Mystic_CA Certificate.pdf18 Oct 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 7_Mystic_Architect Certificate.pdf22 Jul 2017
Certificates of CA (Form 3)File: 8_Mystic_CA Certificate.pdf22 Jul 2017
Proforma of Allotment letterFile: 5_Mystic_Allotment and Agreement.pdf22 Jul 2017
Building plan approvalFile: 13_Mystic_Building Plans.pdf20 Jul 2017
Layout approvalFile: 4_Mystic_Sanctioned Layout.pdf20 Jul 2017
Copy of the legal title reportFile: 2_Mystic _Legal Title Opinion.pdf20 Jul 2017
Copy of Layout Approval (in case of layout)File: 4_Mystic_Sanctioned Layout.pdf20 Jul 2017
Building Plan Approval (IOD)File: 13_Mystic_Building Plans.pdf20 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: 12_Mystic_Commencement Certificate.pdf20 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 11_Mystic_Engineer's Certificate.pdf20 Jul 2017
PAN CardFile: 1_Pegasus_Pan Card.PDF18 Jul 2017
Details of encumbrancesFile: 3_Mystic_Encumberances.pdf18 Jul 2017
Declaration in FORM BFile: 6_Mystic_Form B Declaration.pdf18 Jul 2017

Promoter's earlier projects13

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

10 delivered on promise3 delivered late
ProjectLocationFlatsStatusPromisedDelivered
Megapolis Saffron - ShopsHinjewadi33CompletedDec 2024Apr 2024
Megapolis Saffron -A3 to A9Hinjewadi380CompletedJun 2024May 2024
Megapolis Springs - AHinjewadi52CompletedMar 2024Oct 2023
Megapolis Springs - B and FHinjewadi156CompletedMar 2023Nov 2022
Megapolis Springs - CHinjewadi52CompletedMay 2022Sep 2021
Megapolis springs - D and EHinjewadi156CompletedApr 2022Sep 2021
Megapolis Symphony Phase IHinjewadi294CompletedJan 2022Sep 2020
Megapolis Mystic Phase IIHinjewadi214CompletedMar 2020Jun 2019
Megapolis Mystic - CHinjewadi86CompletedDec 2019Nov 2019
SangriaHinjewadi1,075CompletedOct 2015Feb 2015
SplendorHinjewadi1,176CompletedMar 2015Late, Nov 2015
SunwayHinjewadi1,176CompletedJul 2013Late, May 2014
SparkletHinjewadi1,184CompletedMar 2013Late, Apr 2013

How this compares with Pune

26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Megapolis Mystic Phase 2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Hinjewadi13,700+ in Pune

2 kmMegapolis Mystic Phase 2Completed 27Lapsed / revoked 10Other 17Dot size: filed unitsN

Filed coordinates, straight-line distance. 54 registered projects within 2 km.

Builder: Pegasus Properties Pvt. Ltd.

Pegasus Properties Pvt. Ltd. has 17 registrations on MahaRERA, including Megapolis Symphony Phase I and Megapolis Mystic Phase 2. Its filings disclose 13 earlier MahaRERA projects: declares 10 of 13 past projects completed on time. Litigation is declared on 4 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Megapolis Mystic Phase 2 is delayed beyond 1 Mar 2020?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Megapolis Mystic Phase 2?

The registered promoter entity is Pegasus Properties Pvt. Ltd., a company as per the filing. Its CIN U70102PN2007FTC129540 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Megapolis Mystic Phase 2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Megapolis Mystic Phase 2?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Megapolis Mystic Phase 2?

The professionals named in the filing: Architect: Ar Anil Madhusudan Kulkarni; Engineer: Narayan Hanmantgad; Chartered Accountant: Supriya Abhijit Mundada; Chartered Accountant: MSKA & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Megapolis Mystic Phase 2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Megapolis Mystic Phase 2. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Megapolis Mystic Phase 2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.