Registration lapsed No litigation declared Others project

MAVERICK MOOLDEEP

By MAVERICK REALTORS

RG-MH-24072 · RERA P51800003963 · Last updated on MahaRERA portal: 4 Jul 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 4 months past the filed date
  • 2 complaints at MahaRERA
  • Completion date moved by 42 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Jun 2026Possession promised4 months past this date
8 of 11Construction stages donefurthest along: External plumbing and external plaster, 99%
49 of 63Units unsoldnot recorded sold or booked
2Complaints at MahaRERAon this registration
Jump to the 111 documents Report an error

MAVERICK MOOLDEEP is a Others project by MAVERICK REALTORS in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800003963 on 7 Aug 2017. Possession was promised by 30 Jun 2026 and is now 4 months past that date. The completion date has moved by 42 months from the original filing. 14 of the 63 units on this registration are recorded sold or booked, and 8 of 11 construction stages are filed complete. 2 complaints are on record with the regulator.

At a glance

Project

  • NameMAVERICK MOOLDEEP
  • TypeOthers
  • Location
    • Mulund West
    • Mumbai
    • Kurla
    • Mumbai Suburban
    • 400080
  • Pincode400080
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800003963
  • ReraGenie IDRG-MH-24072

Builder

  • NameMAVERICK REALTORS
  • Entity typePartnership
  • PartnersHarsh Paresh Shah, Paresh Kantilal Shah, Tushar Babulal Kuvadia
  • Other registrations8 more →
  • Completed2 of 9
  • No longer live3 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

4 months past promisethis monthRegisteredAug 2017First promiseDec 2022Revised toJun 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on7 Aug 2017
  • Promised completion30 Jun 2026
  • Revised completionRevised to 30 Jun 2026 (originally 30 Dec 2022)
  • Buildings1 building record
  • Documents filed111 files

Current status

22%14 of 63 units booked

Figures as on 4 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
MooldeepNA1717521163

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 4 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 11 construction stages are filed complete. The stage furthest along is External plumbing and external plaster, at 99%.

Mooldeep: 90% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.99%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%

Progress on shared amenities15

As on 4 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes50%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes85%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes50%
Open ParkingYes50%

Parking filed77

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots77
Closed/Covered77

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,287 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
Declared on19 Jun 2026
LandownerVillageDistrict
MOOLDEEP CO-OPERATIVE HOUSING SOCIETY LIMITEDKurlaMumbai Suburban

Approvals and building plan

Sanctioning authoritySlum Rehabilitation Authority
Permissible FSI5201.0
Proposed, not sanctioned4,369 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMulund East, Mumbai - 400080

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectV S VAIDYA & ASSOCIATES Mr Rajesh Khadeparkar LS
ArchitectTrisha chaplot Proprietor (Werachayati.Co)
EngineerAssociated StructuralConsultants LLP
EngineerKunwarji Ratnani
Chartered AccountantS K RAMBHIA & ASSOCIATES
Chartered AccountantSachin Sunil And Associates
PartnerRole in project
MAVERICK REALTORS-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800012291Dec 2022 → Dec 2023

Reason as filed by the promoterIt’s a redevelopment project with change of Developer from Siroya Developers Pvt Ltd (Old Developer) to us (Maverick Realtors) by Mooldeep CHS Ltd (The Society) the said approved by Rera authority as on 11.09.2019, further on account of restrictions imposed on Construction activities and Real Estate sector due to Covid 19 since Mar’ 2020 & thereafter due to low demand & overall slowdown in economy, in Real Estate Sector there is a delay in completion of Project. And due to the same it is expected that Project would get completed by Aug’ 2023 and Occupancy Certificate shall be obtained on or bef

EXT51800018274Dec 2022 → Jun 2025

Reason as filed by the promoterIt’s a redevelopment project with change of Developer from Siroya Developers Pvt Ltd (Old Developer) to us (Maverick Realtors) by Mooldeep CHS Ltd (The Society) the said approved by Rera authority as on 11.09.2019, further on account of restrictions imposed on Construction activities and Real Estate sector due to Covid 19 since Mar’ 2020 & thereafter due to low demand & overall slowdown in economy, in Real Estate Sector there is a delay in completion of Project. And due to the same it is expected that Project would get completed by Feb’ 2025 and Occupancy Certificate shall be obtained on or bef

EA04062501442Dec 2022 → Jun 2026

Reason as filed by the promoterIt is a re-development project , where we took over the project from Siroya Developers. Many structural changes had to carried out and rectification of faulty structure also had to be repaired. This changes and repair work was never anticipated. The lift shaft had to completely re-worked and the same is going on. In view of the above unforeseen rectification the execution got delayed. So, request you kindly grant Extension upto 30-06-2026.

Complaints filed with MahaRERA2

Case no.ComplainantRespondentFiled
CC006000000079206BHARAT VITHALDAS THAKKARSIROYA DEVELOPERS PVT. LTD.10/05/2019
CC006000000110885BHARAT V. THAKKARSIROYA DEVELOPERS PVT LTD12/09/2019

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 26 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 26 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 26 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 18 Nov 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed111

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 111 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: MooldeepFrom1Dt31122023.pdf4 Jul 2026
Form 2File: Mooldeeep Form 2 31122023.pdf4 Jul 2026
Form 3File: Mooldeeep Form 3 31122023.pdf4 Jul 2026
Disclosure of Sold and Booked InventoryFile: Mooldeep Sold Unsold Inventory Dec2023.pdf4 Jul 2026
Form 1File: MooldeepDt10102023.pdf4 Jul 2026
Form 2File: Mooldeeep Form 2 30092023.pdf4 Jul 2026
Form 3File: Mooldeeep Form 3 30092023.pdf4 Jul 2026
Disclosure of Sold and Booked InventoryFile: Mooldeep Sold Unsold Inventory Sep2023.pdf4 Jul 2026
Form 1File: Mooldeep Form 1 31032024.pdf3 Jul 2026
Form 2File: Mooldeep Form 2 31032024.pdf3 Jul 2026
Form 3File: Mooldeep Form3 31032024.pdf3 Jul 2026
Disclosure of Sold and Booked InventoryFile: Mooldeep Sold Unsold Inventory mar24.pdf3 Jul 2026
Form 1File: J5152 C04 LS Cert for Mooldeep Dt 200723.pdf3 Jul 2026
Form 2File: Form 2 Mooldeep 30062023.pdf3 Jul 2026
Form 3File: Form 3 Mooldeep 30062023.pdf3 Jul 2026
Disclosure of Sold and Booked InventoryFile: Mooldeep Sold Unsold Inventory June2023.pdf3 Jul 2026
Form 1File: Mooldeep form1 31032025.pdf30 Jun 2026
Form 2File: Mooldeep Form 2 31032025.pdf30 Jun 2026
Form 3File: Form 3 Maverick Mooldeep -March 25.pdf30 Jun 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Mooldeep 31032025.pdf30 Jun 2026
Form 1File: Mooldeep Form 1 - Jun' 24.pdf30 Jun 2025
Form 2File: Form 2 Mooldeep 30062024.pdf30 Jun 2025
Form 3File: Form 3 Mooldeep 30062024 R.pdf30 Jun 2025
Disclosure of Sold and Booked InventoryFile: Disclosure Sold Booked Inventory 30062024.pdf30 Jun 2025
Form 1File: Mooldeep Form 1 - Sep' 24.pdf30 Jun 2025
Form 2File: Form 2 Mooldeep 30092024.pdf30 Jun 2025
Form 3File: Form 3 Mooldeep 30092024 R.pdf30 Jun 2025
Disclosure of Sold and Booked InventoryFile: Disclosure Sold Booked Inventory 30092024.pdf30 Jun 2025
Form 1File: Mooldeep Form 1 - Dec' 24.pdf26 Jun 2025
Form 2File: Form 2 Mooldeep 31122024.pdf26 Jun 2025
Form 3File: Form 3 Mooldeep 31122024 R.pdf26 Jun 2025
Disclosure of Sold and Booked InventoryFile: MR Mooldeep Declaration Of Sold.pdf26 Jun 2025
Form 2A (FY 2024-2025)File: Form 2A Mooldeep.pdf25 Jun 2025
Certificates of CA (Form 3)File: MooldeeepForm330092023.pdf17 Feb 2025
Certificates of CA (Form 3)File: MooldeeepForm331122023COMPS.pdf17 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: MooldeeepForm230092023Comps.pdf17 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: MooldeeepForm231122023comps.pdf17 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form2MooldeepDonewithbothSignaturecompressed.pdf17 Feb 2025
Certificates of CA (Form 3)File: Mooldeep Form331032024.pdf15 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Mooldeep Form231032024compressed.pdf15 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: RERA Form-5_FY23-24_Mooldeep (2).pdf15 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: MooldeepDt10102023.pdf7 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: MooldeepFrom1Dt31122023.pdf7 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: MooldeepDt05042024C.pdf7 Feb 2025
CERSAI detailsFile: Undertaking Cersai.pdf29 Jan 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosre of Interest - Paresh Kantilal Shah.pdf22 Jan 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosre of Interest - Harsh Paresh Shah.pdf22 Jan 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosre of Interest - Tushar Babulal Kuvadia.pdf22 Jan 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Separate Bank Account Details (Maverick Mooldeep).pdf22 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A (F Y 2019-20) Mooldeep.pdf18 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A (F Y 2020-21) Mooldeep.pdf18 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A (F Y 2021-22) Mooldeep.pdf18 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 5 - Mooldeep - 31032020.pdf18 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5 - Mooldeep - 31032021.pdf18 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5 - Mooldeep - 31032022.pdf18 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Mooldeep 30062023.pdf12 Jan 2024
Certificates of CA (Form 3)File: Form 3 Mooldeep 30062023.pdf12 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Mooldeep.pdf10 Jan 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: J5152 C03 LS Cert Mooldeep Dt 150523.pdf2 Jan 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: J5152 C04 LS Cert for Mooldeep Dt 200723.pdf2 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A Mooldeep Mar' 23.pdf2 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: RERA Form-5_FY22-23_Mooldeep.pdf2 Jan 2024
Declaration in FORM BFile: From B -Mooldeep.pdf20 Dec 2023
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Unsold Unit - Mooldeep.pdf20 Dec 2023
Certificates of CA (Form 3)File: Mooldeep Form3 310323.pdf10 May 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Mooldeep 30092022.pdf19 Apr 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM -1 Mar-20.pdf7 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FOMR -1 Mar-21.pdf7 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM-1 Mar-22.pdf7 Feb 2023
Certificates of CA (Form 3)File: FORM-3 Mar-21.pdf7 Feb 2023
Certificates of CA (Form 3)File: FORM-3 Mar-22.pdf7 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 2020 (1).pdf6 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 2021 (1).pdf6 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 2022 (1).pdf6 Feb 2023
Certificates of CA (Form 3)File: FORM-3 Mar-20.pdf6 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Mooldeep FORM 1 2020.pdf18 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Mooldeep form 1 2021.pdf18 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Mooldeep Form 1 2022.pdf18 Jan 2023
Certificates of CA (Form 3)File: Mooldeep Form 3 - 31 March 2020.pdf18 Jan 2023
Certificates of CA (Form 3)File: Mooldeep Form 3 - 31 March 2021.pdf18 Jan 2023

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
OM SAKTHIVALJI LADDHA ROAD MULUND WEST MUMBAI-40008031CompletedNov 2015Late, Dec 2019

How this compares with Mumbai Suburban

22%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 42 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep MAVERICK MOOLDEEP on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Mumbai6,700+ in Mumbai Suburban

2 kmMAVERICK MOOLDEEPCompleted 125Lapsed / revoked 96Other 153Dot size: filed unitsN

Filed coordinates, straight-line distance. 374 registered projects within 2 km.

Builder: MAVERICK REALTORS

MAVERICK REALTORS has 9 registrations on MahaRERA, including NEELKANTH TIRTH CO. OP. HOUSING SOC. LTD. and MAVERICK MOOLDEEP. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that MAVERICK MOOLDEEP shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if MAVERICK MOOLDEEP is delayed beyond 30 Jun 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of MAVERICK MOOLDEEP?

The registered promoter entity is MAVERICK REALTORS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in MAVERICK MOOLDEEP?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against MAVERICK MOOLDEEP?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for MAVERICK MOOLDEEP?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at MAVERICK MOOLDEEP?

The professionals named in the filing: Architect: V S VAIDYA & ASSOCIATES Mr Rajesh Khadeparkar LS; Architect: Trisha chaplot Proprietor (Werachayati.Co); Engineer: Associated StructuralConsultants LLP; Engineer: Kunwarji Ratnani; Chartered Accountant: S K RAMBHIA & ASSOCIATES; Chartered Accountant: Sachin Sunil And Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MAVERICK MOOLDEEP?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MAVERICK MOOLDEEP. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MAVERICK MOOLDEEP to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.