Home / Browse projects / Mumbai Suburban, Maharashtra / Mayur Tower

Registered Litigation declared Residential / Group Housing project

Mayur Tower

By Geopreneur Spire Realty

RG-MH-26023 · RERA P51800011901 · Last updated on MahaRERA portal: 22 Aug 2025

Source: official MahaRERA filing

Red flags

  • Litigation declared, 4 cases
  • 10 complaints at MahaRERA
  • Completion date moved by 93 months
  • 3 extensions taken

Clear

  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 93 months from the original
12 of 22Construction stages doneacross 2 buildings; furthest along: Internal walls, 95%
75 of 127Units unsoldnot recorded sold or booked
10Complaints at MahaRERAon this registration
Jump to the 54 documents Report an error

Mayur Tower is a Residential / Group Housing project by Geopreneur Spire Realty in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800011901 on 31 Aug 2017. Possession is promised by 31 Dec 2026. The completion date has moved by 93 months from the original filing. 52 of the 127 units on this registration are recorded sold or booked, and 12 of 22 construction stages are filed complete. 10 complaints are on record with the regulator.

At a glance

Project

  • NameMayur Tower
  • TypeResidential / Group Housing
  • Location
    • Khernagar
    • Andheri
    • Mumbai Suburban
    • 400051
  • Pincode400051
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800011901
  • ReraGenie IDRG-MH-26023

Builder

  • NameGeopreneur Spire Realty
  • Entity typePartnership
  • PartnersSatish Baburao Patil, Arun Baburao Patil
  • Other registrations1 more →
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects2 →

Key dates

this monthRegisteredAug 2017First promiseMar 2019Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on31 Aug 2017
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 31 Mar 2019)
  • Buildings2 building records
  • Documents filed54 files

Current status

41%52 of 127 units booked
64.8%Work done, per cost certificate

Figures as on 22 Aug 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
MAYUR TOWER A WING REHABNA191559059
MAYUR TOWER B WING SALENA191768068

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 22 Aug 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

12 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Internal walls, at 95%.

MAYUR TOWER A WING REHAB87%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises95%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.75%
MAYUR TOWER B WING SALE87%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises95%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.75%

Progress on shared amenities15

As on 22 Aug 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes80%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes50%
Street LightingYes75%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes75%
Electrical meter room, sub-station, receiving stationYes90%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed2

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots2
Closed/Covered2
BuildingClosed/CoveredTotal
MAYUR TOWER A WING REHAB11
MAYUR TOWER B WING SALE11

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,834 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
Aditya EnterprisesAndheriMumbai Suburban

Approvals and building plan

Sanctioning authorityMHADA
Permissible FSI8221.0
Proposed, not sanctioned5,999 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMalad West
Estimated costRs 128.42 cr
Cost incurredRs 83.25 cr
Work done64.83%
BuildingWingEstimatedIncurred
MAYUR TOWER A WING REHABNARs 58.26 crRs 38.82 cr
MAYUR TOWER B WING SALENARs 58.26 crRs 38.82 cr
-NARs 11.90 crRs 5.62 cr

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectHARISH GANDHI
ArchitectELLORA PROJECTS CCONSULTANTS PVT LTD
EngineerRAMJI GUPTA
Chartered AccountantNalin R Panchal
PartnerRole in project
Geopreneur Spire Realty-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800001791Mar 2019 → Mar 2020

Reason as filed by the promoterwe have received Commencement Certificate from Municipal Corporation of Greater Mumbai on 31st December 2010 and further extended upto 12th floor part on 31st October 2014, thereafter further approval was stuck due to MCGM and MHADA internal problems. Vide a Notification of Urban Development Department, Govt. of Maharashtra u/no. TPB/4315/167/CR-51/2015/UD-II dated 23rd May 2018. Govt. of Maharashtra appointed MHADA as planning authority for MHADA layouts, respect of this notification MHADA issued further part CC upto 15th Floor to us on 04th July 2018, therefore, project delayed for more than

EXT51800011037Mar 2019 → Dec 2024

Reason as filed by the promoterVide a Notification of Urban Development Department, Govt. of Maharashtra u/no. TPB/4315/167/CR-51/2015/UD-II dated 23rd May, 2018. Govt. of Maharashtra appointed MHADA as planning authority for MHADA layouts, respect of this notification MHADA issued further part CC upto 15th Floor to us on 04th July 2018, therefore, project delayed for more than 3 years

EA16072502083Mar 2019 → Dec 2026

Reason as filed by the promoterDelay in Approvals from Govt. Authorities & MHADA

Litigation declared4

CaseCourtStatus
114 of 2016/2016Bombay High CourtThe matter is converted to Suit number Nine hundred Sixty Two of Two Thousand Fifteen
250 OF 2016/2016BOMBAY HIGH COURTThe matter is converted to Suit number Nine Hundred Eighty Four of Two Thousand Fifteen
962 of 2015/2015BOMBAY HIGH COURTDISPOSED
984 of 2015/2015BOMBAY HIGH COURTDISPOSED

Complaints filed with MahaRERA10

Case no.ComplainantRespondentFiled
CC006000000209756Joydeep MathiasGeoprenueur Spire Realty28/01/2022
CC006000000209987AnkurArun BagariaM/s Geopreneur Spire Realty11/02/2022
CC006000000210222Rahul Arun BagariaM/s Geopreneur Spire Realty02/03/2022
CC006000000396347Yashvi Dhiren PanchalGeopreneur Spire Realty20/06/2023
CC006000000054698SUNIL DEVNANIM/S ADITYA ENTERPRISES01/06/2018
CC006000000591541Tapan RayM/s Geopreneur Spire Realty14/08/2024
CC12503074Jayant MavlankarGeopreneur Spire Realty01/09/2025
CC12600264Samir ModyGeopreneur Spire Realty15/01/2026
CC12600272Vishal SharmaGeopreneur Spire Realty15/01/2026
CC12600273Margi Joy DesaiGeopreneur Spire Realty15/01/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 30 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 30 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 27 May 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed54

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Architect Certificate Mayur Phase I_HDG_27 July 2017.pdf22 Aug 2025
Withdrawal Update Form 2File: Engineers Certificate Mayur Phase I_VHG_28 July 2017.pdf22 Aug 2025
Withdrawal Update Form 3File: Registration Application Form3.pdf22 Aug 2025
Commencement Certificates / NA Order for plotted developmentFile: 008 A Mayur CC Dated 04th July 2018_15th Floor_NEW.pdf27 May 2024
Declaration about Commencement CertificateFile: 008 A Mayur CC Dated 04th July 2018_15th Floor_NEW.pdf27 May 2024
Details of encumbrances concerned to FinanceFile: Partnership Deed of Retirement Cum Admission_Mayur_13 March 2021_FINAL.pdf23 Jun 2023
Details of encumbrances concerned to LegalFile: Partnership Deed of Retirement Cum Admission_Mayur_13 March 2021_FINAL.pdf23 Jun 2023
Declaration about Commencement CertificateFile: Mayur Tower Declaration CC.pdf26 Apr 2022
Declaration about Commencement CertificateFile: MAYUR TOWER DECLARATION C C.pdf26 Apr 2022
Disclosure of sold/ booked inventoryFile: Mayur Tower Sold Unsold Unit.pdf26 Apr 2022
Status of Formation of Legal Entity (Society/Co Op etc.)File: Society Certificate.pdf25 Apr 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A 19-20.pdf24 Dec 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A 20-21.pdf24 Dec 2021
Certificates of CA (Form 3)File: Form 03 CA.pdf13 Dec 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 Signed 18-19 Mayur.pdf13 Dec 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 Signed 19-20- Mayur.pdf13 Dec 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 Signed Signed 20-21 Mayur.pdf13 Dec 2021
Certificates of CA (Form 5)File: CA Certificate Form 5_Mayur.pdf7 Jun 2019
Commencement Certificates / NA Order for plotted developmentFile: 008 A Mayur CC Dated 04th July 2018_15th Floor.pdf23 Jan 2019
Certificates of CA (Form 3)File: Mayur Phase I CA CERTIFICATE 01_DEC 2018.pdf23 Jan 2019
Certificates of CA (Form 3)File: Mayur Phase I CA CERTIFICATE 02_DEC 2018.pdf23 Jan 2019
Certificates of CA (Form 3)File: CA Certificate Mayur PH I_Sep 2018_01.pdf12 Nov 2018
Certificates of CA (Form 3)File: CA Certificate Mayur PH I_Sep 2018_02.pdf12 Nov 2018
Certificates of CA (Form 3)File: CA Certificate Mayur Phase I_30 June 2018.pdf30 Jul 2018
Certificates of CA (Form 3)File: CA Certificate 1 July 2017 to 30 Sep 2017.pdf24 Oct 2017
Certificates of CA (Form 5)File: CA Certificate Mayur Phase I.pdf31 Jul 2017
Proforma of Allotment letterFile: Mayur RERA Agreement Upload.pdf31 Jul 2017
OtherFile: Self Declaration Mayur Tower.pdf31 Jul 2017
Layout approvalFile: Plan_Mayur_BMC 06.pdf30 Jul 2017
Layout approvalFile: Plan_Mayur_BMC 07.pdf30 Jul 2017
Layout approvalFile: Plan_Mayur_BMC 05.pdf30 Jul 2017
Building plan approvalFile: IOD 06 Feb 2013.pdf30 Jul 2017
Building plan approvalFile: IOD Amended 09 Oct 2014.pdf30 Jul 2017
PAN CardFile: GEOPRENEUR SPIRE REALTY PAN 001.pdf30 Jul 2017
Copy of Layout Approval (in case of layout)File: Plan_Mayur_BMC 05.pdf30 Jul 2017
Copy of Layout Approval (in case of layout)File: Plan_Mayur_BMC 06.pdf30 Jul 2017
Copy of Layout Approval (in case of layout)File: Plan_Mayur_BMC 07.pdf30 Jul 2017
Building Plan Approval (IOD)File: IOD 06 Feb 2013.pdf30 Jul 2017
Building Plan Approval (IOD)File: IOD Amended 09 Oct 2014.pdf30 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT CERTIFICATE_31 OCT 2014.pdf30 Jul 2017
Certificates of CA (Form 3)File: CA Certificate Mayur Phase I_30 July 2017.pdf30 Jul 2017
Layout approvalFile: Plan_Mayur_BMC 04.pdf29 Jul 2017
Layout approvalFile: Plan_Mayur_BMC 01.pdf29 Jul 2017
Layout approvalFile: Plan_Mayur_BMC 03.pdf29 Jul 2017
Layout approvalFile: Plan_Mayur _BMC 02.pdf29 Jul 2017
Copy of the legal title reportFile: TITLE CERTIFICATE.pdf29 Jul 2017
Details of encumbrancesFile: Indenture of Mortgage Altico Captial India Pvt Ltd_09 May 2017_Index II.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: Plan_Mayur_BMC 01.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: Plan_Mayur _BMC 02.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: Plan_Mayur_BMC 03.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: Plan_Mayur_BMC 04.pdf29 Jul 2017
Declaration in FORM BFile: Affidavit cum Declaration_Mayur Phase I.pdf29 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Mayur Phase I_HDG_27 July 2017.pdf29 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate Mayur Phase I_VHG_28 July 2017.pdf29 Jul 2017

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 not delivered by the promised date
ProjectLocationRegisteredStatusPromisedDelivered
EKTA APARTMENT UPTO 17TH FLOORP51800009361Rajendra Nagar, Mumbai SuburbanAug 2017Certificate SignedFeb 2026Registered original: Mar 2019Not delivered
Tagore Nagar Anjali CHS Ltdp51800013097Plot No 33 CTS No 348 PT, , , , Kurla, Mumbai Suburban, 400083, MAHARASHTRA-Certificate SignedDec 2024Not delivered

How this compares with Mumbai Suburban

41%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 93 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Mayur Tower on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Khernagar6,700+ in Mumbai Suburban

2 kmMayur TowerCompleted 89Lapsed / revoked 45Other 98Dot size: filed unitsN

Filed coordinates, straight-line distance. 232 registered projects within 2 km.

Builder: Geopreneur Spire Realty

Geopreneur Spire Realty has 2 registrations on MahaRERA, including Mayur Tower and MAYUR PHASE II 16TH TO 19TH FLOOR. Its filings disclose 2 earlier MahaRERA projects, none completed yet. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if Mayur Tower is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Mayur Tower?

The registered promoter entity is Geopreneur Spire Realty, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Mayur Tower?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Mayur Tower?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Mayur Tower?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Mayur Tower?

The professionals named in the filing: Architect: HARISH GANDHI; Architect: ELLORA PROJECTS CCONSULTANTS PVT LTD; Engineer: RAMJI GUPTA; Chartered Accountant: Nalin R Panchal. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Mayur Tower?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Mayur Tower. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Mayur Tower to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.