Home / Browse projects / Matrix Alfa 1

Registration lapsed No litigation declared Residential / Group Housing project

Matrix Alfa 1

By MATRIX INFRA

RG-MH-12942 · RERA P52100029984 · Last updated on MahaRERA portal: 25 Feb 2022

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 7 months past the filed date
  • Completion date moved by 51 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: .
Mar 2026Possession promised7 months past this date
8 of 11Construction stages donefurthest along: Internal walls, 50%
0Complaints at MahaRERAon this registration
Jump to the 20 documents Report an error

Matrix Alfa 1 is a Residential / Group Housing project by MATRIX INFRA in Rajjaram Patil Nagar, 411015, registered with MahaRERA as P52100029984 on 20 Jul 2021. Possession was promised by 31 Mar 2026 and is now 7 months past that date. The completion date has moved by 51 months from the original filing.

At a glance

Project

  • NameMatrix Alfa 1
  • TypeResidential / Group Housing
  • Location
    • Lane no 9
    • Rajjaram Patil Nagar
    • 411015
  • Pincode411015
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100029984
  • ReraGenie IDRG-MH-12942

Builder

  • NameMATRIX INFRA
  • Entity typePartnership
  • PartnersRishikesh Namdeo Gadilkar, Kedar Namdeo Gadilkar, Madhukar Bhausaheb Shinde
  • Other registrations1 more →
  • Completed1 of 2
  • No longer live1 lapsed, de-registered or revoked

Key dates

7 months past promisethis monthRegisteredJul 2021First promiseDec 2021Revised toMar 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on20 Jul 2021
  • Promised completion31 Mar 2026
  • Revised completionRevised to 31 Mar 2026 (originally 31 Dec 2021)
  • Buildings1 building record
  • Documents filed20 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
1NA70000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 25 Feb 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 50%.

1: 82% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%

Progress on shared amenities16

As on 25 Feb 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%
LIFT INSTALLATIONYes50%

Parking filed24

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots24
Open Space24

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,662 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI517.42
Proposed, not sanctioned517 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGround Floor Krishna Kaveri, Nagar Shirdi Road, Near Zopdi Canteen, Savedi Ahmednagar PIN 414003

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVarsha Vastunirmiti
EngineerVarsha Vastunirmiti
Chartered AccountantJoshi Raikar Associates
Chartered AccountantCA CHETAN MAHORE
PartnerRole in project
MATRIX INFRA-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100015112Dec 2021 → Mar 2026

Reason as filed by the promoterBuilding is completed. Occupancy certificate is yet to be received.

EXT52100011137Dec 2021 → Jul 2022

Reason as filed by the promoterDue to some unavoidable reason i.e. labour, electricity and life installation etc. , we want extension of completion to our project till July 31th 2022.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 15 Jul 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Jun 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 8 Jun 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 4 Jul 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed20

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)_compressed.pdf25 Feb 2022
CERSAI detailsFile: CERSAI Details.pdf25 Feb 2022
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Unsold.pdf25 Feb 2022
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Unsold.pdf25 Feb 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate.pdf25 Feb 2022
Copy of the legal title reportFile: Legal Title report Matrix Infra_Advocate-Com.pdf15 Jul 2021
Details of encumbrancesFile: encumbrances_compressed.pdf15 Jul 2021
Declaration about Commencement CertificateFile: DECLARATION ABOUT COMMENCEMNT CERTIFICATE.pdf1 Jul 2021
Layout approvalFile: Location Plan.pdf29 Jun 2021
PAN CardFile: Matrix Infra PAN.PDF29 Jun 2021
Copy of the legal title reportFile: TITLE REPORT ALFA 1.pdf29 Jun 2021
Copy of Layout Approval (in case of layout)File: Location Plan.pdf29 Jun 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3Certificate.pdf29 Jun 2021
Proforma of Allotment letterFile: ALLOTMENT LETTER draft.pdf10 Jun 2021
Proforma of Allotment letterFile: Agreement to sale draft.pdf10 Jun 2021
Building plan approvalFile: Location Plan.pdf8 Jun 2021
Building Plan Approval / NA Order for plotted developmentFile: Location Plan.pdf8 Jun 2021
Declaration in FORM BFile: Form B Declaration.pdf8 Jun 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FOR 1 ARCH CERT.pdf8 Jun 2021
Commencement Certificates / NA Order for plotted developmentFile: 20190128053506.pdf4 Jul 2019

Keep Matrix Alfa 1 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Rajjaram Patil Nagar

Builder: MATRIX INFRA

MATRIX INFRA has 2 registrations on MahaRERA, including Matrix Alfa 1 and MATRIX HOMES. Its filings disclose no earlier MahaRERA projects. Read the full track record.

Frequently asked questions

What does it mean that Matrix Alfa 1 shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Matrix Alfa 1 is delayed beyond 31 Mar 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Matrix Alfa 1?

The registered promoter entity is MATRIX INFRA, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Matrix Alfa 1?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Matrix Alfa 1?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Matrix Alfa 1?

The professionals named in the filing: Architect: Varsha Vastunirmiti; Engineer: Varsha Vastunirmiti; Chartered Accountant: Joshi Raikar Associates; Chartered Accountant: CA CHETAN MAHORE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Matrix Alfa 1?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Matrix Alfa 1. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Matrix Alfa 1 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.