By MAJESTIQUE HOUSING LLP

RG-MH-01632 · RERA P52100001192 · Last updated on MahaRERA portal: 20 Apr 2024

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA
  • All 1 earlier projects delivered on promise

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 7 other registrations and every project registered within 2 km.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Apr 2022Possession promisedregistration recorded completed
53 of 55Construction stages doneacross 5 buildings; furthest along: Sanitary Fittings within the flats /..., 70%
0Complaints at MahaRERAon this registration
Jump to the 76 documents Report an error

MANHATTAN is a Residential / Group Housing project by MAJESTIQUE HOUSING LLP in Pune, Maharashtra, registered with MahaRERA as P52100001192 on 27 Jul 2017. The registration is recorded completed; possession was promised by 1 Apr 2022.

At a glance

Project

  • NameMANHATTAN
  • TypeResidential / Group Housing
  • Location
    • Wagholi
    • Haveli
    • Pune
    • 412207
  • Pincode412207
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100001192
  • ReraGenie IDRG-MH-01632

Builder

  • NameMAJESTIQUE HOUSING LLP
  • Entity typePartnership
  • GSTIN27AAVFM6361P1Z8
  • PartnersAMIT ANIL LALWANI, MANISH DWARKADAS MAHESHWARI, BRB REALTY LLP THROUGH NILESH BHATTAD
  • Other registrations7 more →
  • Completed7 of 8
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

this monthRegisteredJul 2017PromisedApr 2022Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on27 Jul 2017
  • Promised completion1 Apr 2022
  • Revised completionNone
  • Buildings5 building records
  • Documents filed76 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ENA140000
FNA140000
A1NA30000
A2NA20000
CLUBHOUSENA30000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building5

As on 20 Apr 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

53 of 55 construction stages are filed complete across 5 buildings. The stage furthest along is Sanitary Fittings within the flats / premises, at 70%.

E100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
F100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
A1100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
A297%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises70%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
CLUBHOUSE91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 20 Apr 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingNoNot applicable

Parking filed119

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots119
Closed/Covered119
BuildingClosed/CoveredTotal
E6161
F5858

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area11,130 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI12776.96
Proposed, not sanctioned12,777 sq m
Buildings approved5
Buildings sanctioned5

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchPUNE

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectARC ATIT ADMULWAR
EngineerJW CONSULTANTS LLP
PartnerRole in project
MAJESTIQUE HOUSING LLP-

Litigation declared1

CaseCourtStatus
6929/2012CIVIL JUDGE JUNIOR DIVISIONPENDING

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 2 Aug 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 16 Jan 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 16 Jan 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 7 May 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 14 Nov 2022

Documents filed76

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: MANHATTAN C ARCHITECT UPDATE 2.pdf20 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: MANHATTAN C RERA ARCHITECT UPDATE 3.pdf20 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 UPDATE 4 PLOT C.pdf20 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 UPDATE 5 PLOT C.pdf20 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: UPDATE 6 FORM 1.pdf20 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: UPDATE 7 FORM 1.pdf20 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: UPDATE 8 FROM 1.pdf20 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: MANHATTAN PLOT C- FORM 1 PHASE 1 UPDATE 9_compressed.pdf20 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: MANHATTAN PLOT C- FORM 1 PHASE1 UPDATE 10_compressed.pdf20 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: MANHATTAN PLOT C FORM 1 PHASE1 UPDATE 11_compressed.pdf20 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: MANHATTAN PLOT C FORM 1 PHASE1 UPDATE 12_compressed.pdf20 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 UPDATE 14_compressed.pdf20 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 1 UPDATE 13.pdf20 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: MANHATTAN C ENGINEER UPDATE 2.pdf20 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: MANHATTAN C RERA ENGINEER UPDATE 3.pdf20 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 UPDATE 4 PLOT C.pdf20 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 UPDATE 5 PLOT C.pdf20 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: UPDATE 6 FORM 2.pdf20 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: UPDATE 7 FORM 2.pdf20 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: UPDATE 8 FORM 2.pdf20 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: MANHATTAN PLOT C- FORM 2 PHASE 1 UPDATE 9.pdf20 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: MANHATTAN PLOT C- FORM 2 PHASE1 UPDATE 10.pdf20 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: MANHATTAN PLOT C FORM 2 PHASE1 UPDATE 11.pdf20 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: MANHATTAN PLOT C FORM 2 PHASE1 UPDATE 12.pdf20 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: MANHATTAN PLOT C FORM 2 PHASE1 UPDATE 13.pdf20 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: MANHATTAN PLOT C FORM 2 PHASE1 UPDATE 14.pdf20 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A PHASE 1 20-21.pdf15 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A PHASE 1 21- 22.pdf15 Apr 2024
Certificates of Architect (Form 4)File: A1.pdf21 Jan 2023
Certificates of Architect (Form 4)File: A2.pdf21 Jan 2023
Certificates of Architect (Form 4)File: E AND F.pdf21 Jan 2023
Certificates of Architect (Form 4)File: H.pdf21 Jan 2023
Disclosure of sold/ booked inventoryFile: Manhattan Bld-E.pdf12 Jan 2023
Disclosure of sold/ booked inventoryFile: Manhattan Bld-F.pdf12 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Majestique Housing LLP Form-5 Phase I.pdf8 Dec 2022
Status of Formation of Legal Entity (Society/Co Op etc.)File: EFG Society Regn.pdf15 Nov 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: A1-FULL.pdf14 Nov 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: A2 COMPLETION -COMPRESSED.pdf14 Nov 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: E-F COMPLETION.pdf14 Nov 2022
Disclosure of sold/ booked inventoryFile: Manhattan E_compressed.pdf18 Jun 2022
Disclosure of sold/ booked inventoryFile: Manhattan F_compressed.pdf18 Jun 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Majestique Housing LLP - Plot-C_compressed.pdf18 Jun 2022
Certificates of CA (Form 5)File: Majestique Housing LLP - Plot C.pdf24 Jun 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Majestique Housing LLP - Plot C.pdf24 Jun 2021
Disclosure of sold/ booked inventoryFile: Tower E.pdf31 May 2021
Disclosure of sold/ booked inventoryFile: Tower F.pdf31 May 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5.pdf18 Dec 2019
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Completion A1 and Club house.pdf10 Aug 2019
Copy of the legal title reportFile: Search Plot C.pdf2 Aug 2019
Proforma of Allotment letterFile: Agreement E and F.pdf2 Aug 2019
Proforma of Allotment letterFile: Part A1 and A2 building.pdf2 Aug 2019
Certificates of Architect (Form 4)File: FORM 4 AND COMPLETION.pdf20 Jul 2019
OtherFile: COMPLETION A1 PART CLUBHOUSE.pdf18 Jul 2019
Form 2AFile: FORM 2A PHASE 1.pdf14 Jun 2019
Commencement Certificates / NA Order for plotted developmentFile: CC REV - Copy.pdf7 May 2019
Layout approvalFile: MANHATTAN PLOT C 1-150.pdf16 Jan 2019
Building plan approvalFile: MANHATTAN PLOT C 8-15.pdf16 Jan 2019
Building plan approvalFile: MANHATTAN PLOT C 9-15.pdf16 Jan 2019
Copy of Layout Approval (in case of layout)File: MANHATTAN PLOT C 1-150.pdf16 Jan 2019
Building Plan Approval (IOD)File: MANHATTAN PLOT C 8-15.pdf16 Jan 2019
Building Plan Approval (IOD)File: MANHATTAN PLOT C 9-15.pdf16 Jan 2019
Certificates of CA (Form 5)File: Maiestique Housing LLP - Plot-C.PDF15 Oct 2018
Details of encumbrancesFile: Revised Encumbrances.pdf13 Aug 2018
Declaration in FORM BFile: Form B.pdf20 Jul 2017
Certificates of CA (Form 3)File: FORM 3_CA CERTIFICATE_MANHATTAN PLOT C.pdf18 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Eng Certificate_Manhattan Plot C.pdf15 Jul 2017
Proforma of Allotment letterFile: Manhattan Plot C.pdf15 Jul 2017
Details of encumbrancesFile: No Encum Manhattan Plot C.pdf10 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: _Form_1.pdf4 Jul 2017
Layout approvalFile: Majestique Manhattan-Plot C-Sheet no-010.pdf1 Jul 2017
Building plan approvalFile: Majestique Manhattan-Plot C-Sheet no-010.pdf1 Jul 2017
Copy of Layout Approval (in case of layout)File: Majestique Manhattan-Plot C-Sheet no-010.pdf1 Jul 2017
Building Plan Approval (IOD)File: Majestique Manhattan-Plot C-Sheet no-010.pdf1 Jul 2017
Copy of the legal title reportFile: STR_PLOT_C_MANHATTAN.pdf26 Jun 2017
Commencement Certificates / NA Order for plotted developmentFile: Commencement -PLOT -C.pdf26 Jun 2017
PAN CardFile: M Housing LLp Pan.pdf14 Jun 2017

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationStatusPromisedDelivered
--CompletedDec 2020Dec 2020

How this compares with Pune

26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep MANHATTAN on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Wagholi13,700+ in Pune

2 kmMANHATTANCompleted 67Lapsed / revoked 27Other 44Dot size: filed unitsN

Filed coordinates, straight-line distance. 138 registered projects within 2 km.

Builder: MAJESTIQUE HOUSING LLP

Majestique Housing LLP has 8 registrations on MahaRERA, including Manhattan and MANHATTAN. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if MANHATTAN is delayed beyond 1 Apr 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of MANHATTAN?

The registered promoter entity is MAJESTIQUE HOUSING LLP, a partnership as per the filing. Its GSTIN 27AAVFM6361P1Z8 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in MANHATTAN?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for MANHATTAN?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at MANHATTAN?

The professionals named in the filing: Architect: ARC ATIT ADMULWAR; Engineer: JW CONSULTANTS LLP. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MANHATTAN?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MANHATTAN. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MANHATTAN to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.