Registration lapsed Litigation declared Residential / Group Housing project

MARUTI PALATIAL

By GRS SHELTERS PRIVATE LIMITED

RG-MH-34093 · RERA P51900008828 · Last updated on MahaRERA portal: 24 Sep 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 22 months past the filed date
  • Litigation declared, 5 cases
  • 1 complaint at MahaRERA
  • Completion date moved by 12 months
  • 2 extensions taken

Clear

  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

6 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: .
Dec 2024Possession promised22 months past this date
27 of 33Construction stages doneacross 3 buildings; furthest along: Staircases, 99%
6 of 60Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 96 documents Report an error

MARUTI PALATIAL is a Residential / Group Housing project by GRS SHELTERS PRIVATE LIMITED in Parel, 400012, registered with MahaRERA as P51900008828 on 19 Aug 2017. Possession was promised by 29 Dec 2024 and is now 22 months past that date. The completion date has moved by 12 months from the original filing. 54 of the 60 units on this registration are recorded sold or booked, and 27 of 33 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameMARUTI PALATIAL
  • TypeResidential / Group Housing
  • Location
    • E. Borges Marg
    • Parel
    • 400012
  • Pincode400012
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51900008828
  • ReraGenie IDRG-MH-34093

Builder

  • NameGRS SHELTERS PRIVATE LIMITED
  • Entity typeCompany
  • CINU45400MH2008PTC178309
  • GSTIN27AADCG0802A1ZF
  • Managing DirectorDHANANJAY GOPAL SINGH
  • ChairpersonGOPAL RAMPRITSINGH THAKUR
  • Declared earlier projects2 →

Key dates

22 months past promisethis monthRegisteredAug 2017First promiseDec 2023Revised toDec 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on19 Aug 2017
  • Promised completion29 Dec 2024
  • Revised completionRevised to 29 Dec 2024 (originally 30 Dec 2023)
  • Buildings3 building records
  • Documents filed96 files

Current status

90%54 of 60 units booked

Figures as on 24 Sep 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A WINGNA282246248
B WING REHABNA20206612
C WINGNA70000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 24 Sep 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

27 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Staircases, at 99%.

A WING90%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks99%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.91%
B WING REHAB91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
C WING82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 24 Sep 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes50%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes40%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,779 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
Declared on24 Sep 2025

Approvals and building plan

Sanctioning authorityMCGM
Permissible FSI13816.84
Proposed, not sanctioned5,951 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHOP NO.1, THAWAR APARTMENT, KASTURBA ROAD, BORIVALI (E), MUMBAI 400 066.

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPOOJA SAKHARAM SALGAONKAR
EngineerRakesh Singh
Chartered AccountantNEETA PREMNATH SHETTY
Chartered AccountantHSP AND ASSOCIATES
PartnerRole in project
GRS SHELTERS PRIVATE LIMITED-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51900018100Dec 2023 → Jun 2024

Reason as filed by the promoterAS DUE TO MONSOON OUR OUTER PLASTER AND EXTERNAL PAINTING WORK GOT DELAYED.ALSO PASSENGER LIFT ORDERED ON NOVEMBER 2022 GOT DELIVERED ON AUG 2023 AND SIMILAR IS WITH CAR LIFT AS WE RECEIVED ONLY 1 CAR LIFT AS OF NOW.

EXT51900024257Dec 2023 → Dec 2024

Reason as filed by the promoter1.Our passenger lift delivery from Kone Elevator got delayed by 2 months and further its installation got delayed due to low manforce and Audit issue of Kone Elevator hence currently out of 2 passenger lift only 1 is installed and second one is still pending.Kindly grant us 6months extension for obtaining OC.

Litigation declared5

CaseCourtStatus
160/2006BOMBAY HIGH COURTDISMISSAL
2502/2009BOMBAY HEIGHT COURTWITHDRAWN SUIT
1137/2010BOMBAY HIGH COURTREJECTED BY DIVISION BENCH
2010/2010SUPREME COURTDISMISSAL BY SUPREM COUR
659/2011BOMBAY HIGH COURTSETTLED

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC006000000000484MCGM DELAYESTATE DEPARTMENT08/09/2017

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 30 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 16 Nov 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 16 Nov 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed96

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 96 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: Form 1-Architect Certificate.pdf24 Sep 2025
Form 2File: Form 2-Engineer Certificate.pdf24 Sep 2025
Form 3File: FORM 3 Grs Shelters Pvt Ltd.pdf24 Sep 2025
Disclosure of Sold and Booked InventoryFile: inventory list on letterhead grs.pdf24 Sep 2025
Form 1File: Form 1-Architect Certificate.pdf24 Sep 2025
Form 2File: Form 2-Engineer Certificate-.pdf24 Sep 2025
Form 3File: Form-3 CA Certificate.pdf24 Sep 2025
Disclosure of Sold and Booked InventoryFile: inventory list on letterhead grs.pdf24 Sep 2025
Architect’s Certificate on Completion of Project (Form 4)File: EPSON007.PDF23 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2-Engineer Certificate.pdf19 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1-Architect Certificate.pdf19 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1-Architect Certificate.pdf19 Nov 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2-Engineer Certificate.pdf19 Nov 2024
Building plan approvalFile: IOD Amended Letter-Latest-Grs Shelter.pdf16 Nov 2024
Building plan approvalFile: IOD PLAN-GRS LATEST_11zon.pdf16 Nov 2024
Building plan approvalFile: IOD Amended Letter-Latest-Grs Shelter.pdf16 Nov 2024
Building plan approvalFile: IOD PLAN-GRS LATEST_11zon.pdf16 Nov 2024
Certificates of CA (Form 3)File: FORM 3 Grs Shelters Pvt Ltd.pdf16 Nov 2024
Building Plan Approval (IOD)File: IOD Amended Letter-Latest-Grs Shelter.pdf16 Nov 2024
Building Plan Approval (IOD)File: IOD PLAN-GRS LATEST_11zon.pdf16 Nov 2024
Commencement Certificates / NA Order for plotted developmentFile: Further CC-Latest-Grs Shelters.pdf16 Nov 2024
Certificates of CA (Form 3)File: FORM 3 Grs Shelters Pvt Ltd.pdf16 Nov 2024
Commencement Certificates / NA Order for plotted developmentFile: Further CC-Latest-Grs Shelters.pdf16 Nov 2024
Building Plan Approval (IOD)File: IOD Amended Letter-Latest-Grs Shelter.pdf16 Nov 2024
Building Plan Approval (IOD)File: IOD PLAN-GRS LATEST_11zon.pdf16 Nov 2024
Declaration in FORM BFile: affidavit cum declaration -rera extension grs.pdf18 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: form 5-Grs.pdf18 Oct 2024
Declaration about Commencement CertificateFile: affidavit cum declaration -rera extension grs.pdf16 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5-GRS-FY 23-24.pdf16 Oct 2024
Certificates of CA (Form 5)File: FORM 5-GRS.pdf17 Jul 2024
Declaration about Commencement CertificateFile: Format D-Declaration of CC Grs.pdf12 Jul 2024
Disclosure of sold/ booked inventoryFile: inventory list on letterhead grs.pdf12 Jul 2024
Other - TechnicalFile: affidavit cum declaration -rera extension grs.pdf12 Jul 2024
Other - TechnicalFile: Format D-Declaration of CC Grs.pdf12 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE FOR GRS_compressed.pdf4 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE GRS.pdf4 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 ENGINEER CERTIFICATE.pdf4 Jul 2024
Certificates of CA (Form 3)File: FORM 3 Grs Shelters Pvt Ltd.pdf4 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form-2A.pdf22 Jun 2024
Certificates of CA (Form 3)File: FORM 3 Grs Shelters Pvt Ltd-REVISED.pdf22 Jun 2024
Other - TechnicalFile: Form 2A.pdf22 Jun 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 ENGINEER CERTIFICATE.pdf11 May 2024
Certificates of CA (Form 3)File: FORM 3 Grs Shelters Pvt Ltd.pdf29 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate-Grs.pdf26 Mar 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER'S Certificate.pdf23 Feb 2024
Certificates of CA (Form 3)File: form 3 grs shelters (2).pdf22 Feb 2024
Certificates of CA (Form 5)File: form 5-Grs.pdf5 Dec 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Rera Architect Letter-Grs Shelter.pdf4 Dec 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2-ENGINEER CERTIFICATE-GRS.pdf1 Dec 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Rakesh Singh- ENGINEER CERTIFICATE-GRS.pdf1 Dec 2023
Disclosure of sold/ booked inventoryFile: Inventory Booked details-Grs.pdf29 Nov 2023
Certificates of CA (Form 3)File: FORM 3 GRS SHELTERS.pdf28 Nov 2023
Other - LegalFile: grs declartion.pdf9 Mar 2023
Other - FinanceFile: grs declartion.pdf9 Mar 2023
Building plan approvalFile: B1-1-2318 Amended Letter_signed.pdf8 Mar 2023
Building Plan Approval (IOD)File: B1-1-2318 Amended Letter_signed.pdf8 Mar 2023
Commencement Certificates / NA Order for plotted developmentFile: B2-Further CC-Grs till 22nd floor of A Wing.pdf8 Mar 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT RERA CERTIFICATE WING A 05 11 22.pdf8 Mar 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT RERA CERTIFICATE WING C 05 11 22.pdf8 Mar 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT RERA CERTIFICATE WING D 05 11 22.pdf8 Mar 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf8 Mar 2023
Certificates of CA (Form 3)File: Form 3-CA-grs shelters rera update-5th update_compressed.pdf8 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5-18-19.pdf8 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 5 19-20.pdf8 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5 20-21.pdf8 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5-21-22.pdf8 Mar 2023
Certificates of CA (Form 5)File: GRS FORM 5.pdf15 Oct 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf18 Sep 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Scan0168 (1).pdf18 Sep 2018
Certificates of CA (Form 3)File: FORM 3-CERTIFICATE-REVISED.pdf18 Sep 2018
Layout approvalFile: PAGE 1.pdf30 Jul 2017
Building plan approvalFile: IOD.pdf30 Jul 2017
Building plan approvalFile: PAGE 1.pdf30 Jul 2017
Building plan approvalFile: PAGE NO 2.pdf30 Jul 2017
Building plan approvalFile: PAGE 3.pdf30 Jul 2017
Building plan approvalFile: PAGE 4.pdf30 Jul 2017
Building plan approvalFile: PAGE 5.pdf30 Jul 2017
Building plan approvalFile: PAGE 6.pdf30 Jul 2017
PAN CardFile: PAN CARD.pdf30 Jul 2017
Copy of the legal title reportFile: Title certificate.pdf30 Jul 2017

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise1 delivered late
ProjectLocationFlatsRegisteredStatusPromisedDelivered
SIDDHI VINAYAK GRANDEURP51900013137SAYANI ROAD PRABHADEVI50Sep 2017CompletedOct 2023Registered original: Dec 2022Aug 2023
GBD UJWALA KUTIRP51900026722borivali east, Mumbai City34Oct 2020CompletedAug 2023Late, Apr 2024

Keep MARUTI PALATIAL on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Parel

2 kmMARUTI PALATIALCompleted 28Lapsed / revoked 11Other 18Dot size: filed unitsN

Filed coordinates, straight-line distance. 57 registered projects within 2 km.

Builder: GRS SHELTERS PRIVATE LIMITED

GRS SHELTERS PRIVATE LIMITED has 1 registration on MahaRERA, including MARUTI PALATIAL. Its filings disclose 2 earlier MahaRERA projects: declares 1 of 2 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record.

Frequently asked questions

What does it mean that MARUTI PALATIAL shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if MARUTI PALATIAL is delayed beyond 29 Dec 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of MARUTI PALATIAL?

The registered promoter entity is GRS SHELTERS PRIVATE LIMITED, a company as per the filing. Its CIN U45400MH2008PTC178309 and GSTIN 27AADCG0802A1ZF can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in MARUTI PALATIAL?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against MARUTI PALATIAL?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for MARUTI PALATIAL?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at MARUTI PALATIAL?

The professionals named in the filing: Architect: POOJA SAKHARAM SALGAONKAR; Engineer: Rakesh Singh; Chartered Accountant: NEETA PREMNATH SHETTY; Chartered Accountant: HSP AND ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MARUTI PALATIAL?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MARUTI PALATIAL. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MARUTI PALATIAL to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.