Pegasus Properties Pvt. Ltd.: RERA track record

CIN U70102PN2007FTC129540 · Company · attribution by exact filing name, entity resolution in progress

Pegasus Properties Pvt. Ltd. has 17 registrations on MahaRERA, including Megapolis Symphony Phase I and Megapolis Mystic Phase 2. Its filings disclose 13 earlier MahaRERA projects: declares 10 of 13 past projects completed on time. Litigation is declared on 4 of its registrations.

17RERA registrations
13Past projects disclosed
on timeMedian delivery slip
4Registrations with litigation
Follow this developer. An email when Pegasus Properties Pvt. Ltd. registers a new project on MahaRERA, and when the filings of their existing projects change: new sales, moved possession dates, extensions, complaints. Runs 12 months, no auto-renew. Follow · Rs 999 / 12 months

Projects by this developer

Showing all 17 projects.

Largest first, by the unit count in the filing.

ProjectLocationUnitsBookedRegisteredStatus
Megapolis Serenity A1 to A7, B1 and Conv shop AP52100023051Rajiv Gandhi Infotech Park Phase 3, Pune, 411057622100%22 Nov 2019Completed
Megapolis Shimmer - A1P52100052912Rajiv Gandhi Infotech Park Phase 3, Pune, 41105751196%5 Oct 2023Registered
Megapolis Mystic - GP52100047674Rajiv Gandhi Info Tech Park Phase 3, Pune, 41105712998%17 Nov 2022Registered
Megapolis Mystic - FP52100029121Rajiv Gandhi Infotech Park Phase 3, Pune, 41105712896%29 Apr 2021Completed
Megapolis Mystic - CP52100019959Rajiv Gandhi Infotech Park, Phase 3, Pune, 411057--15 Mar 2019Completed
Megapolis Mystic Phase 2P52100001391Hinjewadi, Pune, 411057--27 Jul 2017Completed
Megapolis Saffron - A10 to A14P52100021609Rajiv Gandhi Infotech Park Phase 3, Pune, 411057--15 Jul 2019Completed
Megapolis Saffron - A3 to A9P52100018779Rajiv Gandhi Infotech Park, Phase 3, Pune, 411057--4 Dec 2018Completed
Megapolis Saffron - ShopsP52100034988Rajiv Gandhi Infotech Park Phase 3, Pune, 411057--28 Apr 2022Completed
Megapolis Serenity A8 to A12, B2 and Conv shop BP52100022957Rajiv Gandhi Infotech Park Phase 3, Pune, 411057--6 Nov 2019Completed
Megapolis Springs - AP52100018284Rajiv Gandhi Infotech Park, Phase 3, Pune, 411057--22 Oct 2018Completed
Megapolis Springs - B and FP52100017386Rajiv Gandhi Infotech Park, Phase 3, Pune, 411057--9 Aug 2018Completed
Megapolis Springs - CP52100016848Rajiv Gandhi Infotech Park, Phase 3, Pune, 411057--20 Jun 2018Completed
Megapolis Springs - D and EP52100015188Rajiv Gandhi Infotech Park, Phase 3, Pune, 411057--7 Feb 2018Completed
Megapolis Symphony Phase IP52100000887Hinjawadi, Pune, 411057--23 Jul 2017Completed
WINDS OF JOY PROJECT AP52100053478Rajiv Gandhi InfoTech Park - Phase 3, Pune, 411057--6 Nov 2023De-registered
WINDS OF JOY PROJECT BP52100054608Rajiv Gandhi InfoTech Park - Phase 3, Pune, 411057--31 Jan 2024De-registered

What this promoter declares as its own experience

Pegasus Properties Pvt. Ltd. declares experience on 13 earlier projects. None of them carries a registration number we could match on MahaRERA, which is usual for work done before the register existed.

From the promoter experience table each promoter files with MahaRERA, matched to the register by registration number. A declaration naming another promoter's project is a claim of involvement, and involvement takes several shapes: a parent and its project company, one firm re-registering under a second name, or a joint venture between two separate developers. We publish the claim as filed and do not treat it as proof that the entities are one builder.

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
Sparklet
22 Mar 201330 Apr 2013+1 months
Sunway
25 Jul 20135 May 2014+9 months
Splendor
7 Mar 201510 Nov 2015+8 months
Sangria
9 Oct 201525 Feb 2015On time
Megapolis Mystic - C
31 Dec 201914 Nov 2019On time
Megapolis Mystic Phase II
1 Mar 202027 Jun 2019On time
Megapolis Symphony Phase I
31 Jan 202229 Sep 2020On time
Megapolis springs - D and E
27 Apr 20226 Sep 2021On time
Megapolis Springs - C
28 May 20226 Sep 2021On time
Megapolis Springs - B and F
30 Mar 202329 Nov 2022On time
Megapolis Springs - A
29 Mar 20246 Oct 2023On time
Megapolis Saffron -A3 to A9
30 Jun 202431 May 2024On time

Frequently asked questions

How do I verify Pegasus Properties Pvt. Ltd. as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. Cross-check its CIN U70102PN2007FTC129540 on the MCA and GST portals before signing anything. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with Pegasus Properties Pvt. Ltd.?

Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

Does the declared litigation make Pegasus Properties Pvt. Ltd. unsafe to buy from?

Not by itself. Litigation on a registration ranges from a boundary dispute to an allottee case about delay; what matters is the case type, which court or forum, and whether it touches the land title of the project you are buying. The case list is in each project's filed documents. Treat litigation as a question to resolve in writing before booking, not as a verdict either way.

Spotted a project attributed to the wrong developer, or something else wrong on this page? Projects are grouped by the promoter name as filed, so a firm that registers under two spellings can split across two pages. Tell us and we will check it against the filings.

Report an errorShare feedback

Data from official MahaRERA filings. How we handle corrections is on the about page.

Report an error or share feedback

About the Pegasus Properties Pvt. Ltd. developer page. Projects are grouped by the promoter name as filed, so a wrongly attributed project is the most useful thing to report.