Home / Browse projects / Pune, Maharashtra / Mangalam Icon

Completed Litigation declared Residential / Group Housing project

Mangalam Icon

By Ramdas Damodar Phuge proprietor of Bhagyalaxmi Construction

RG-MH-21528 · RERA P52100029682 · Last updated on MahaRERA portal: 4 Mar 2025

Source: official MahaRERA filing

Red flags

  • Litigation declared, 5 cases
  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jun 2025Possession promisedregistration recorded completed
5 of 11Construction stages donefurthest along: Internal walls, 80%
41 of 47Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 56 documents Report an error

Mangalam Icon is a Residential / Group Housing project by Ramdas Damodar Phuge proprietor of Bhagyalaxmi Construction in Pune, Maharashtra, registered with MahaRERA as P52100029682 on 26 Jun 2021. The registration is recorded completed; possession was promised by 29 Jun 2025. The completion date has moved by 12 months from the original filing. 6 of the 47 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete.

At a glance

Project

  • NameMangalam Icon
  • TypeResidential / Group Housing
  • Location
    • Sector 3 Plot no 65/3 Bhosari PCNTDA Pune
    • Bhosari
    • Haveli
    • Pune
    • 411039
  • Pincode411039
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100029682
  • ReraGenie IDRG-MH-21528

Builder

  • NameRamdas Damodar Phuge proprietor of Bhagyalaxmi Construction
  • Entity typeIndividual
  • GSTIN27AHHPP4297J1ZP

Key dates

this monthRegisteredJun 2021First promiseJun 2024Revised toJun 2025Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on26 Jun 2021
  • Promised completion29 Jun 2025
  • Revised completionRevised to 29 Jun 2025 (originally 30 Jun 2024)
  • Buildings1 building record
  • Documents filed56 files

Current status

13%6 of 47 units booked
66.2%Work done, per cost certificate

Figures as on 4 Mar 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Building ANA7042547

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 4 Mar 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 80%.

Building A: 64% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises2%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks70%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 4 Mar 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed10

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots10
Closed/Covered10

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,706 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on27 Sep 2024
LandownerVillageDistrict
Shivsmit AssociatesBhosariPune

Approvals and building plan

Sanctioning authorityPimpri Chinchwad Muncipal Corporation
Permissible FSI4847.7
Proposed, not sanctioned4,352 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchShree Ganesh Plaza Hinjawadi Pune 411057
Estimated costRs 10.11 cr
Cost incurredRs 6.69 cr
Work done66.21%
BuildingWingEstimatedIncurred
Building ANARs 9.56 crRs 6.27 cr
-NARs 55.00 lakhRs 42.25 lakh

Certifying professionals and partners8

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectArchitect Vipul Pagariya
ArchitectVIPUL PAGARIYA
EngineerHitesh Lahoti Structural Engineers
EngineerVikrant Gavhane
Chartered AccountantVSAP and Company
Chartered AccountantAmruta Shinde and Associates
Chartered AccountantVikas Khadsare
Chartered AccountantAmruta Shinde
PartnerRole in project
Ramdas Damodar Phuge proprietor of Bhagyalaxmi Construction-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100019802Jun 2024 → Jun 2025

Reason as filed by the promoter(1)Due to Global pandemic labours at site were not available also material was not available due to that construction work was very slow. (2)Due to Global Pandemic Covid-19 sales of flats was very slow that also affected speed of construction. (3)Due to lockdown 2 in year 2021 our construction completion got delayed and due to that we were unable to complete works and get PCMC completion certificate.

Litigation declared5

CaseCourtStatus
879/2011Honarable Civil Senior Judge Civil DivisionPending in court
200879/2011/2011Civil Court PuneHearing
555/2024/2024Civil Court PuneHearing
200879/2011/2011Civil Court PuneOngoing
2764/2024/2024Civil courtOngoing

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 21 Jun 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 6 May 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 6 May 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 6 May 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 4 Mar 2025

Documents filed56

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Corrected Fom 4 with completion certificate.pdf4 Mar 2025
Architect’s Certificate on Completion of Project (Form 4)File: Form 4 with Full OC.pdf24 Dec 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Form 4 with Full OC.pdf24 Dec 2024
Other - TechnicalFile: Form 4 with Full OC.pdf24 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 melizma upto sept 2024.pdf18 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 2023to2024.pdf18 Oct 2024
Declaration about Commencement CertificateFile: Declaration of CC.pdf23 May 2024
Declaration in FORM BFile: Self declaration Form B Icon for extension.pdf23 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM2A 21TO22.pdf23 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM2A 22TO23.pdf23 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM2A 23TO24.pdf23 May 2024
Disclosure of sold/ booked inventoryFile: DOSU 31032024.pdf23 May 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: DOInterest Ram sir.pdf23 May 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Seperate bank letter.pdf23 May 2024
Details of encumbrances concerned to FinanceFile: Encumbrances letter.pdf21 May 2024
Details of encumbrances concerned to LegalFile: Encumbrances letter.pdf21 May 2024
CERSAI detailsFile: Cersai declaration.pdf21 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Icon Form 2 Sept 2023.pdf20 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Icon Form 2 Dec 2023.pdf20 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Icon Form 2 March 2024.pdf20 May 2024
Proforma of Agreement for saleFile: MODEL AGREEMENT TO SALE.pdf20 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: M ICON FORM 3 MARCH 2024compressed.pdf7 May 2024
Layout approvalFile: Sanctioned Plan 1 compressed.pdf6 May 2024
Layout approvalFile: Building Plans 1 .pdf6 May 2024
Building plan approvalFile: Sanctioned Plan 1 compressed.pdf6 May 2024
Building plan approvalFile: Building Plans 1 .pdf6 May 2024
Copy of Layout Approval (in case of layout)File: Sanctioned Plan 1 compressed.pdf6 May 2024
Copy of Layout Approval (in case of layout)File: Building Plans 1 .pdf6 May 2024
Building Plan Approval / NA Order for plotted developmentFile: Sanctioned Plan 1 compressed.pdf6 May 2024
Building Plan Approval / NA Order for plotted developmentFile: Building Plans 1 .pdf6 May 2024
Commencement Certificates / NA Order for plotted developmentFile: Revised CC Icon .pdf6 May 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 CA Certificate 22to23.pdf8 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 2MB Form 3 Dec 2023 compressed.pdf2 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA certificate Mangalam Icon 30092023.pdf4 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch Cert Form 1 M Icon Sept 2023.pdf9 Nov 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM5 FY2122.pdf26 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arc-Form 1-30-09-22.pdf24 Nov 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Eng- Certificate-Form-2-30-09-22.pdf24 Nov 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Quality Cert-Form 2A-30-09-22.pdf24 Nov 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate-Form 3-30-09-22.pdf24 Nov 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arc-Cert- Form-1-30-6-2022.pdf31 Oct 2022
Layout approvalFile: Plan Sanction Copy 1.pdf21 Jun 2021
Layout approvalFile: Plan Sanction Copy 2.pdf21 Jun 2021
Copy of the legal title reportFile: 1mb Latest Search Title Report070621.pdf21 Jun 2021
Copy of Layout Approval (in case of layout)File: Plan Sanction Copy 1.pdf21 Jun 2021
Copy of Layout Approval (in case of layout)File: Plan Sanction Copy 2.pdf21 Jun 2021
Declaration about Commencement CertificateFile: Mangalam Icon commencement declaration.pdf21 Jun 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: First CA Certificate.pdf14 Jun 2021
Proforma of Allotment letterFile: MANGALAM ICON RERA DRAFT (1).pdf14 Jun 2021
Proforma of Allotment letterFile: Icon allotment letter download.pdf14 Jun 2021
Building plan approvalFile: Plan Sanction Copy 2.pdf8 Jun 2021
PAN CardFile: New PAN card - Ram Phuge.pdf8 Jun 2021
Details of encumbrancesFile: Encumbrance Mangalam Icon.pdf8 Jun 2021
Building Plan Approval / NA Order for plotted developmentFile: Plan Sanction Copy 2.pdf8 Jun 2021
Commencement Certificates / NA Order for plotted developmentFile: Commencement certificate Mangalam Icon compressed.pdf8 Jun 2021
Declaration in FORM BFile: Form b mangalam icon bhagyalaxmi construction.pdf8 Jun 2021

How this compares with Pune

13%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 12 months
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Mangalam Icon on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Bhosari13,700+ in Pune

2 kmMangalam IconCompleted 23Lapsed / revoked 15Other 15Dot size: filed unitsN

Filed coordinates, straight-line distance. 53 registered projects within 2 km.

Builder: Ramdas Damodar Phuge proprietor of Bhagyalaxmi Construction

Ramdas Damodar Phuge proprietor of Bhagyalaxmi Construction has 1 registration on MahaRERA, including Mangalam Icon. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Mangalam Icon is delayed beyond 29 Jun 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Mangalam Icon?

The registered promoter entity is Ramdas Damodar Phuge proprietor of Bhagyalaxmi Construction, an individual as per the filing. Its GSTIN 27AHHPP4297J1ZP can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Mangalam Icon?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Mangalam Icon?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Mangalam Icon?

The professionals named in the filing: Architect: Architect Vipul Pagariya; Architect: VIPUL PAGARIYA; Engineer: Hitesh Lahoti Structural Engineers; Engineer: Vikrant Gavhane; Chartered Accountant: VSAP and Company; Chartered Accountant: Amruta Shinde and Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Mangalam Icon?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Mangalam Icon. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Mangalam Icon to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.