Home / Browse projects / Pune, Maharashtra / MANTRA INSIGNIA PHASE 2

Completed No litigation declared Residential / Group Housing project

MANTRA INSIGNIA PHASE 2

By MANTRA INSIGNIA LLP

RG-MH-99992 · RERA P52100016894 · Last updated on MahaRERA portal: 13 Oct 2023

Source: official MahaRERA filing

Red flags

  • 4 complaints at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2024Possession promisedregistration recorded completed
22 of 22Construction stages doneacross 2 buildings; every applicable stage filed complete
4Complaints at MahaRERAon this registration
Jump to the 99 documents Report an error

MANTRA INSIGNIA PHASE 2 is a Residential / Group Housing project by MANTRA INSIGNIA LLP in Pune, Maharashtra, registered with MahaRERA as P52100016894 on 22 Jun 2018. The registration is recorded completed; possession was promised by 30 Dec 2024. 4 complaints are on record with the regulator.

At a glance

Project

  • NameMANTRA INSIGNIA PHASE 2
  • TypeResidential / Group Housing
  • Location
    • KESHAVNAGAR
    • Keshavnagar-Mundwa
    • Pune City
    • Pune
    • 411036
  • Pincode411036
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100016894
  • ReraGenie IDRG-MH-99992

Builder

  • NameMANTRA INSIGNIA LLP
  • Entity typePartnership
  • PartnersMANTRA PROPERTIES AND DEVELOPERS PRIVATE LIMITED THROUGH ITS DIRECTOR ROHIT GHANSHYAM GUPTA, ASHISH SATISH GUPTA
  • Other registrations4 more →
  • Completed5 of 5

Key dates

this monthRegisteredJun 2018PromisedDec 2024Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on22 Jun 2018
  • Promised completion30 Dec 2024
  • Revised completionNone
  • Buildings2 building records
  • Documents filed99 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUILDING CNA240000
BUILDING DNA240000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 13 Oct 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

22 of 22 construction stages are filed complete across 2 buildings.

BUILDING C100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
BUILDING D100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 13 Oct 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%

Parking filed195

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots195
Closed/Covered117
Open Space78
BuildingClosed/CoveredOpen SpaceTotal
BUILDING C6354117
BUILDING D542478

Land and ownership7

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area5,261 sq m
Land owned byThe promoter, with other names on the file
Named landowners7
LandownerVillageDistrict
MOTOSHREE MALKAI COOPERATIVE SOCIETYMundhawaPune
ASHOK SHIVAJIRAO BHOSALEMundhawaPune
KASHINATH SHIVAJIRAO BHOSALEMundhawaPune
BHALCHANDRA SHIVAJIRAO BHOSALEMundhawaPune
SUNITA VITTHALJADHAVPimpale GuravPune
SULOCHANA DAGADU JADHAVMundhawaPune
VAIJYANTA SHIVAJIRAO BHOSALE-Pune

Approvals and building plan

Permissible FSI14753.27
Proposed, not sanctioned14,753 sq m
Buildings approved2
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSENAPATI BAPAT ROAD

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMITESH SIDHPURA
PartnerRole in project
MANTRA INSIGNIA LLP-

Litigation declared1

CaseCourtStatus
1/2017/2017SDO PUNE CITYAppeal is Pending

Complaints filed with MahaRERA4

Case no.ComplainantRespondentFiled
CC005000000471404RAVI JAINM/S MANTRA INSIGNIA LLP30/07/2024
CC005000000471418SANJEEV RAGHUWANSHIM/S MANTRA INSIGNIA LLP01/08/2024
CC12400464Brajesh SharmaMANTRA INSIGNIA LLP19/10/2024
CC12501500Aniket Sitaram BidaveMANTRA INSIGNIA LLP06/05/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 16 Jun 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 13 Dec 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 13 Dec 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 16 Jun 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 13 Oct 2023

Documents filed99

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 99 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Completion cert.pdf13 Oct 2023
Architect’s Certificate on Completion of Project (Form 4)File: Form 4 Phase 2.pdf13 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Insignia_Phase 2_17-18.pdf25 Sep 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Insignia_Phase 2 Resi_FORM 5.pdf29 Aug 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A Ph 2.pdf3 Aug 2023
Disclosure of sold/ booked inventoryFile: Sold Unsold Ph 2.pdf19 Jul 2023
Certificates of CA (Form 3)File: CA Cert Ph 2.pdf19 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arc Cert Ph 2.pdf17 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Eng Cert Ph 2.pdf17 Jul 2023
CERSAI detailsFile: CERSAI Search Report Mantra Insignia.pdf18 May 2023
Details of encumbrancesFile: Insignia_Phase 2_Finance encumbrances.pdf15 May 2023
Certificates of CA (Form 3)File: CA Cert Insignia Ph 2.pdf20 Apr 2023
Disclosure of sold/ booked inventoryFile: Sold Unsold Ph 2.pdf19 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arc Cert Ph 2.pdf18 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Eng Cert Ph 2.PDF18 Apr 2023
Status of Formation of Legal Entity (Society/Co Op etc.)File: MANTRA INSIGNIA PH 2.pdf20 Mar 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arc Cert C D Building.pdf13 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Eng Cert C D Building.pdf13 Feb 2023
Disclosure of sold/ booked inventoryFile: Sold Unsold C D building.pdf13 Feb 2023
Certificates of CA (Form 3)File: CA Cert C D Building.pdf13 Feb 2023
Details of encumbrances concerned to FinanceFile: LEGAL ENCUMB.pdf10 Jan 2023
Details of encumbrancesFile: FINANCE ENCUMB.pdf10 Jan 2023
Details of encumbrances concerned to LegalFile: LEGAL ENCUMB.pdf10 Jan 2023
Proforma of Agreement for saleFile: ATS.pdf10 Jan 2023
Proforma of Allotment letterFile: Allotment Letter Insignia.pdf10 Jan 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: bANK DECLARATION.pdf10 Jan 2023
Deviation Report with respect to Allotment letterFile: DEVIATION ALLOTMENT.pdf10 Jan 2023
Deviation Report with respect to model copy of AgreementFile: DEVIATION ATS.pdf10 Jan 2023
Layout approvalFile: Layout Plan_compressed (3).pdf13 Dec 2022
Building plan approvalFile: 10 C wing compressed.pdf13 Dec 2022
Building plan approvalFile: 11 C wing compressed.pdf13 Dec 2022
Building plan approvalFile: 13 D wing compressed.pdf13 Dec 2022
Copy of Layout Approval (in case of layout)File: Layout Plan_compressed (3).pdf13 Dec 2022
Building Plan Approval (IOD)File: 10 C wing compressed.pdf13 Dec 2022
Building Plan Approval (IOD)File: 11 C wing compressed.pdf13 Dec 2022
Building Plan Approval (IOD)File: 13 D wing compressed.pdf13 Dec 2022
Declaration about Commencement CertificateFile: CC.pdf13 Dec 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A_ENG CERT_Phase 2.pdf13 Dec 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Insignia_Phase II Resi.pdf6 Dec 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Mantra Insignia Ph 2.pdf20 Oct 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arc Cert_Ph 2.pdf17 Oct 2022
Certificates of CA (Form 3)File: CA Certificate_Insignia_Phase 2_compressed (1).pdf27 Aug 2022
Disclosure of sold/ booked inventoryFile: Sold Unsold_Ph 2_.pdf13 Jul 2022
Certificates of CA (Form 3)File: CA Cert_Ph 2.pdf13 Jul 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1_ARC CERT_PH2.pdf7 Apr 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2_ENG CERT_PH2_final.pdf7 Apr 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A_ENG CERT_Phase 2.pdf7 Apr 2022
Disclosure of sold/ booked inventoryFile: SOLD_UNSOLD_PH2_C,D BUILDING_compressed.pdf7 Apr 2022
Certificates of CA (Form 3)File: FORM 3_CA CERT_PH2_compressed.pdf7 Apr 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT_PH2.pdf8 Jan 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENG PH 2.pdf8 Jan 2022
Disclosure of sold/ booked inventoryFile: CD MERGE_compressed.pdf8 Jan 2022
CERSAI detailsFile: INSIGNIA_CERSAI.pdf8 Jan 2022
Certificates of CA (Form 3)File: CA CERT PH2_compressed.pdf8 Jan 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: phase 2 c d_compressed.pdf6 Oct 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: RERA Certificates C D wing ENGINEERING.pdf6 Oct 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Rera Quality Insignia Commercial bldg C D.PDF6 Oct 2021
Disclosure of sold/ booked inventoryFile: phase 2_compressed.pdf6 Oct 2021
Certificates of CA (Form 3)File: phase 2_compressed.pdf6 Oct 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: mantra insignia llp form 5 phase -2 19-20.pdf6 Oct 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: mantra insignia llp form 5 phase -2 20-21.pdf6 Oct 2021
Declaration about Commencement CertificateFile: INSIGNIA.pdf4 Oct 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: phase 2 cd architect.pdf19 Aug 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Rera Certificate C D Bldg eng.pdf19 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Insignia phase 2 C D.pdf19 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Insignia phase 2 E wing.pdf19 Aug 2021
Certificates of CA (Form 3)File: INSIGNIA PH 2 CA Certificate_compressed.pdf19 Aug 2021
Disclosure of sold/ booked inventoryFile: Insignia Phase 2_compressed.pdf27 Jul 2021
Disclosure of sold/ booked inventoryFile: Mantra Insignia LLP PH2_compressed.pdf18 Jun 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf25 Nov 2020
Certificates of CA (Form 3)File: CA Certiifcate Mantra Insignia Phase 2 CD building.pdf25 Nov 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Mantra Insignia Phase 2.pdf17 Dec 2019
Building plan approvalFile: 1.pdf2 Apr 2019
Building plan approvalFile: 3.pdf2 Apr 2019
Building plan approvalFile: 7.pdf2 Apr 2019
Building plan approvalFile: 8.pdf2 Apr 2019
Building plan approvalFile: 10.pdf2 Apr 2019
Building plan approvalFile: 11.PDF2 Apr 2019
Building Plan Approval (IOD)File: 1.pdf2 Apr 2019
Building Plan Approval (IOD)File: 3.pdf2 Apr 2019

How this compares with Pune

26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep MANTRA INSIGNIA PHASE 2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near KESHAVNAGAR13,700+ in Pune

2 kmMANTRA INSIGNIA PHASE 2Completed 57Lapsed / revoked 14Other 39Dot size: filed unitsN

Filed coordinates, straight-line distance. 110 registered projects within 2 km.

Builder: MANTRA INSIGNIA LLP

MANTRA INSIGNIA LLP has 5 registrations on MahaRERA, including MANTRA INSIGNIA and MANTRA INSIGNIA COMMERCIAL PHASE 1. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if MANTRA INSIGNIA PHASE 2 is delayed beyond 30 Dec 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of MANTRA INSIGNIA PHASE 2?

The registered promoter entity is MANTRA INSIGNIA LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in MANTRA INSIGNIA PHASE 2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against MANTRA INSIGNIA PHASE 2?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for MANTRA INSIGNIA PHASE 2?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at MANTRA INSIGNIA PHASE 2?

The professionals named in the filing: Architect: MITESH SIDHPURA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MANTRA INSIGNIA PHASE 2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MANTRA INSIGNIA PHASE 2. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MANTRA INSIGNIA PHASE 2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.