MARIGOLD MIRAAYA
RG-MH-08989 · RERA P51800003669 · Last updated on MahaRERA portal: 10 Mar 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 16 months past the filed date
- Completion date moved by 6 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
MARIGOLD MIRAAYA is a Residential / Group Housing project by MARIGOLD REALTY in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800003669 on 6 Aug 2017. Possession was promised by 30 Jun 2025 and is now 16 months past that date. The completion date has moved by 6 months from the original filing. 44 of the 133 units on this registration are recorded sold or booked, and 12 of 22 construction stages are filed complete.
At a glance
Project
- NameMARIGOLD MIRAAYA
- TypeResidential / Group Housing
- Location
- OFF P.K.ROAD
- MULUND WEST
- Kurla
- Mumbai Suburban
- 400080
- Pincode400080
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800003669
- ReraGenie IDRG-MH-08989
Builder
- NameMARIGOLD REALTY
- Entity typePartnership
- PartnerPRANAY SURESH JOGANI
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on6 Aug 2017
- Promised completion30 Jun 2025
- Revised completionRevised to 30 Jun 2025 (originally 30 Dec 2024)
- Buildings2 building records
- Documents filed79 files
Current status
Figures as on 10 Mar 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| MARIGOLD MIRAAYA - A WING | NA | 25 | 19 | 57 | 0 | 57 |
| MARIGOLD MIRAAYA - B WING | NA | 25 | 19 | 76 | 0 | 76 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 10 Mar 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
12 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Internal walls, at 60%.
MARIGOLD MIRAAYA - A WING67%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 60% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 47% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 35% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
MARIGOLD MIRAAYA - B WING67%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 60% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 47% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 35% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 10 Mar 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 50% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 50% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed186
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| MARIGOLD MIRAAYA - A WING | 86 | 0 | 86 |
| MARIGOLD MIRAAYA - B WING | 93 | 7 | 100 |
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| MARIGOLD MIRAAYA - A WING | NA | Rs 27.50 cr | Rs 213.81 cr |
| MARIGOLD MIRAAYA - B WING | NA | Rs 27.50 cr | Rs 213.81 cr |
| - | NA | Rs 5.00 cr | - |
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | ARCHITECT HAFEEZ CONTRACTOR |
| Engineer | RAJU NAREJA |
| Chartered Accountant | NITIN MARU AND ASSOCIATES |
| Chartered Accountant | ESHA BHANUSHALI AND COMPANY |
| Partner | Role in project |
|---|---|
| MARIGOLD REALTY | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterProject is complete in All Aspects - Paining Sanitary fittings & Small Miscellaneous work is pending. Kindly Grant us an Extension for Additional Period of 6 Months i.e upto 30/06/2025 to deliver OC Received Building.
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 30 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 30 Jun 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 29 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 21 Dec 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed79
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 2A (FY 2023-2024)File: Form 2A NEW FORMAT 2023-24.pdf | 10 Mar 2026 |
| Form 2A (FY 2024-2025)File: Form 2A 2024 -25.pdf | 10 Mar 2026 |
| Form 5 (FY 2023-2024)File: FY 23-24 FORM 5.pdf | 10 Mar 2026 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 March 2024.pdf | 19 Feb 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 Jun 2024.pdf | 19 Feb 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 September 2024.pdf | 19 Feb 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 December 2024.pdf | 19 Feb 2025 |
| Certificates of CA (Form 3)File: Form 3 Dec 2024.pdf | 6 Feb 2025 |
| CERSAI detailsFile: CERSAI Decl.pdf | 6 Feb 2025 |
| Declaration about all RERA Designated Bank Accounts (Format A)File: bank account declaration.pdf | 6 Feb 2025 |
| Certificates of CA (Form 3)File: FORM 3 31032024.pdf | 5 Feb 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FY 18-19 FORM 5.pdf | 5 Feb 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FY 19-20 FORM 5.pdf | 5 Feb 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FY 20-21 FORM 5.pdf | 5 Feb 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FY 21-22 FORM 5.pdf | 5 Feb 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FY 22-23 FORM 5.pdf | 5 Feb 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A NEW FORMAT 2023-24.pdf | 5 Feb 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FY 23-24 FORM 5.pdf | 5 Feb 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 as on 31-3-23 1.pdf | 27 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 as on 30-6-23 2.pdf | 27 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 as on 30-9-23 3.pdf | 27 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 as on 31-12-23 4.pdf | 27 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 as on 31-3-24 5.pdf | 27 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 as on 30-6-24 6.pdf | 27 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 as on 30-9-24 7.pdf | 27 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 as on 31-12-24 8.pdf | 27 Jan 2025 |
| Details of encumbrances concerned to FinanceFile: decl finance.pdf | 25 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Marigold reality Sold booked.pdf | 25 Jan 2025 |
| Details of encumbrances concerned to LegalFile: decl finance.pdf | 25 Jan 2025 |
| Declaration about Commencement CertificateFile: Decl CC.pdf | 10 Jan 2025 |
| Details of encumbrances concerned to FinanceFile: Non-Encunbrance certificate concerned to legal.pdf | 21 Dec 2024 |
| Declaration in FORM BFile: Form B.pdf | 21 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 31-03-19.pdf | 21 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 31-08-18.pdf | 21 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 31-03-18.pdf | 21 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 30-01-18.pdf | 21 Dec 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: Revalidate CC.pdf | 21 Dec 2024 |
| Details of encumbrances concerned to LegalFile: Non-Encunbrance certificate concerned to legal.pdf | 21 Dec 2024 |
| Disclosure for secured/unsecured finance availed for the projectFile: Disclosure for secured unsecured finance.pdf | 21 Dec 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A 30-06-2019.pdf | 18 Dec 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A 31-03-2020.pdf | 18 Dec 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A 30-09-2019.pdf | 18 Dec 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A 31-12-2019.pdf | 18 Dec 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A 30-06-20.pdf | 18 Dec 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A 30-09-2020.pdf | 18 Dec 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A 30-12-2020.pdf | 18 Dec 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A 31-03-2021 (FY 2020-21).pdf | 18 Dec 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A 31-03-2022 (FY 2021-22).pdf | 18 Dec 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 31-03-2023 (FY 2022-23).pdf | 18 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Form 1 310323 Comp.pdf | 22 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Form 1 310322.pdf | 22 Oct 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Interest in other organisations Bharat Prajapati.pdf | 21 Jun 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 RERA Certificate March 24.pdf | 4 Apr 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: Full CC Signed Marigold Realty.pdf | 1 Apr 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Interest in other real estate organisation.pdf | 4 Oct 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: Marigold Realty CC.pdf | 25 Nov 2022 |
| Certificates of CA (Form 5)File: RERA CA Certificate Nitun Maru-compressed.pdf | 16 Jul 2019 |
| Commencement Certificates / NA Order for plotted developmentFile: Miraaya CC 2.pdf | 14 Jan 2019 |
| Copy of the legal title reportFile: Miraaya Title certificate.pdf | 30 Jul 2017 |
| Certificates of CA (Form 3)File: RERA CERTIFICATE MARIGOLD12.pdf | 30 Jul 2017 |
| Certificates of CA (Form 3)File: RERA CERTIFICATE MARIGOLD12.pdf | 30 Jul 2017 |
| Proforma of Allotment letterFile: Miraaya Agreement.pdf | 30 Jul 2017 |
| Building plan approvalFile: IOD MIRAAYA FOR RERA.pdf | 29 Jul 2017 |
| Details of encumbrancesFile: Encumberances Decleration.pdf | 29 Jul 2017 |
| Building Plan Approval (IOD)File: IOD MIRAAYA FOR RERA.pdf | 29 Jul 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: CC MIRAAYA(1).pdf | 29 Jul 2017 |
| Declaration in FORM BFile: affidavits cum decleration (1).pdf | 29 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect CERTIFICATE 260717.pdf | 29 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Eng certificate 260717.pdf | 29 Jul 2017 |
| OtherFile: To whom so ever it may concern.pdf | 29 Jul 2017 |
| Layout approvalFile: Ground Floor Plan.pdf | 30 Jun 2017 |
| Layout approvalFile: Basement Floor Plan.pdf | 30 Jun 2017 |
| Layout approvalFile: Section.pdf | 30 Jun 2017 |
| Layout approvalFile: Block Plan.pdf | 30 Jun 2017 |
| PAN CardFile: REALTY Pan card_1.pdf | 30 Jun 2017 |
| Copy of Layout Approval (in case of layout)File: Ground Floor Plan.pdf | 30 Jun 2017 |
| Copy of Layout Approval (in case of layout)File: Basement Floor Plan.pdf | 30 Jun 2017 |
| Copy of Layout Approval (in case of layout)File: Section.pdf | 30 Jun 2017 |
| Copy of Layout Approval (in case of layout)File: Block Plan.pdf | 30 Jun 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 79 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep MARIGOLD MIRAAYA on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near MULUND WEST6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 320 registered projects within 2 km.
Eternia Towers A to D
Oberoi Constructions Limited
Bellanza Phase 1 - Wing A, B, C at The Prestig
PRESTIGE MULUND REALTY PRIVATE LIMITED
Atmosphere O2
Atmosphere Realty Pvt Ltd
Bellanza Phase 2 - Wing D, E, F at The Prestig
PRESTIGE MULUND REALTY PRIVATE LIMITED
Forest Hills Ph 1 at The Prestige City
PRESTIGE MULUND REALTY PRIVATE LIMITED
Kalpataru Elitus
Arimas Real Estate Private Limited
See every Mumbai Suburban project, with the district possession charts
Builder: MARIGOLD REALTY
MARIGOLD REALTY has 1 registration on MahaRERA, including MARIGOLD MIRAAYA. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What does it mean that MARIGOLD MIRAAYA shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if MARIGOLD MIRAAYA is delayed beyond 30 Jun 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of MARIGOLD MIRAAYA?
The registered promoter entity is MARIGOLD REALTY, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in MARIGOLD MIRAAYA?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for MARIGOLD MIRAAYA?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at MARIGOLD MIRAAYA?
The professionals named in the filing: Architect: ARCHITECT HAFEEZ CONTRACTOR; Engineer: RAJU NAREJA; Chartered Accountant: NITIN MARU AND ASSOCIATES; Chartered Accountant: ESHA BHANUSHALI AND COMPANY. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in MARIGOLD MIRAAYA?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.