ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai Suburban, Maharashtra / MARIGOLD MIRAAYA

Registration lapsed No litigation declared Residential / Group Housing project

MARIGOLD MIRAAYA

By MARIGOLD REALTY

RG-MH-08989 · RERA P51800003669 · Last updated on MahaRERA portal: 10 Mar 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 16 months past the filed date
  • Completion date moved by 6 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Jun 2025Possession promised16 months past this date
12 of 22Construction stages doneacross 2 buildings; furthest along: Internal walls, 60%
89 of 133Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 79 documents Report an error

MARIGOLD MIRAAYA is a Residential / Group Housing project by MARIGOLD REALTY in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800003669 on 6 Aug 2017. Possession was promised by 30 Jun 2025 and is now 16 months past that date. The completion date has moved by 6 months from the original filing. 44 of the 133 units on this registration are recorded sold or booked, and 12 of 22 construction stages are filed complete.

At a glance

Project

  • NameMARIGOLD MIRAAYA
  • TypeResidential / Group Housing
  • Location
    • OFF P.K.ROAD
    • MULUND WEST
    • Kurla
    • Mumbai Suburban
    • 400080
  • Pincode400080
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800003669
  • ReraGenie IDRG-MH-08989

Builder

  • NameMARIGOLD REALTY
  • Entity typePartnership
  • PartnerPRANAY SURESH JOGANI

Key dates

16 months past promisethis monthRegisteredAug 2017First promiseDec 2024Revised toJun 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on6 Aug 2017
  • Promised completion30 Jun 2025
  • Revised completionRevised to 30 Jun 2025 (originally 30 Dec 2024)
  • Buildings2 building records
  • Documents filed79 files

Current status

33%44 of 133 units booked
712.7%Work done, per cost certificate

Figures as on 10 Mar 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
MARIGOLD MIRAAYA - A WINGNA251957057
MARIGOLD MIRAAYA - B WINGNA251976076

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 10 Mar 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

12 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Internal walls, at 60%.

MARIGOLD MIRAAYA - A WING67%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks47%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.35%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
MARIGOLD MIRAAYA - B WING67%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks47%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.35%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 10 Mar 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes50%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes50%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed186

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots186
Closed/Covered179
Open Space7
BuildingClosed/CoveredOpen SpaceTotal
MARIGOLD MIRAAYA - A WING86086
MARIGOLD MIRAAYA - B WING937100

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area4,190 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on30 Jul 2025

Approvals and building plan

Sanctioning authorityMUNICIPAL CORPORATION OF GREATER MUMBAI
Permissible FSI11313.54
Proposed, not sanctioned3,379 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHOP NO 889, HALLMARK BLOCK, LBS MARG BRANCH, MULUND WEST, MUMBAI - 400080
Estimated costRs 60.00 cr
Cost incurredRs 427.62 cr
Work done712.7%
BuildingWingEstimatedIncurred
MARIGOLD MIRAAYA - A WINGNARs 27.50 crRs 213.81 cr
MARIGOLD MIRAAYA - B WINGNARs 27.50 crRs 213.81 cr
-NARs 5.00 cr-

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectARCHITECT HAFEEZ CONTRACTOR
EngineerRAJU NAREJA
Chartered AccountantNITIN MARU AND ASSOCIATES
Chartered AccountantESHA BHANUSHALI AND COMPANY
PartnerRole in project
MARIGOLD REALTY-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800025697Dec 2024 → Jun 2025

Reason as filed by the promoterProject is complete in All Aspects - Paining Sanitary fittings & Small Miscellaneous work is pending. Kindly Grant us an Extension for Additional Period of 6 Months i.e upto 30/06/2025 to deliver OC Received Building.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 30 Jun 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 29 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 21 Dec 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed79

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2023-2024)File: Form 2A NEW FORMAT 2023-24.pdf10 Mar 2026
Form 2A (FY 2024-2025)File: Form 2A 2024 -25.pdf10 Mar 2026
Form 5 (FY 2023-2024)File: FY 23-24 FORM 5.pdf10 Mar 2026
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 March 2024.pdf19 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 Jun 2024.pdf19 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 September 2024.pdf19 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 December 2024.pdf19 Feb 2025
Certificates of CA (Form 3)File: Form 3 Dec 2024.pdf6 Feb 2025
CERSAI detailsFile: CERSAI Decl.pdf6 Feb 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: bank account declaration.pdf6 Feb 2025
Certificates of CA (Form 3)File: FORM 3 31032024.pdf5 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FY 18-19 FORM 5.pdf5 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FY 19-20 FORM 5.pdf5 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FY 20-21 FORM 5.pdf5 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FY 21-22 FORM 5.pdf5 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FY 22-23 FORM 5.pdf5 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A NEW FORMAT 2023-24.pdf5 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FY 23-24 FORM 5.pdf5 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 as on 31-3-23 1.pdf27 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 as on 30-6-23 2.pdf27 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 as on 30-9-23 3.pdf27 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 as on 31-12-23 4.pdf27 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 as on 31-3-24 5.pdf27 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 as on 30-6-24 6.pdf27 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 as on 30-9-24 7.pdf27 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 as on 31-12-24 8.pdf27 Jan 2025
Details of encumbrances concerned to FinanceFile: decl finance.pdf25 Jan 2025
Disclosure of sold/ booked inventoryFile: Marigold reality Sold booked.pdf25 Jan 2025
Details of encumbrances concerned to LegalFile: decl finance.pdf25 Jan 2025
Declaration about Commencement CertificateFile: Decl CC.pdf10 Jan 2025
Details of encumbrances concerned to FinanceFile: Non-Encunbrance certificate concerned to legal.pdf21 Dec 2024
Declaration in FORM BFile: Form B.pdf21 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 31-03-19.pdf21 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 31-08-18.pdf21 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 31-03-18.pdf21 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 30-01-18.pdf21 Dec 2024
Commencement Certificates / NA Order for plotted developmentFile: Revalidate CC.pdf21 Dec 2024
Details of encumbrances concerned to LegalFile: Non-Encunbrance certificate concerned to legal.pdf21 Dec 2024
Disclosure for secured/unsecured finance availed for the projectFile: Disclosure for secured unsecured finance.pdf21 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A 30-06-2019.pdf18 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A 31-03-2020.pdf18 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A 30-09-2019.pdf18 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A 31-12-2019.pdf18 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A 30-06-20.pdf18 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A 30-09-2020.pdf18 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A 30-12-2020.pdf18 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A 31-03-2021 (FY 2020-21).pdf18 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A 31-03-2022 (FY 2021-22).pdf18 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 31-03-2023 (FY 2022-23).pdf18 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Form 1 310323 Comp.pdf22 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Form 1 310322.pdf22 Oct 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Interest in other organisations Bharat Prajapati.pdf21 Jun 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 RERA Certificate March 24.pdf4 Apr 2024
Commencement Certificates / NA Order for plotted developmentFile: Full CC Signed Marigold Realty.pdf1 Apr 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Interest in other real estate organisation.pdf4 Oct 2023
Commencement Certificates / NA Order for plotted developmentFile: Marigold Realty CC.pdf25 Nov 2022
Certificates of CA (Form 5)File: RERA CA Certificate Nitun Maru-compressed.pdf16 Jul 2019
Commencement Certificates / NA Order for plotted developmentFile: Miraaya CC 2.pdf14 Jan 2019
Copy of the legal title reportFile: Miraaya Title certificate.pdf30 Jul 2017
Certificates of CA (Form 3)File: RERA CERTIFICATE MARIGOLD12.pdf30 Jul 2017
Certificates of CA (Form 3)File: RERA CERTIFICATE MARIGOLD12.pdf30 Jul 2017
Proforma of Allotment letterFile: Miraaya Agreement.pdf30 Jul 2017
Building plan approvalFile: IOD MIRAAYA FOR RERA.pdf29 Jul 2017
Details of encumbrancesFile: Encumberances Decleration.pdf29 Jul 2017
Building Plan Approval (IOD)File: IOD MIRAAYA FOR RERA.pdf29 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: CC MIRAAYA(1).pdf29 Jul 2017
Declaration in FORM BFile: affidavits cum decleration (1).pdf29 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect CERTIFICATE 260717.pdf29 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Eng certificate 260717.pdf29 Jul 2017
OtherFile: To whom so ever it may concern.pdf29 Jul 2017
Layout approvalFile: Ground Floor Plan.pdf30 Jun 2017
Layout approvalFile: Basement Floor Plan.pdf30 Jun 2017
Layout approvalFile: Section.pdf30 Jun 2017
Layout approvalFile: Block Plan.pdf30 Jun 2017
PAN CardFile: REALTY Pan card_1.pdf30 Jun 2017
Copy of Layout Approval (in case of layout)File: Ground Floor Plan.pdf30 Jun 2017
Copy of Layout Approval (in case of layout)File: Basement Floor Plan.pdf30 Jun 2017
Copy of Layout Approval (in case of layout)File: Section.pdf30 Jun 2017
Copy of Layout Approval (in case of layout)File: Block Plan.pdf30 Jun 2017

How this compares with Mumbai Suburban

33%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 6 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep MARIGOLD MIRAAYA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near MULUND WEST6,700+ in Mumbai Suburban

2 kmMARIGOLD MIRAAYACompleted 104Lapsed / revoked 74Other 142Dot size: filed unitsN

Filed coordinates, straight-line distance. 320 registered projects within 2 km.

Builder: MARIGOLD REALTY

MARIGOLD REALTY has 1 registration on MahaRERA, including MARIGOLD MIRAAYA. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that MARIGOLD MIRAAYA shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if MARIGOLD MIRAAYA is delayed beyond 30 Jun 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of MARIGOLD MIRAAYA?

The registered promoter entity is MARIGOLD REALTY, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in MARIGOLD MIRAAYA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for MARIGOLD MIRAAYA?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at MARIGOLD MIRAAYA?

The professionals named in the filing: Architect: ARCHITECT HAFEEZ CONTRACTOR; Engineer: RAJU NAREJA; Chartered Accountant: NITIN MARU AND ASSOCIATES; Chartered Accountant: ESHA BHANUSHALI AND COMPANY. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MARIGOLD MIRAAYA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MARIGOLD MIRAAYA. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MARIGOLD MIRAAYA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.