Home / Browse projects / Pune, Maharashtra / Manu

Registered No litigation declared Residential / Group Housing project

Manu

By SHAILESH FATECHAND RANKA

RG-MH-57997 · RERA P52100076863 · Last updated on MahaRERA portal: 16 Jul 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 35 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Mar 2028Possession promisedmoved 35 months from the original
6 of 11Construction stages donefurthest along: Internal walls, 80%
13 of 14Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 114 documents Report an error

Manu is a Residential / Group Housing project by SHAILESH FATECHAND RANKA in Pune, Maharashtra, registered with MahaRERA as P52100076863 on 3 Jul 2024. Possession is promised by 30 Mar 2028. The completion date has moved by 35 months from the original filing. 1 of the 14 units on this registration are recorded sold or booked, and 6 of 11 construction stages are filed complete.

At a glance

Project

  • NameManu
  • TypeResidential / Group Housing
  • Location
    • 8/38+43/1
    • Gultekadi
    • Mukund Nagar
    • Gultekadi
    • Pune City
    • Pune
    • 411037
  • Pincode411037
  • RERA no.P52100076863
  • ReraGenie IDRG-MH-57997

Builder

  • NameSHAILESH FATECHAND RANKA
  • Entity typeIndividual

Key dates

this monthRegisteredJul 2024First promiseApr 2025Revised toMar 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on3 Jul 2024
  • Promised completion30 Mar 2028
  • Revised completionRevised to 30 Mar 2028 (originally 29 Apr 2025)
  • Buildings1 building record
  • Documents filed114 files

Current status

7%1 of 14 units booked
99.8%Work done, per cost certificate

Figures as on 16 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ManuNA8714014

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 16 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 80%.

Manu: 76% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises25%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks70%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%

Progress on shared amenities15

As on 16 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyNoNot applicable
Sewerage (Chamber, Lines, Septic Tank , STP)NoNot applicable
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed31

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots31
Closed/Covered31

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area562 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on18 Jul 2025

Approvals and building plan

Sanctioning authorityPune Municipal Corporation
Permissible FSI2039.45
Proposed, not sanctioned2,039 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGround Floor , Shop No- 1 , A wing , Saishware Apts, CTS - 580 , Narayan Peth , Kelkar Road Pune -41
Estimated costRs 3.20 cr
Cost incurredRs 3.19 cr
Work done99.84%
BuildingWingEstimatedIncurred
ManuNARs 3.20 crRs 3.19 cr

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAMIET PRAKASH NAIK
EngineerAMIET PRAKASH NAIK
Chartered AccountantAMIT SATISH SHANGVI
PartnerRole in project
SHAILESH FATECHAND RANKA-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100028324Apr 2025 → Mar 2026

Reason as filed by the promoterI, Shailesh Fatechand Ranka, aged 42 years, Occupation: Business, residing at Flat No. 601, Arnav Residency, Dr. Gugale Lane, Bund Garden Road, Pune - 411001, am the promoter of the registered project titled "Manu", located at Mukund Nagar, Pune. At the time of project registration, the originally proposed date of completion mentioned in the application was 29/04/2025, based on the sanctioned plan for construction of 3 floors. Subsequently, we have acquired TDR for the project, and are in the process of submitting an application for revised sanction to the competent authority, in accordance wi

EA30032620468Apr 2025 → Mar 2028

Reason as filed by the promoterI, Shailesh Fatechand Ranka, aged 42 years, Occupation: Business, residing at Flat No. 601, Arnav Residency, Dr. Gugale Lane, Bund Garden Road, Pune - 411001, am the promoter of the registered project titled "Manu", located at Mukund Nagar, Pune. At the time of project registration, the originally proposed date of completion mentioned in the application was 29/04/2025, based on the sanctioned plan for construction of 3 floors. Subsequently, we have acquired TDR for the project, and are in the process of submitting an application for revised sanction to the competent authority, in accordance wi

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 19 Feb 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 22 Feb 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 11 Jun 2026
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 19 Feb 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Mar 2028

Documents filed114

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 114 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: FORM 1 QPR JUNE 26.pdf16 Jul 2026
Withdrawal Update Form 2File: FORM 2 QPR JUNE 26.pdf16 Jul 2026
Withdrawal Update Form 3File: FORM-3 MANU CONSTRUCTION.pdf16 Jul 2026
Building plan approvalFile: MANU SANCTION PLAN SHEET 1-2 CC001526.pdf11 Jun 2026
Building plan approvalFile: MANU SANCTION PLAN SHEET 2-2 CC001526.pdf11 Jun 2026
Form 2A (FY 2024-2025)File: form 2A 2025.pdf29 Apr 2026
Form 2A (FY 2025-2026)File: FORM 2A 2026.pdf29 Apr 2026
Withdrawal Update Form 1File: form 1 qpr manu.pdf24 Apr 2026
Withdrawal Update Form 1File: form 1 qpr manu.pdf24 Apr 2026
Withdrawal Update Form 2File: Ranka Form 2.pdf24 Apr 2026
Withdrawal Update Form 2File: Ranka Form 2.pdf24 Apr 2026
Withdrawal Update Form 3File: form 3 Qpr Ranka.pdf24 Apr 2026
Withdrawal Update Form 3File: form 3 Qpr Ranka.pdf24 Apr 2026
Form 5 (FY 2025-2026)File: FORM 5.pdf24 Apr 2026
Form 5 (FY 2024-2025)File: FORM 5.pdf24 Apr 2026
Withdrawal Update Form 1File: form 1 ranka qpr 2026.pdf30 Jan 2026
Withdrawal Update Form 1File: form 1 ranka qpr 2026.pdf30 Jan 2026
Withdrawal Update Form 1File: form 1 ranka qpr 2026.pdf30 Jan 2026
Withdrawal Update Form 1File: form 1 ranka qpr 2026.pdf30 Jan 2026
Withdrawal Update Form 1File: form 1 ranka qpr 2026.pdf30 Jan 2026
Withdrawal Update Form 2File: form 2 ranka qpr.pdf30 Jan 2026
Withdrawal Update Form 2File: form 2 ranka qpr.pdf30 Jan 2026
Withdrawal Update Form 2File: form 2 ranka qpr.pdf30 Jan 2026
Withdrawal Update Form 2File: form 2 ranka qpr.pdf30 Jan 2026
Withdrawal Update Form 2File: form 2 ranka qpr.pdf30 Jan 2026
Withdrawal Update Form 3File: form 3 ranka opr.pdf30 Jan 2026
Withdrawal Update Form 3File: form 3 ranka opr.pdf30 Jan 2026
Withdrawal Update Form 3File: form 3 ranka opr.pdf30 Jan 2026
Withdrawal Update Form 3File: form 3 ranka opr.pdf30 Jan 2026
Withdrawal Update Form 3File: form 3 ranka opr.pdf30 Jan 2026
Withdrawal Update Form 1File: form 1 ranka qpr.pdf30 Oct 2025
Withdrawal Update Form 1File: form 1 ranka qpr.pdf30 Oct 2025
Withdrawal Update Form 2File: form 2 ranka .pdf30 Oct 2025
Withdrawal Update Form 2File: form 2 ranka .pdf30 Oct 2025
Withdrawal Update Form 3File: form 3 ranka qpr.pdf30 Oct 2025
Withdrawal Update Form 3File: form 3 ranka qpr.pdf30 Oct 2025
Withdrawal Update Form 1File: form 1 architect certi qpr july 25.pdf21 Jul 2025
Withdrawal Update Form 1File: form 1 architect certi qpr july 25.pdf21 Jul 2025
Withdrawal Update Form 1File: form 1 architect certi qpr july 25.pdf21 Jul 2025
Withdrawal Update Form 2File: form 2 engineer certi qpr july 25.pdf21 Jul 2025
Withdrawal Update Form 2File: form 2 engineer certi qpr july 25.pdf21 Jul 2025
Withdrawal Update Form 2File: form 2 engineer certi qpr july 25.pdf21 Jul 2025
Withdrawal Update Form 3File: form 3 qpr july 25 Ca Certi.pdf21 Jul 2025
Withdrawal Update Form 3File: form 3 qpr july 25 Ca Certi.pdf21 Jul 2025
Withdrawal Update Form 3File: form 3 qpr july 25 Ca Certi.pdf21 Jul 2025
Form 2File: engineer apr 25 qpr.pdf19 Jul 2025
Form 3File: Form 3-Q4 2024-25 ca.pdf19 Jul 2025
Form 1File: architect apr 25 qpr .pdf19 Jul 2025
Disclosure of Sold and Booked InventoryFile: sold unslod apr 25 qpr.pdf19 Jul 2025
Self-declaration of Quarterly ProgressFile: declaration for extention rera.pdf19 Jul 2025
OthersFile: consent Extention.pdf19 Jul 2025
Form 1File: form 1 2 nd qpr.pdf19 Jul 2025
Form 2File: form 2 2 nd qpr.pdf19 Jul 2025
Form 3File: OPR DEC 24.pdf19 Jul 2025
Disclosure of Sold and Booked InventoryFile: inventory 2 nd qpr .pdf19 Jul 2025
Withdrawal Update Form 1File: form 1 architect certi qpr july 25.pdf19 Jul 2025
Withdrawal Update Form 2File: form 2 engineer certi qpr july 25.pdf19 Jul 2025
Withdrawal Update Form 3File: form 3 qpr july 25 Ca Certi.pdf19 Jul 2025
Declaration in FORM BFile: form b extention.pdf30 Apr 2025
Details of encumbrances concerned to FinanceFile: LEGAL AND FINCANCE DECLRAE QPR 25.pdf28 Apr 2025
Details of encumbrances concerned to FinanceFile: LEGAL AND FINCANCE DECLRAE QPR 25.pdf28 Apr 2025
Details of encumbrances concerned to LegalFile: LEGAL AND FINCANCE DECLRAE QPR 25.pdf28 Apr 2025
Details of encumbrances concerned to LegalFile: LEGAL AND FINCANCE DECLRAE QPR 25.pdf28 Apr 2025
Disclosure for secured/unsecured finance availed for the projectFile: finance encumbrance qpr apr 25.pdf28 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect apr 25 qpr .pdf25 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3-Q4 2024-25 ca.pdf25 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engineer apr 25 qpr.pdf25 Apr 2025
Disclosure of sold/ booked inventoryFile: sold unslod apr 25 qpr.pdf25 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: OPR DEC 24.pdf4 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 SECOND QUARTER DEC 24.pdf4 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1 2 nd qpr.pdf29 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 2 nd qpr.pdf29 Jan 2025
Disclosure of sold/ booked inventoryFile: inventory 2 nd qpr .pdf29 Jan 2025
Other - FinanceFile: DocScanner 30-Oct-2024 3-19 pm (2).pdf30 Oct 2024
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: DocScanner 30-Oct-2024 3-19 pm (2).pdf30 Oct 2024
Details of encumbrances concerned to FinanceFile: legal and finance 3 month.pdf28 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: new engineer 3 month.pdf28 Oct 2024
Details of encumbrances concerned to LegalFile: legal and finance 3 month.pdf28 Oct 2024
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: bank ranka form b.pdf28 Oct 2024
Details of encumbrances concerned to FinanceFile: LEGAL ENCUMBRANCE QUARTERLY.pdf25 Oct 2024

How this compares with Pune

7%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 35 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Manu on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Mukund Nagar13,700+ in Pune

Builder: SHAILESH FATECHAND RANKA

SHAILESH FATECHAND RANKA has 1 registration on MahaRERA, including Manu. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Manu is delayed beyond 30 Mar 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Manu?

The registered promoter entity is SHAILESH FATECHAND RANKA, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Manu?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Manu?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Manu?

The professionals named in the filing: Architect: AMIET PRAKASH NAIK; Engineer: AMIET PRAKASH NAIK; Chartered Accountant: AMIT SATISH SHANGVI. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Manu?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Manu. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Manu to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.