Home / Browse projects / Mumbai Suburban, Maharashtra / MARATHON NEOHILLS 1
MARATHON NEOHILLS 1
By NEXZONE ENERGY UTILITES LLP
RG-MH-44436 · RERA P51800018328 · Last updated on MahaRERA portal: 29 Apr 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 34 months past the filed date
- 1 complaint at MahaRERA
Clear
- No litigation declared
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
MARATHON NEOHILLS 1 is a Residential / Group Housing project by NEXZONE ENERGY UTILITES LLP in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800018328 on 23 Oct 2018. Possession was promised by 30 Dec 2023 and is now 34 months past that date. 1 complaint is on record with the regulator.
At a glance
Project
- NameMARATHON NEOHILLS 1
- TypeResidential / Group Housing
- Location
- L BS ROAD VILLAGE BHANDUP
- BHANDUP TEMBIPADA
- Kurla
- Mumbai Suburban
- 400078
- Pincode400078
- RERA no.P51800018328
- ReraGenie IDRG-MH-44436
Builder
- NameNEXZONE ENERGY UTILITES LLP
- Entity typeCompany
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on23 Oct 2018
- Promised completion30 Dec 2023
- Revised completionNone
- Buildings1 building record
- Documents filed171 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| MARATHON NEOHILLS 1 | NA | 23 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 29 Apr 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
8 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 99%.
MARATHON NEOHILLS 1: 91% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 99% |
| Sanitary Fittings within the flats / premises | 98% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 29 Apr 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 60% |
| Street Lighting | Yes | 75% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed18
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Partner | Role in project |
|---|---|
| NEXZONE ENERGY UTILITES LLP | - |
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC12400206 | Sonam Nandkumar Patil | NEXZONE ENERGY UTILITES LLP | 24/09/2024 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 5 Oct 2018 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 3 Oct 2023 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 29 Jun 2019 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 3 Oct 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 5 Nov 2024
Documents filed171
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 171 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Q4_AC_Form-1_Neohill_2025.pdf | 29 Apr 2025 |
| Certificates of CA (Form 3)File: Form 03 Neohills-1 Rera Certificate Mar 2025 1.pdf | 29 Apr 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2_Engineer's Certificate_NEOHILLS-1-Mar 25.pdf | 29 Apr 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2_Engineer's Certificate_NEOHILLS-1-Mar 25.pdf | 29 Apr 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Q2_AC_Form-1_Neohill_2020.pdf | 11 Feb 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Q3_AC_Form-_Neohill_2018.pdf | 11 Feb 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A Neohills 2 Mar 2021.pdf | 11 Feb 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A Neohills Jun 2021.pdf | 11 Feb 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A Neohills Sep 2021.pdf | 11 Feb 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A Neohills Dec 2021.pdf | 11 Feb 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A Neohills Mar 2022.pdf | 11 Feb 2025 |
| Certificates of CA (Form 3)File: Form 03 Neohills-1 Rera Certificate Dec 2024.pdf | 28 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2_Engineer's Certificate_NEOHILLS-1-Dec 2024.pdf | 28 Jan 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Arc Cert Neohill Sep 2021.pdf | 15 Jan 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Q3_AC_Form-1_Neohill_2024.pdf | 14 Jan 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Arc Cert Neohill Dec 20.pdf | 23 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Arc Cert Neohill jun 20.pdf | 23 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Arc Cert Neohill Mar 19.pdf | 23 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer's Certificate_NEOHILLS-1-Dec 2018.pdf | 23 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer's Certificate_NEOHILLS-1-Mar 2019.pdf | 20 Dec 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A Neohills Dec 2019.pdf | 20 Dec 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A Neohills Mar 2020.pdf | 20 Dec 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A Neohills Mar 2020.pdf | 20 Dec 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A Neohills Sep 2019.pdf | 20 Dec 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A Neohills Jun 2019.pdf | 20 Dec 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A Neohills Mar 2019.pdf | 20 Dec 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A Neohills Dec 2018.pdf | 20 Dec 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A Neohills Sep 2018.pdf | 20 Dec 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A Neohills Jun 2018.pdf | 20 Dec 2024 |
| Certificates of CA (Form 3)File: NEOHILL 1 RERA CERTIFICATE Dec 18.pdf | 7 Dec 2024 |
| Certificates of CA (Form 3)File: MARATHON NEOHILL-1 RERA CERTIFICATE AS ON MAR 2020.pdf | 7 Dec 2024 |
| Certificates of CA (Form 3)File: NEOHILL- 1 RERA CERTI _ SEP 20.pdf | 7 Dec 2024 |
| Certificates of CA (Form 3)File: Nehohills 1_Rera Certi_As on Sept-21.pdf | 7 Dec 2024 |
| Certificates of CA (Form 3)File: Nehohills 1_Rera Certi_As on Dec-21.pdf | 7 Dec 2024 |
| Certificates of CA (Form 3)File: Neohills-1 Rera Certi As On Mar 22.pdf | 7 Dec 2024 |
| Certificates of CA (Form 3)File: Neohills Rera Cert June 23.pdf | 7 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer's Certificate_NEOHILLS-1-Sep 2020.pdf | 7 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer's Certificate_NEOHILLS-1-Dec 2020.pdf | 7 Dec 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 05 Neohills-1 Apr-23-Mar-24.pdf | 11 Nov 2024 |
| Architect’s Certificate on Completion of Project (Form 4)File: Form 4 UT Neohills.pdf | 6 Nov 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC Copy Neohills -23-Aug-24.pdf | 5 Nov 2024 |
| Certificates of CA (Form 3)File: Form 03 Neohills-1 Rera Certificate Sept'24.pdf | 21 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: signedForm 2_Engineer's Certificate_NEOHILLS-1-Sep 2024.pdf | 21 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Q2_AC_Form-1_Neohill_2024.pdf | 14 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: signedQ1_AC_Form-1_Neohill_2024.pdf | 12 Aug 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2_Engineer's Certificate_NEOHILLS-1-June 2024.pdf | 12 Aug 2024 |
| Certificates of CA (Form 3)File: Form 03 Neohills-1 Rera Certificate June 2024.pdf | 12 Aug 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Neohill RERA Eng Certificate MAR 2024.pdf | 27 May 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM-2A NEOHILLS 1_ MAR-2024.pdf | 27 May 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Q4_AC_Form-1_Neohill_2024.pdf | 15 Apr 2024 |
| Certificates of CA (Form 3)File: Form 03 Neohills-1 Rera Certificate Mar 2024.pdf | 15 Apr 2024 |
| Certificates of CA (Form 3)File: Form 03 Neohills-1 Rera Certificate Dec 2023.pdf | 20 Feb 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Q3_AC_Form-1_Neohill_2023.pdf | 25 Jan 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2_Engineer's Certificate_NEOHILLS-1-Dec 23.pdf | 25 Jan 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 Neohills-1 Rera Certificate Apr-22-Mar-23.pdf | 6 Dec 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2_Engineer's Certificate_NEOHILLS-1-Sep 23.pdf | 30 Oct 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 10012022.pdf | 17 Oct 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 06042022.pdf | 17 Oct 2023 |
| Certificates of CA (Form 3)File: NEOHILL1 RERA CERTIDEC 20_compressed.pdf | 17 Oct 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: AC_Form-1_Neohill_2023.pdf | 13 Oct 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: AC_Form-1_Neohill_2023.pdf | 13 Oct 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: AC_Form-1_Neohill_2023.pdf | 13 Oct 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: AC_Form-1_Neohill_2023 Revised.pdf | 4 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: QUARTER-1-2020.pdf | 4 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: QUARTER-1-2020.pdf | 4 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: QUARTER-3-2020.pdf | 4 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: QUARTER-4-2022-23.pdf | 4 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: [Untitled]_0410202313583100.pdf | 4 Oct 2023 |
| Certificates of CA (Form 3)File: Form 3 NZEN June23.pdf | 4 Oct 2023 |
| Proforma of Agreement for saleFile: AFS Neohills1 28022023.pdf | 4 Oct 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: [Untitled]_0410202313573500.pdf | 4 Oct 2023 |
| Layout approvalFile: 18th Aug 2021 Amended IOA.pdf | 3 Oct 2023 |
| Copy of Layout Approval (in case of layout)File: 18th Aug 2021 Amended IOA.pdf | 3 Oct 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: Sale Bldg Re-endorse CC.pdf | 3 Oct 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: Full CC 310222.pdf | 3 Oct 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Eng Certificate_NEOHILLS-1-Sep19.pdf | 30 Sep 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer's Certificate_NEOHILLS-1-Dec 2020.pdf | 30 Sep 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer's Certificate_NEOHILLS-1-Dec18.pdf | 30 Sep 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer's Certificate_NEOHILLS-1-Dec19.pdf | 30 Sep 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer's Certificate_NEOHILLS-1-Jun19.pdf | 30 Sep 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- All 171 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep MARATHON NEOHILLS 1 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near BHANDUP TEMBIPADA6,700+ in Mumbai Suburban
Runwal Forests Tower 9 - 11
Wheelabrator Alloy Castings Limited
SHRADDHA VARDAAN
SHRADDHA LANDMARK PRIVATE LIMITED
SHRADDHA EVOQUE
SHRADDHA LANDMARK PRIVATE LIMITED
Sugee Vaayu
Sugee Developers Private Limited
SHRADDHA CLASSIC
SHRADDHA LANDMARK PRIVATE LIMITED
Om Siddhivinayak CHS Ltd
Shree Shiv Samarth Reality
See every Mumbai Suburban project, with the district possession charts
Builder: NEXZONE ENERGY UTILITES LLP
NEXZONE ENERGY UTILITES LLP has 1 registration on MahaRERA, including MARATHON NEOHILLS 1. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What does it mean that MARATHON NEOHILLS 1 shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if MARATHON NEOHILLS 1 is delayed beyond 30 Dec 2023?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of MARATHON NEOHILLS 1?
The registered promoter entity is NEXZONE ENERGY UTILITES LLP, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in MARATHON NEOHILLS 1?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against MARATHON NEOHILLS 1?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for MARATHON NEOHILLS 1?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
What should I check before booking in MARATHON NEOHILLS 1?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback